Ronald G. Fuchs, Project Planner
Current Planning Division
City of Fort Collins
281 N. College Avenue
Fort Collins, CO 80524
RE: Development Schedule for the Settler's Green Project
Dear Ron,
Due to the small size of the Settler's Green Project the construction of the infrastructure will be done in one
phase of stage. This would include the underground utilities such as water and sewer, the streets, curbs,
gutters, and sidewalks, and finally the landscaping of the greenbelt and path ways.
Expected start date for construction: January 2001
Expected completion date of construction: September 2001