HomeMy WebLinkAboutLINDEN PARK (KEATING PROP.) - PDP - 62-98B - CORRESPONDENCE - (3)City of Fort Collins
Date:
To:
From:
Subject:
Commi. ty. Planning and Environmental rvices
Current Planning
October 26, 1999
Greg Byrne
Ronald G. Fuchst�
Linden Park (City File #62-98B)
As requested, this memo outlines a tentative time frame for a project development plan
that was submitted on October 13, 1999, for Linden Park PDP. As noted in our previous
conversations, the application did not include the required Soils Report and the needed
off -site improvement utility plans. The following is a possible schedule to bring this
application to public hearing and through appeal with only two rounds of review. Due to
past experience, three (3) additional weeks may be needed for an additional round of
review. In addition, the applicant's final utility plan mylars may not be ready for final
compliance review following public hearing which may add an additional three (3) weeks
for utility plan review prior to utility plan mylar submittal. It is also important to note that
the applicant's response time frame may alter the below schedule:
10.13.99
Application Submittal
11.10.99
Discuss at Staff Review
11.17.99
Staff Report Sent Out
12.20.99
Second Tier - Revisions Submitted For Review
1.19.00
Second Tier - Discuss at Staff Review
1.26.00
Second Tier - Staff Report Sent Out
2.14.00
Tentative Public Hearing
2.24.00
Decision Document Rendered
3.6.00
Appeal Period Ends
3.27.00
Conditions Met and Document Preparation
4.15.00
Documents Signed and Mylar Recorded
5.1.00
Tentative Ground Breaking
It is our hope to have the project under construction sometime in mid -April.
281 North College Avenue • P.O. Box 580 • Fort Collins, CO 80522-0580 • (970) 221-6750 • FAX (970) 416-2020