32. See Above
If you have any questions or comments, or need additional information, please do not hesitate
to contact me at (970) 491-9888. Thank you.
Sincerely,
JR Engineering
q D W.
4&WA�-
David W. Klockeman, P.E.
Project Manager
cc: Ms. Janine Walkup, Kaufman & Broad Multi Housing Group
Mr. Mike Marini, Kaufman & Broad Multi Housing Group
Mr. Steve Olt
March 10, 1999
Page 3 of 4
d. Noted.
14. Water/Wastewater — These comments have been addressed with the revised Utility
Plans.
15. Stormwater - These comments have been addressed with the revised Utility Plans and
Drainage Report.
16. Engineering Department — Mark McCallum - These comments have been addressed
with the revised Utility Plans.
17. Transfort — Information only
Stormwater
18. Information has been added to the Utility Plans.
19. The drainage scheme has been revised. The majority of the drainage is surface.
20. The storm sewer has been deleted.
21. This has been addressed in the revised Utility Plans and Drainage Report.
Engineering
22. Additional Right -of -Way and easements have been included on the revised Utility
Plans.
23. The plans have been revised for consistency.
24. Noted.
25. Noted.
26. The traffic circle has been deleted.
Planning
27. Noted.
28. The Ownership has been clarified on the revised plans.
29. Noted.
Transportation Planning
30. See Above
31. See Above
Mr. Steve Olt
March 10, 1999
Page 2 of 4
being addressed by separate letter.
b. The carports do not have dividers between each stall. Therefore, the standard
24 foot drive aisle is being utilized.
C. The request has been changed from an "Alternative Compliance" to a
"Modification".
d. This information has been added.
e. Noted.
f. Noted.
g. The trash enclosures have been enlarged based on information from Natural
Resources.
h. The roundabout has been deleted.
i. There was no Item i.
j. The landscape plan has been revised.
k. Two (2) trash enclosures have been provided.
1. The building placement is such that there are numerous units close to
accessible parking.
M. Carport elevations have been included.
n. Noted. See revised plans.
o. They are 9' by 17'.
8. Light and Power
a. The utility layout has been revised.
b. Noted.
9. Engineering Department — Matt Baker — Street Oversizing Fees — Noted.
10. Utility Education Specialist — Noted
11. City Forester — Noted
12. Transportation Planning
a. A pedestrian connection to Somerset Apartments is not feasible due to no
sidewalks on Somerset west of their buildings as it is the rear of the units with
a 6 foot wood privacy fence along the property line. In addition, the southwest
corner of their site has a detention pond with inadequate room for a pedestrian
connection.
b. Noted.
C. Gaylen has been coordinated with and she did not have any definite plans at
this time.
d. The south entrance will be a full access, not just an emergency access.
13. Natural Resources
a. The trash enclosures have been revised.
b. Noted. (This is the likely scenario.)
C. Noted.
JREngineering, Ltd.
2620 East Prospect Rd. Suite 190
Fort Collins, Colorado 80525
(970) 491-9888 • FAX (970) 491-9984
www.jreng.com
March 10, 1999
Mr. Steve Olt
City of Fort Collins — Current Planning
281 North College Avenue
P.O. Box 580
Fort Collins, Colorado 80522
Re: JFK Senior Apartments — Review Comment Information
Dear Steve:
In order to help clarify some of the items identified in your letter of December 30, 1998, we
offer the following: (The items are identified by number. In the interest of space, we have
not repeated the information presented in your letter.)
1. This item was presented for information only and is noted.
2. Kaufman & Broad will be coordinating with TCI as part of the building permit
process.
3. Kaufman & Broad will be coordinating with US West as part of the building permit
process.
4. Public Service Company
a. The proposed storm sewer has been deleted.
b. The proposed tree locations have been modified.
5. Building Inspections comments will be included in the plans submitted by Kaufman &
Broad for the building permit process.
6. Poudre Fire Authority
a. The driveway will be utilized as the fire lane. A fire service line has been
added to all buildings.
b. This item will be addressed with the building permit.
C. Fire hydrant spacing has been set so that no building is greater than 300 feet
from a hydrant.
d. The turn -about has been deleted.
7. Zoning Department
a. The easement has been moved away from the carports. The parking issue is
4935 North 30th Street 6020 Greenwood Plaza Blvd. 704 Fortino Blvd. West
Colorado Springs, Colorado 80919 Englewood, Colorado 80111 Pueblo, Colorado 81008
(719) 593-2593 • FAX (719) 528-6613 (303) 740-9393 • FAX (303) 721-9019 (719) 583-2575 • FAX (719) 583-8119