Erosion
Control
Cost Estimate
Project Number: 947-002
Location: Fort Collins, CO
Date: January 20, 2016
Total Acres: 2.40
Lstimated Unito
a
EROSION CONTROL MEASURE
Units
Quantity Price
Price
Silt Fencing
L.F.
0 $1.50
$0.00
Construction Fence w/Rock Sock
L.F.
1296 $4.50
$5,832.00
Inlet Protection
each
18 $75.00
$1,350.00
Wattle Dike Inlet Protection
each
0 $100.00
$0.00
Wattle Dike Curb Side Check Dam
each
0 $75.00
$0.00
Wattle Dike Swale Protection
each
0 $100.00
$0.00
Vehicle Tracking Control Pads
each
1 $300.00
$300.00
Sediment Trap
each
0 $150.00
$0.00
Concrete Washout Area
each
1 $200.00
$200.00
Rock Sock
each
28 $75.00
$2,100.00
Sawcutting Pollution Prevention
L.F.
795 $1.00
$795.00
Street Sweeping and Cleaning
per hour
25 $60.00
$1,500.00
Sub -Total:
$12,077.00
1.5 x Sub -Total:
$18,115.50
Option 1 1 BMP Costs
Amount of security:
$18,115.50
Option 2 Cost to Re -seed Disturbed acreage
Total Acres x $1325/acre:
$3,180.00
Sub -Total:
$3,180.00
1.5 x Sub -Total:
$4,770.00
Cost to Re -seed.
$4,770.00
Option 3
1 Miniumum Escrow Amount
Minimum escrow amount:
$3, 000.00
Erosion Control Escrow:
$18r 115.50
NOTE: 'Total Acres' represents total disturbed area.