HomeMy WebLinkAboutLINDEN PARK - FDP - 62-98C - SUBMITTAL DOCUMENTS - ROUND 1 - REVISIONS (3)♦ Corona North & Red Willow North: The vertical curve was eliminated per the redline
comments.
♦ Corona South & Red Willow South: 2% slope used, riprap shown, and redlines
changed.
TIMBERLINE IMPROVEMENTS
♦ Interim striping and signing, grading and cross -sections were added.
DETAIL
♦ Under drain details added to sheet 38 of 50 for the cleanouts and services.
♦ Under drain notes referencing Sections 2.3 and 3.4 were added to the under drain
cleanout detail on sheet 38.
♦ Mid -Block detail 12.6 was added to detail sheet 40.
PHASING PLAN
♦ Barricades, temporary cul-de-sacs and hydrants were added. Redlines were done.
INTERIM TIMBERLINE RPROVEMENTS
♦ Met with City Engineering, addressed redline comments.
LIGHT & POWER
♦ An agreement between Doug Martine of City Light & Power and the developer has
been reached for the City to acquire the necessary easement to supply this site.
♦ Street trees coordination has been done.
NATURAL RESOURCES
All parties have agreed to the arrangement proposed in the Linden Park plan set.
Currently we are awaiting signature.
♦ Discussed this with Bob Zackley. Plans have been standardized with drainage and
erosion control on sheets 42 & 43. Grading will reference sheets 5 & 6.
♦ Cost changed on the erosion control calculations sheet in the drainage report.
Sincerely,
Kevin Ash, P.E.
TST, INC. CONSULTING ENGINEERS
s J
August 22, 2000
Mr. Ron Fuchs
City of Fort Collins Current Planning
P.O. Box 580
Fort Collins, CO 80522-0580
RE: Linden Park P.D.P.
Project No. 0930-001
Dear Mr. Fuchs:
Enclosed are responses to the City of Fort Collins comment sheets from the review of the
Linden Park P.D.P. submittal on June 6, 2000.
ENGINEERING
GENERAL COMMENTS
♦ Redline comments addressed. See plan set.
♦ Subdrain pipe changed to AASHTO M267-77 or ASTM 3034.
♦ All sheets title changed to "Linden Park Final Compliance Plans
Fort Collins, Colorado'
PLAT
♦ Planning Statement added.
OVERALL UTILITY PLAN
♦ Emergency Access Easement was shown and labeled on previous submittal. We have
know enhanced it.
SANITARY SEWER PLAN & PROFILE
♦ Outfall from the underdrain will add a minimal 0.48 cfs at build out. This will not
affect the 100-year flow event in the channel south of Trilby. This is a repeat
response.
LOCAL STREETS
♦ White Willow Drive: Construction stopped short of property line and 4:1 tie-ins are
now shown.
♦ Fossil Creek Parkway East: Vertical Curves added and Timberline note added.
♦ Prairie Hill Drive West: Mid -Block Ramp Detail added.