HomeMy WebLinkAboutSTORYBOOK - PDP - 49-98 - CORRESPONDENCE - REVISIONS3. For a site of this size, it would be more advantageous and accurate to model the
runoff and pond sizing using UDSWM2-PC. Please delineate the site into smaller
subbasins and incorporate the SWMM model into the runoff analysis.
RESPONSE: k)6 leave dome +/,,j �o, fkc t,*4a a.,I 4//0 -4 4. t'
!Z 4f-r EJ 1!11 1 EQrf % f'i' fi'lc . we- '(ij i70-f /I1L / Ae //o 4C✓,OJ
F.J. D . ow'u.
4. The retention pond should be graded and noted as a retention pond. In addition,
please size the retention pond for the 100-year stone with zero release and indicate
the approximate surface area, volume, and allowable release rate on the plans.
RESPONSE:
5. The historic time of concentration has been computed inaccurately. The flow from
north to south across the majority of the basin should be considered as overland flow
and the flow from west to east in the borrow ditch should be considered as
channel/gutter flow. Please recalculate time of concentrations and revise runoff.
RESPONSE: WE- ALL of TH6 H/Iro,eic
6. The composite runoff coefficient assumed for developed conditions is too low.
According to the project development plan, the coefficient should be higher. Please
revise this value as needed.
RESPONSE: W6 CEcALCUIZATEp `C, OK O4fG
and 0.1-T(o- /0o.1,.
7. In any case, ditch owner approval will be needed. In addition, offsite easements from
the site to the Outfall No. 8 will be required. �+
TAe O�><JIf�, CQJe-,e-4.r r-V+ JIfG �O ti0. S EEJervolK G.t
RESPONSE: 1<f d f I k were- j,er e,..e t Se 4,e- P.I-D. bvµ4LF tAi !/o 4,.
R .D. Cv;11 d-ed, c'of - f 4 t OgF.i,'ic e&.re ,elfr. 5tavc(F CVEt1e r<
R57AIA)/NG .4vD A)cT P6L—CAVI r D,7C{� (�J��� D,{�� (y �,a c Fu ✓�j�
8. Water quality still needs to be addressed. The ditch owner requires extended
detention.
RESPONSE: w E A P-e D e rA,,v,.0 c A k/> R C7TAWIAI ) c wHIc y cu11 4__
A D D,e Gsy CIJ A T-E 2
Please refer to the redlined plans and report for additional review comments.
storybook -I .doc
PROJECT
COMMENT SHEET
City of Fort Collins
Current Planningr�
DATE: September 24, 1998 TO: Stormwater Utility
PROJECT: #49-98 Storybook PDP - Type I - LUC
All comments must be received by Steve Olt no later than the staff
review meeting:
Wednesday, October 21, 1998
❑ No Problems
Problems or Concerns (see below or attached)
1. The biggest issue that needs to be addressed is how runoff from this phase will tie in
with future phases and how this phase will tie in with the outfall for the entire
Storybook Farms site. From conceptual review, it was stated that the ditch company
has required double the total retention with a manual release into the canal, so it is
possible to discharge runoff into the canal; the ditch company just has to approve it.
An overall drainage plan is required for the entire Storybook Farms site and all phases
will need to be included somehow.. 1 / / c
._-� b utvl G{Ii�ILti.�� 4 o (OrGP4.YG fAt dA"&'A•,G �P14n
RESPONSE: iio 4'1-ti4- > 44-e- fcZool ])ui'v«f' ow--t. we
etc+r,} o. �0 6.f� yok�rct of J1.e I�p✓yLu•k f'DP. %X� `�.�6 gc.cttC.y
wv Fe rCr v. of �. ke4 e-4�c. o^-4, RI D. PIope✓i, CA. h*--44 1.19A ve beef
e� re }/ o� fo- bofG p6k.11. < /' •Isrp.
2. On the drainage plan, please show the location of all proposed inlets, storm sewers,
crosspans, manholes, riprap protection, and other related storm sewer facilities.
RESPONSE: w E NA✓C ADDED f k e, SA, e- 4—v I A «�- 4-.
Date: to(zo(ovq Signature:
CC --
CHECK HERE IF YO WISH TO RECEIVE COPIES OF REVISIONS
`�it x v�x�+-FAssec. �r
L<Plet Site�X Drainage Report X Oler
Yak 1 `�E Utiq K LS�: P City of Fort Collins
15. Landscape Plan was revised as per red line drawings.
16. All plans have been revised by Stewart & Associates.
17. All sheets are submitted at this time.
18. An additional two foot of right of way has been granted along County Road 11.
19. Fire truck access will be provided at the end of Sherwood Forest Court for
emergency vehicles.
20. Please see revisions on utility plans.
21. The offsite easement for retention pond has been acquired, it is located on the
Northeast corner of the Poudre R-1 Property.
22. See Storm -water Drainage Plan.
23. Native vegetation will be used in the storm water ponds.
24. A revision of the T.I.S. is being done and will be resubmitted.
25. The cul-de-sac connections to the sidewalk along County Road 11 have been
revised.
26. The park site requirement is submitted with this set of drawings.
'd 0-�' ---m A PI�11
5. Elco Water District assured the developer that all hydrants could deliver 1,000
gallons of water per minute at a residual pressure of 20 pounds.
Address numerals will be 6" numbers place under porch lights with a contrasting
background.
6. I met with Doug Martine, with Light and Power Dept. and found that we do have
as easement in place along the south side and the west side of the proposed
development.
Elco Water district indicated they would work with Light and Power Dept. to
keep the two utilities separated.
Once the electrical plan is completed a clearance of 40 feet for street trees will
be observed.
7. Boxelder Sanitation will work out all payback agreements between themselves
and the developer.
8. I met with Kenneth Jackson of Police Dispatch. Two street names were changed,
Robin Hood Lane was changed to Little John Lane and Marian Court was
changed to Maid Marian Court, these changes were approved by Mr. Jackson.
9. Stewart & Associates have made the appropriate changes to storm water utilities,
Please see Utility Plan.
10. All engineering red lines have been changed. Please see Utility Plans.
11. The traffic study is being revised to address alternative modes of transportation.
The street network for Storybook O.D.P. has been removed from the traffic study
and the ground has been sold to the Poudre R-1 School District.
The offsite street improvements for this area will be handled by Matt Baker of the
Street Oversizing Dept.
12. County Road 11 and Mountain Vista Drive will meet current street standards.
13. The Patio Home Association will handle the snow removal on sidewalk along
Little John Lane.
14. I met with Matt Baker, Street Oversizing Dept. and he is handling offsite street
improvements.
IF
NEBARADO CONSTRUCTION, INC.
6804 AARON DRIVE
FORT COLLINS, CO. 80524
Steve Olt, Project Planner
City of Fort Collins
281 North College Ave.
Fort Collins, Co. 80524
Dear Mr. Olt,
n/ala8 1&�
The following are our re22nses to your comments on the proposed Storybook
Development.
The site data was labeled wrong, our units are actually single family attached
units and has been corrected on the site plan.
2. Public Service Company will relocate the existing power lines overhead into
the development as needed with no charge to the developer.
3. On the end of Little John Lane we now have a neighborhood park that con-
sists of a least one acre. All units located within the Storybook Patio Home
P.D.P. are within the 1760 foot boundary.
(c.) Section 3.52(E) (1) states that the garages may be side -loaded. Attached
or detached with a side entry, provided that the side of the garage facing the
street has windows and other detailing that mimic the features of the living
portion of the home. The subdivision in the development plan clearly indicates
which lots have side -loaded garages and which have front loaded garages.
The building elevations that are submitted now are labeled (front, rear, left,
right, front -loaded or side loaded).
Building elevations for Lots 13, 14, 55 & 56 will be our standard patio home
split in half.
Phasing will be done on this project with Phase I being the first 46 lots and
Phase 11 will consist of 28 lots as requested by Storm -water Drainage Dept.
4. Elco Water District submitted red lined drawings and all changes have been
made.