HomeMy WebLinkAboutCIVIC CENTER OFFICE BUILDING - PDP - 29-99 - REPORTS - RECOMMENDATION/REPORT W/ATTACHMENTS03/13/2000 11:35
970484"n59
DBA/DDA
:I
PAGE 02
DDA MINUTES
PAGE 8
- kcarch 41 1gCtG
Participate, to request any additional funding ne�-6 sary,4hIis was
seconded by Mr. Slezak and the motion passed with opposition.
LPC UPDATE Angela Milewski provided an update on behalf, of,the Laridmark—
Preservation Commission, and indicated that of recent date six projects
had been awarded funding: four residential and two non residential.
CITY OFFICE UUILDING Returning to the Board a second time to provide an update on the new
City Office Building, City Staff shared that RFP's have gone out, and that
this 70,000 square foot office building is estimated at a cost of `j8.2 million.
It is currently proposed that groundbreaking will begin between April and
July 2000. Site elevation maps and artist renderings were displayed to
explain the plans. In addition to the building, careful thought has been
given to the center of the plaza which is a focal point of the project.
Questions were posed concerning the positioning of the building on the
comer, and there was some discussion about the bike path and pedestrian
Plaza which runs along Mason and LaPorte Streets. The customer
approach Is projected through the parking lot in the center of the
structure, although this is still under discussion. The center door will provide
the formal access, although there will be several other doors by which to
enter the building.
The three story structure lends the Justice Center greater stature, and it has
been designed with optimum flexibility. On entering, a very attractive
rotunda will greet visitors, and provide the information center for the
building.
STAFF CONTRACTS Staff contracts were included in the packets for the Board's review.
Mr. Slezak moved to approve both contracts as written, with one change
noted on Mr. Hardy's in the area of retirement benefits. The motion was
seconded by Mr. Belcher and carried unanimously.
ADJOURN There being no further discussion, the meeting adjourned at 9:35 a.m.
Jason Meodors, Secretary
DDA Miviv% 3/q/qq
03/13/2000 11:35
97040e -59
PAGE 01
DDA MINUTES
PAGE s
.NEW CITY OFFICE
BUILDING
6cT 7, 1ch94 �5 �etc7e� 1
PAR 1 3 `
H .
Ann Tumquist outlined .the,project whichiIs`intended to consolidate many of
the City offices currently spread throughout town. The plan calls for a 70,000
square foot, four story building. The R.F.P's are slated to go out in November
and it is hoped the design will be completed and approved in 1999, with the
construction phase begun in 2000 and completion by 2001.
Board input is sought to ensure this building is planned with the public In mind:
with many of the more commonly used facilities housed together so they may be
more readily accessed.
251 LINDEN ST Owner Douglas Gennetten, appeared before the Board to seek DDA
participation in the restoration of this building. Mr. Gennetten advised that
both he and the Silver Grill were recipients of a State Historical Grant in the
amount of $140,000 to be shared between the two projects.
The restoration, spearheaded by Richard Beardmore, will be done in phases.
Tate first being structural reinforcements, roof repairs and interior finish of the
lower level, This, combined with the facade restoration, will facilitate the
leasing of 2,000 square feet of retail space, thus providing funds for the
second floor restoration, which is phase two of the project.
Initially, a motion was made to support the project in the amount of up to
$20,000. This was moved and seconded by Messrs. Belcher and Pitner
respectively. Then concern was expressed that appropriation of DDA funds had
not yet been worked out by the City's Finance Department, and while the
hearing by City Council will take place by year end, these funds are not yet in
place. Therefore, Mr, Wanner moved to table the motion, with indication of
future support at such a time as the governmental variables are removed. This
was seconded by Mr. Meadors and the motion carried with two opposed.
BELCHER PROJECT Mr. Steiner stated that the City has required the developers of this project to
revise right -Of --way improvements, which could result in a reduction of funding
for this segment of the project, which DDA had agreed to underwrite. The
developers have posed the question as to whether some of the funds can be re -
appropriated to cover facade costs. The Consultant shared his reasons why this
request did not seem appropriate.
Following some discussion by the Board. Ms. Brayton moved that the
level of DDA participation previously agreed upon remain proportional to the
funding envisioned for this project. This was seconded by Mr, Wanner.
As the issue was further clarified, Mr. Allard summarized that the Board should
consider the above a point of information only at this early date. He concluded,
that when final numbers are received, whatever action is appropriate could be
taken by the Board at that time.
OTHER BUSINESS ' Rand -Scot Incorporated
Ms. Brayton declared a conflict of interest and declined to take part in the
discussion. Mr_ Steiner recapped the Board's commitment of $32,000 made
to this entity in 1997 for facade and right-of-way improvements. CDBG funds
were earmarked for this project, but it was later teamed that they could not be
DDA hv1vteS 16/e/18
03/13/2000 11:35
9704840969
DBA/DDA
PAGE 05
ABA MINUTES
PAGE 2
NEW EXECUTIVE
DIRECTOR
The budding will house such entities as Information Technology, Human
Resources, Forestry, Parks, Planning, Transportation, etc, The entry will
open up into a rotunda which will house an information center for the entire
building. Responding to questions on how the building will look, the Board was
advised that most surfaces will be brick, probably with a stone
facing. Construction is slated to begin in 2000 and will take approximately
nine months to complete. Cost of the building will be paid for by the City's
General Fund. It is under consideration at this time to put the new Library
and a third parking structure on this lot
David ' Short, new Executive Director, was formally introduced and welcomed
by the Board.
FINANCIALS Scott Smith reviewed the financial report for the Board, noting that assets
were greater than liabilities. The aging report reflects funds due through the
end of the year and Jacor has finally paid in full.
A question arose regarding sponsorship monies. Jay will check on this and
Provide the information to David. A review of First Night financials showed
us over budget by $9,000 most of this was in the area of entertainment.
Other factors were less sponsorship dollars than the previous year and not
as many button sales as projected.
The budget for 1999 - 2000 was reviewed. First Night is less aggressively
budgeted than last year, ' in fact it is "lore realistic. David 7amzow made a
motion to adopt the budget as presented, this was seconded by Ann James
and carried unanimously.
EVENT UPDATE
St. Patrick's Day Parade -,For the first time in history, this event made money.
There were sixty three paid entries, seventy three, including sponsorships. A
suggestion was made to set the parade time a little later, to encourage crowds to stay
downtown for lunch and shopping.
ART IN PUBLIC
PLACES
Lee Swanson provided the Board with a very comprehensive, thought provoking
report on his meeting with the captioned committee, and the deciding vote to
commission Michael Haynes to prepare plexiglass banners to be hung from
downtown light poles. The Board reviewed the samples provided by Lee, and
expressed great concern on several levels. It was generally felt that in no way did
work of this caliber complement the historic look of downtown. Safety issues were
discussed because of the high winds this area experiences. In
addition, plexiglass
becomes cloudy and abrades very quickly when exposed to the elements, and lacks
the timeless quality which fits downtown. Thus the Board is in opposition to
this art form. It was urged that a letter be sent to die City
expressing concern.
It was also felt that the Landmark Preservation Commission should be apprised.
ELECTION OF
OFFICERS
In the February Board Meeting, Directors were asked to consider serving in an
executive capacity. The sate of officers is as follows:
Dak M(n s `j/7/q`j p,2-
03/13/2000 11:35 97048d`G9
DBA/DDA
PAGE 04
BOARD OF DIRECTORS' MEETING
MINUTES OF APRIL 7, 1999
REGULAR MEETING
The Board of Directors of the Downtown Business Association met in regular
session at 3:00 p.m. April 7,1999 in the Adriel Hills Club House at 1900 Kedron
Drive.
PRESENT
There were present:
Mary Brayton, President
Ed Stoner, Vice President
Scott Smith, Treasurer
Debbie Reider, SecretaryR i1)
Robin Goette
Lee Swanson
David Zamzow
Jeff Nuttall
Ann James
Jim Larsen
Ed Stuessie
Brenda Cams
ABSENT
Tommy Short
STAFF
David Short, Executive Director
Brynn Markle
Anne Garrison
GUESTS
Jay Hardy, lack GianoJa, Wendy Irving Wells, Jim Bowie, Bill West
CALL TO ORDER
The meeting came to order at 3:00 p.m. with Mary Brayton
presiding.
APPROVAL OF
MINUTES
Ed Stoner made a motion to approve the minutes of March 3, 1990
this was seconded by Scott Smith and carried unanimously.
NEW CITY OFFICE
BUILDING
The updated design was presented by representatives of the Neenan
Company. It
reflects the ideas and suggestionsof such Boards
and Commissions as DBA. The
three story, 7l,000 square foot building
is to be set back from North Mason and LaPorte, in order to allow for a
pedestrian pathway.
I)ow"town Business Association . 19 Old Town Square. Suite 230. Fort Collins, CO 80524
Tel: 970-484-6500 - Fax: 970-484-2069
P6Ar ffilAutt6 q/T/,Iq 95l
03/13/2000 11:35 97048n" ;9 DBA/DDA PAGE 03
jr
DBA MINUTES MAR 1 3
PAGE 2
NEf anoFFXE A presentation was given by Ann Tumquist who explained that the
BUILDING projected building would be a 70,000 square feet, possibly four story
building located on the southeast corner of Block 32, (LaPorte and Mason
Streets.)
The intent is to house as numy administrative offices under one roof as
possible, i.e. departments such as Transportation, Human Resources and
Information Technology, to name a few. RFD's are going out at the end
of the month in the hope of finding a Design -Build firm that will do both
the design and construction of the building. The timeline is to complete the
design in 1999, construction will take place in the year 2000 and
completion/occupancy in 2001.
It is planned to design a building that will be customer friendly, energy
efficient and both flexible and durable over its lifespan of 40+ years. City
personnel is requesting input from the Board which would assist them in
determining the image this building will project. Mr. Stoner suggested that
a design be employed other than that projected for the new parking .
structure. It was also suggested that the building have a more functional
look, in contrast to the more inspiring Justice Center.
TRANSPORTATION John Daggett spoke concerning the Northeast Trucking Route; that
consideration is being given to moving Highway #14 and Riverside out of
the downtown area. Throughout the summer various options have been
examined; they are presented here for the Board's consideration.
Using a master street plan, John indicated projects scheduled for build out
by 2015, including developments which will house 13,000 residents and
include a high school. The projected Fort Collins population in ten years is
150,000. This undertaking is currently in its third tier of evaluation.
The three alternatives presented were as follows:
* Vine Drive - Interchange at Interstate
* Mulberry Corridor - to Lemay/Mulberry Intersection
* Vine Drive - Straight to College Avenue
Cost to do one of the ahernatives would be $15 - 20 million and the
timeline is one to five years.
EVENTS At the November meeting a full report will be provided regarding the
Farmer's Market research. In addition, a meeting with City personnel
has been arranged to discuss the occurrence at NewWestFest, in which
Sierra Club personnel paraded in opposition to a political booth.
Dm Minuet, tom/°fib
New City Office Building
Public Comments:
Optional:
Name:
Address:
Phone:
1��v�ovt � open 1nw,�
350.000
300,000
250,000
City of Fort Collins
Facilities Planning: Space needs for employees in the downtown
FORECAST OF SPACE Ni.-ZEDS VS EXISTING AVAILABLE
291,053
253,089
OTRANSPORTATION
® POLICE
® EXEC/LEG SVCS
® CLRS
CPES
®ADMIN. SVCS
—EXISTING
6 TOTAL
II 131,808 1
1980 1985 1990 1995 1999 2000 2005 2010 2015
YEAR
assumes no new facilities leased or constructed, and space on Blocks 31 and 32 not available after year 2010
9/23/98
Proposed Occupants
New City Office Building
Finance Department
• Accounting
• Purchasing
• Risk Management
• Treasury
Cultural, Library and Recreation Services
• Forestry Administration
• Golf Administration
• Parks Planning
• Parks Maintenance Administration
Human Resources Department
Information Technology and GIS
Transportation Services Administration
�qH� �OM Oftlk
NEW CITY OFFICE BUILDING
PROJECT DESCRIPTION
COST: $11,578,449 (projected)
FUNDING: Tax-exempt lease certificates of
participation
SIZE: 70,000 sq. foot, four story building
LOCATION: Southeast corner of Block 32
LaPorte and Mason
SCHEDULE:
Design/Build Team RFP
Design
Construction Begins
Completion
Fall 1998
1999
January 2000
March 2001
1OV' k �fmn^ OPM61a 1
I
NEW CITY OFFICE BUILDING
PROJECT DESCRIPTION
On September 1, 1998, Council approved the funding for a new City office building
through the issuance of tax-exempt lease certificates of participation. The current
projected cost of the facility is $11,578,449. Plans for the building call for a 70,000
square foot, four story building to be constructed at the southeast corner of Block 32. The
facility will be directly across the street from the new Larimer County Justice Center.
Land directly east of the project will be used to develop a Transit Center on Block 22,
while the new parking structure will be located to the southeast on Block 21.
Several design elements should be considered to be "givens" in the process because they
have been prescribed by various planning documents adopted by the City. Some of the
elements which are predetermined include:
• The building facade should be comprised primarily of sandstone and brick
materials, as outlined in Land Use Code for Mixed Use —Institutional and
Commercial buildings in the Downtown District.
• The architectural features should match those which will be used at the Justice
Center, parking structure, and transit center to reinforce the continuity of the
four corner's projects. These features should include items such as the overall
visual impression of the building, the exterior light fixtures, sidewalks,
crosswalks, and other details.
• The design should support the overall Civic Center Master Plan concept,
including the importance of the pedestrian "spine" in the district, mixed uses,
a human and walkable scale, easy access for a variety of transportation modes,
and strong connections to Old Town, surrounding neighborhoods and the
Poudre River.
• The building design should enhance customer service, be energy efficient. and
make building maintenance efficient over the building's lifetime.
• The Art in Public Places component of the project should be coordinated with
the other three facilities in a master planning process.
Public comment will be sought on such issues as:
• How can we best design the building to meet the goals of the Civic Center
Master Plan;
• What image should the building project to the community;
• How can the overall design enhance customer service;
• What qualities in the building will help it to be both flexible and durable over
its expected 40+ year lifespan, as well as energy efficient; and
• What "sustainable design" elements are important in the building to minimize
the building's impact on the environment.
I A404 6M open W-YA-
NEW CITY OFFICE BUILDING
Pre -Design Outreach Process
Handouts
October 1998
Rook Qm OPMAP*
Page 2
• Try to include a water feature or native rock feature that ties to the history of Fort
Collins
• There should be an outside professional helping to evaluate designs
• Tie the design in to the Mason Street Multi -Modal Transportation Corridor plan
• The new buildings at the four corners shouldn't be too much alike, or it will seem like
an institution
• Emphasize natural materials
• The look of the buildings at this intersection should be diverse or downtown becomes
boring
• Needs to be a timeless look, not trendy. It will serve as an anchor for the downtown,
so it needs to look permanent
• Too much gaudy design is difficult to maintain
• Include a place in the lobby for kids to wait as business is conducted
• The building should have clean lines, not too "grand"
• Not as "fussy" a design as the parking structure
• It should look like a government building, solid and permanent
• Not too flashy or expensive looking like Jefferson County
• Classic lines are best
• It should look useful, efficient, not intimidating
• The building doesn't need a lot of lobby area
• There should be a consistent look with the rest of downtown
• There should be an obvious entry point (s) so that people aren't confused about where
to go into the building
• It seems like Utility Billing should be part of this building so that people know that
those types of functions are all in one place
• Plan for future expansion of the building
pubcouun.doc
Ocfolaer 6 ope&q goose MIMUu6 5
P5Z
New City Office Building
Pre -design Citizen Input
October 1998
• Friends of the Library Nvould like 1200-2500 square feet of temporary
warehouse/sorting space for its program until the new library is built (basement/attic
type space)
• The building should be lower scale, not as imposing as the new Justice Center
• Day lighting should be emphasized
• The space should "delight" the visitor, as. does the new Harmony Library
• Design/Build is not the most cost effective or design effective way to accomplish the
project
• Design/Build is a good way to do this type of project
• It should be easy to find your way through the building. This should include good
mapping and signage. Maybe even a color coding system.
• The building should have enough doors from the outside so that it is convenient to
approach from more than one direction.
• The building should be welcoming, with a clearly established point of contact for
visitors
• The building should be warm, professional and welcoming like Loveland's City Hall
• Well -labeled counters
• Information should be available outside of counters, like applications, forms, or
brochures. Plan for this because it always happens.
• Touch screen directories help people find either departments or individuals
• Wide, well -lighted corridors
• Less angular is more welcoming and comfortable
• Consider issues of water quality and the building's parking lot
• Make sure that the water, sewer, stormwater and electric systems can handle the new
building
• Create a design that helps encourage the use of alternate travel modes: daycare
center, bike shelter or parking, showers, lockers, etc.)
• Include a large multi -purpose room for both day and evening use. Should be easily
accessible at night form community meetings, not buried in office suites.
• Create easy ways to move and change room set-up. Include a good way to store
tables and chairs in a tidy way.
• Balance between a nice finish and the cost
• Needs to be easy to maintain
• Easy access from the sidewalk, not just through a parking lot
• Should be a preference for local architects and builders
• Underground the parking if possible
• Use the concept of borrowed light, possibly as part of the Art in Public Places
• Cubicles are depressing
OQ00er Opev� Hover Mlnvi:s
eb I
NFT 7HBORHOOD INFOR"TATION MEETING
s for I
Project: Ctfi�j 0 Ton4si+
City of Fort Collins
Meetin2 Location: .-Zs 1 N . Cc, i/� rai P Poo t t.. S
Date: _q Z 13 / 47 1
d Attendees: Please sign this sheet. The information will be used to
update the project mailing list and confirm attendance at neighborhood
meetinas. Contact the Planning Department (221-6750) if you wish to
receive minutes of this meeting.
Name Address Zip;
Did You ReceiveCorrect
Written Notification
of this meeting?
Yes No
Address.
Yes No
CD c S
- 2 2
V I rJC1U1R,Co O.�Z� L . ��L 10CC / S
I v
v
T-r�cl 7..i , 'Zi.VGc✓ - Cl e-,c /T/6' i
C3 ow�>ZZ
�A irl ✓�. 74f r� 60///,H6
G . 02 A� /BZo xs� �a. �o
NI
I
� n /-'I Z' 13CI n k Le C OTC
-
'
I
.
public hearing. When a project is under development review, the files are
public record. Any member of the public can look at the files at any time for
any reason.
Q. Has there been any determination of a site for the new library or the
new performing arts center?
A: Sales tax has been appropriated to pay for the acquisition of the land,
but there has been no decision on a site for either building to date. There has
not been any funds appropriated to build either building.
Q: Is there a deadline for choosing these sites?
A: The site for the performing arts center should be determined this year;
the library, probably not until 2004.
A: Both projects will be under construction at the same time, which will
temporarily affect the vehicular circulation and access of the Justice Center.
Q. What is the band of green next (west)to the proposed office building?
A: Landscaping, curb paving, and water quality features.
2. The Transit Center
Q: What is the proposed bike library?
A: A facility where bicycles can be checked out for public use. This would
include a bike maintenance area.
Q: It appears that the existing alley configuration on this block is being
moved. Won't the alley on this block need to line up with the alley
configuration on the block to the north?
A: This is a preliminary design at a very early stage of development. The
city's development review process allows the various departments within the
city the opportunity to review the proposed configuration. If there is a
problem with the configuration, the Transportation Department and the
Engineering Department will have an opportunity to review the proposed alley
alignment against any code requirements for such alignments.
Q: What is the schedule for this project?
A: Originally the project was scheduled to begin construction in March
2000, but it has been pushed back at least 3 months.
Q. Is the city in a discussion with Greyhound about possibly locating bus
service here?
A: There has been nothing finalized, but there is a discussion currently
underway between the city and Greyhound about putting bus service here.
Q. What is the next step?
A: Next week, the applicant will be meeting with the building users to go
over the site plan. Once layout is determined, the project will be formally
submitted to the Current Planning Department for development review as a
Project Development Plan (PDP).
Q: Has the general public been informed about this project?
A: The concept of a transit center on this site has been discussed at city
council meetings in the past, which are public hearings. When this project
goes to hearing as part of the development review process, there will be another
NEIGHBORHOOD MEETING MINUTES
for
The City Office Building & The Transit Center
conducted
7pm — 9pm, September 13, 1999, 281 N. College, Conference Rooms A&B
1. The City Office Building
Q. Time Schedule for construction?
A: Construction will not start until the Howes Outfall is completed. The
outfall is scheduled to be finished across this portion of the site in July of
2000. Construction of this project, if the Howes Outfall is completed on time,
will commence in July of 2000, and will take approximately 1 year to
complete.
Q. How will traffic and access issues (impacts on surrounding properties)
be coordinated during construction?
A: The alley access will be utilized, bike lanes will be maintained, and there
will be a traffic access plan in place that will direct traffic with signage. There
will be no complete closure of access during construction. Construction of
Laporte Avenue will be done in Phases. Matt Baker, the city's street oversizing
coordinator with the Engineering Department can answer any specific
questions about Laporte Ave. construction.
Q: How will stormwater issues be addressed?
A:. The Howes Outfall will be completed before the construction of this
project is underway, therefore, the outfall will take all the stormwater rather
than the streets. The Howes Outfall from Cherry Street north to where it
terminates is currently under construction, and its construction from Cherry
Street to -Laporte Avenue will start in February of 2000. All drainage
easements for the Howes Outfall are within this block will be on our site rather
than on adjacent property owners sites. Laporte Avenue will be lowered 2 feet
to accommodate the outfall.
Q: What types of pre -construction work can we expect on -site?
A:' The existing temporary parking area will be vacated and utility work will
begin several months prior to the July 2000 official start of construction.
Q. How will the Laporte Avenue construction cooinside with the
construction of the proposed office building?
City seeks
By KYLE NENLEY
The Caomamn
What would you like to
see incorporated into the
city's new $11.8 million of-
fice building?
City officials will be
looking for your opinion at
a 4:30 p.m. open house
Tuesday at the Communi-
ty Planning and Environ-
mental Services building,
281 N. College Ave.
City picks
By KYLE NENLEY
The Coloraooen
Plans for an $8.2 million
city, office building are mov-
ing ahead.
Late last week the city
awarded the contract to de-
sign and build the 70,000-
square-foot office to a team
led by Neenan Co., a Fort
Collins -based construction
company.
' The building will be on
the northwest corner of
Mason Street and LaPorte
Avenue. Construction will
begin. in the spring of
2000, and the building is
scheduled to be complete
"We thought befo
started designing
building that we
find out what the
thinks would be
said Ann Turnquist
Council policy mana
The 70,000-squa
office building is pr
for the northwest co
Mason Street and L
Avenue - across the
from the new L
pro
car
input 0n
re we County Justice Center and
the a 900-space parking struc-
should cure.
public Construction has begun
good," on the justice center and
, City parking structure, and
ger. crews will begin building
re -toot the office building early in
2000,
of The city's parks, finance,
aPorte human resources, infor-
street mation technology and
arimer transportation depart -
■Region, State/2, 6-7
RObituaries, Record/4
■Cash 5, Football Fortune/4
■Opinion/5
new office building
ments tentatively are
scheduled to move into the
building, which likely will
be finished in 2001.
"These are departments
with lots of customer con-
tact" Turnquist said. 'We
envision a lot of customer
windows."
Even with the multi-
million -dollar price tag,
the new building is being
billed as a cost -saver.
local contractor to design,
in late 2001.
"Quite a bit of the focus is
on energy efficiency" Assis-
tant City Manager Frank
Bruno said. 'The building,
during the day, %till use very
little artificial bght"
Combined with other en-
ergy -efficient designs, that
will result in 35 percent in
energy savings compared
with traditional designs,
Bruno said.
"I think it is going to be an
extremely attractive project
for the city of Fort Collins,"
Neenah Co. President Jim
Neenan said. "We went to
great lengths to incorporate
human resources,
i We went to great tion technology and trans -
lengths to incorporate portation departments are
the newest ideas that scheduled to move into the
new building. Those depart -
are out there and ments currently are spread
proven successful in out in various leased spaces
the design of the fa- in and around old Town
cility. f The city will save about
$600,000 a year by mining
Jim Neenan, president, employees out of the leased
Neenan Co. space, money that will go 10
ward paying for the new
building, Bruno said.
the newest ideas that are out Neenan, the construction
there and have proven sic- company, will he working
cessfal m the design of the with BHA Design and CZ
facility" Architecture, which will de -
The ciWs parks, finance, sign the structure.
The city currently leases
will be saved "from current
47,256 square feet of office
leases or current needs
space in downtown Fort
that would no longer be re -
Collins. Many of the de-
quired ... with the develop-
partments in leased apace
ment of a new office build -
will move into the new
ing."
building, Assistant City
That will go a long way
Manager Frank Bruno
toward paying the
said.
$850.000 payment
Following the basic phi-
-yearly
on the 20-year bond the
losophy that it is better to
city is using to finance
own than to rent, Bruno
construction of the build -
estimates $600,000 a year
ing.
An Ottioe ksunuing ,
for 2001- �.
4.41�'e� -1': is
Ja:+.
i
The City of fort Collins invites you to an open F'touse
for its next addition The new city office building
will be located on the corner of LaPorte Avenue
and Mason Street:'
Please join us on Tuesday, Oct. 6: from 4:30 to 6:3'
p.m. in the Conference Room at 281 North Collegt
Interested a�tt�zens, downtown neighbors and downtown busi-
nesses areienmoraged;to at4endsWe'II provide information
abouF. 0. city bRc'ebuilding and., elcome feedback
and ideas orn tnterested citizens on the design of the new
facillG `
Thi m i ilding is slated for construction in 2000 and will
611. -,.
be tomQ�rxec-in 2001. The 70.000 square foot building will
be zd'aren-t the -new County justice Center, the new City
parkin'S"'"u' ureand the newTransitCenter,
For more information, all Ann Turnquist at 224-6094.
ion nmrnY ndutUam Ya M1[wembk umm,leJumm bxam,m Gly unkn
pipr11m1.M/dMdOYW W IIYY[RlfulNml"YNUIMu,.,l(lmenu bpll0,r mlt•,..
construct downtown office building
informs" -
Courtesy City of Fon c
FUTURE LOOK An artist's rendering depicts the city office building planned for the comer or
son Street and LaPorte Avenue.
.i��.'t •�TrICIt4 tEi�'.�"'".`""�Iir.:.Y,� ..._�. -
s
City of Fort Collins
Admini itive Services
Facility Services Department
MEMORANDUM
TO: Bob Blanchard, Director of Current Planning
FROM: Jared Interholzinger, Interim Facility Services Directo
DATE: March 6, 2000
RE: NEWSPAPER ARTICLES
Bob, attached are copies of a couple of newspaper articles regarding the New Office Building
being proposed. P&Z Chairperson Colton stated at the March 2°d meeting that he had not
recalled seeing any newspaper articles on this project. I had mentioned that I would send copies
of the articles I had. Please distribute to P&Z members as desired.
Also, note that the exterior rendering has not really changed from the design shown at P&Z.
Attachment: Copy of newspaper articles
cc: Jack Gianola, Senior Project Manager
117 North Mason Street • P.O. Box 580 9 Fort Collins, CO 80522-0580 • (970) 221-6611
Feb-14-00 06:48A
P.03
The plan, as submitted, serves the purpose of the code equally well or better that a plan
which complies with the code for the following reasons:
The street tree placement, as proposed, integrates the building with the site and landscape design.
The landscape plan considers the building's character, form and function, and it accentuates
specific architectural features. A plan which complies with the code would merely line the streets
with trees with no consideration given for features which make the project unique. The code does
not consider site relationships or subtleties which help to integrate the design.
A plan that is in compliance with the street tree requirement would provide two (2) more street
trees in front of the building entrance and two (2) more street trees at the northeast and southeast
corners of the site, or a total of six more street trees.
in order to ensure significant canopy shading, to reduce glare and heat build-up, and to offset the
decreased number of street trees, we have provided eight shade trees around the circular water
quality pond near the northwest corner of the building. All of these trees are above and beyond
those required for "hull tree stocking" purposes.
The proposed street tree planting scheme also serves the purpose of the code by: reducing
conflicts between activity areas and site elements; by contributing to the visual quality and
continuity within and between developmenis; and by enhancing outdoor space's.
Thank you for your consideration in this matter.
End of Request
Rnqu�a - .S'tn�ra 7rre .Sj>arin,�
Feb-14-00 06:48A
P.02
Alternative Compliance Request - Street Tree S
Civic Center Office Building
Section 3.2.1 Landscaping and Tree Protection
Purpose: The intent ol'this section is to require preparation of landscape and tree protection
plans that ensure significant canopy shading to reduce glare and heat build-up, contribute to
visual duality and continuity within and between developments, provide screening and mitigation
of potential conflicts between activity areas and site elements, enhance outdoor spaces, reduce
erosion and stormwater runoff, and mitigate air pollution.
Alternative Compliance Request
There are three locations along the perimeter of -the Civic Center Office Building site which
require that we request alternative compliance for street tree spacing as defined in section
3.2.1(1))(2)(a) of the Fort Collins i.and Use Code which states ... "Wherever the sidewalk is
separated from the street by a parkway, canopy shade trees .shall he planted at thirty-foot to
forty fciot spacing (intervals) in the center of all sued parkway areas. Such sireei trees shrill be
placed at least eight (X)feet away frenn edges of driveivrr).T and alleys, and forte (40) feer away
fi-uni any street light."
Area 1. We request alternative compliance for the street tree requirement in the area adjacent to
the main entrance of the building on the cast facing facade. Street trees have been intentionally
left out of the area in order to preserve views to the building entrance. This portion Of the
building has a significant level of architectural detail and deserves to he seen and framed when
viewed from Mason Street. Please refer to the architectural elevations.
Areas 2 and 3. We also request alternative compliance for the street tree requirement at the
northeast and southeast corners of the site. Street trees have been kept away from the comers for
the following reasons. first, existing or proposed street lights are located on both comers (as
required by the Light and Power Department). The code requires a minimum 40 foot separation
between street lights and shade trees and a mitnniurn fifteen (1 S) leot separation between
ornamental trees and street lights. The proposed shade trees provide the required setback to the
street lights. The code would allow ornamental trees to be closer to the street lights, but we feel
that they would interfere with pedestrian traffic on the sidewalks because of their low branching
habit.
The proposed street tree configuration also preserves views to the southeast comer of the
building, which incorporates significant architectural elements. in reviewing the building
elevations you'll notice that this comer includes a considerable amount of sandstone, cornice
treatments, .and interesting window elements.
Alremative Compliance Request - Sit eer lies )pacing Paer I of?
m
Feb-14-00 O6:47A
P.O1
4803 Innovation Orive. Fort Collins. CO 80525
Tel 970-223-7577, Fax 970-223-1827
design
Fax
To: 1 O M5 Date: !r' �... 00 _
Company: ��� n Project: j! ( g� 0l>�f ( 7,
Subject: A W . 6.Mf!Imo AN=
From: Pages: - - -
❑ As Requested )� For Review ❑ Please Comment ❑ Please Reply
• Commentst
Feb-04-00 04:26P
P-03
mid -block crossing. We feel that it is unsafe to introduce the pedestrian crossing into this
area.
4_ A plan which complies with the Civic Spine standard H.rndd: Add one more conflicting
element to a very active street.
The plan, as submitted, serves the "purpose" of the standard by.
Incorporating civic uses within the Downtown District to complement adjacent uses such as
hotels, entertainment, retail and housing.
2. "The building architecture respects and reflects the local heritage and character by
incorporating brick and indigenous sandstone. The building forms are reminiscent of other
buildings within the immediate area and within the Downtown District.
3. The building incorporates architectural elements (mass breaks, plane changes, columns, and
awnings) which gives a human scale while preserving the institutional character of the Civic
Center. Refer to the building elevations included with the project development plan.
4. Generous sidewalk widths are provided which support the pedestrian oriented character of
the civic center. Ornamental street lights and high mass street lights are provided to support
the night-time use of this area. Street trees and tree lawns create a comfortable and protected
pedestrian zone.
The plan, as submitted, will protect the public. interests and purposes equally well or better than a
plan which complies with the Civic Spine standard
The plan serves the intent of the Civic Spine standard for the following reasons:
1. Well defined cross -walks are provided at the I.allorte/Mason and Maple/Mason intersections.
The LaPorte Street/Maple Street intersection is signalized. We feel that the cross -walks at
the intersections provide safer pedestrian crossing points by reducing the number of
conflicts between cars, buses, trains and pedestrians. "These connections are not as direct as a
plan that would comply with the standard, but they are far safer due to the conditions
described in earlier paragraphs.
2. The cross -walks will serve to connect various buildings in order to unify parks and plazas.
Thank you for your consideration of this modification rcqucsl.
Roger Sherman
BHA Design
Feb-04-00 04:25P
P-02
Modification Request - Civic Spine (Mason Street Mid -Block Crossin
Land Use Code Section 4.12(A) - Downtown District (D)
"Purpose. The Downtown District is intended to provide a concentration of retail, civic, office and
cultural uses in addition to complementary uses such as hotels, entertainment and housing. It is
divided into three (3) subdistricts as depicted in l igure 19. l7re development standards for the
Downtown District are intended to encourage a mix of activity in the area while providing for
duality development that maintains a sense ol'bistory, human scale and pedestrian -oriented
character."
Land Use Code Section 4.12 (E)(5)(a) - Special Provisions - Civic Center Subdistrict
"Civic Spine. All development shall incorporate the concept of the "Civic Spine" as described in the
Downtown Civic Center Master Plan, allowing for continuous north -south and east -west pedestrian
connections. The civic spine will serve to connect various buildings in order to unify parks and
plazas.
Modification Request
1-he east -west civic spine, as described in the Downtown Civic Center Master Plan, is a well
conceived notion from a general perspective. I lowever upon a closer examination ofthe site specific
physical relationships (i.e. adjacent uses, traffic, safety, ctc.) our recommendation to the City is to
modify the east -west spine so that it dues not cross Mason Street at the mid -block location. For
reasons described below, we feel that the Mason Street mid -block crossing would be detrimental to
the public good if installed per the original concept Alternatively, the two proposed Mason Street
cross -walks at the north and south ends of this Mock provide a safer pedestrian connection to
buildings, parks and plazas on the east of Mason Street. Therefore we request a modification of civic
spine standard.
Suppletnental Findings
A plan: which complies with the Civic Spire standard will not protect public interest for the
following reasons:
A plan which complies with the Civic Spine standard would. Extend the east -west civic -spine
across Mawn Street and bisect the existing bus/car loading area at the Transit Center site.
This configuration would create a situation where pedestrians cross in font of buses and cars
that are attempting to merge from the busicar loading area into the Mason Street travel lanes.
This is an unsafe condition for pedestrians.
2. A plan which complies with the Civic Spine standard would: Encourage pedestrians to eroas
the railroad tracks at an un-signalized location. This crossing represents and additional
liability to the railroad company, therefore we anticipate resistance of this idea from the
railroad company.
3. A plan which complies with the Civic Spine standard would: Locate the mid -block crossing
just south of the median in Mason Street. This creates a situation where many drivers are
looking for opportunities to change lanes, or are changing lanes, in and around the area of the
Feb-04-00 04:25P
P.02
4803 Innovation Orivc, Fort Collins, CO 80525
Tef 970-223-7577. Fax 970.223-1827
design
Fax
TO: Date: :7 �il✓%�
Company: � r !� Project: I � / _ N�. w_ fz_3PWO-
Fax:—�Ltf�_ Iv Subject: C/ (i !ELT 4
From: Pages:
n As Requested X For Review
• Comments:
n Please comment ❑ Please Reply
1.1 S.I0 V1
WAE102MPAVAMWAMM,1//a 1
r
Corner Treatment
Fort Collins, Colorado
DOOR OPTION
Corner Treatment
Fort Collins, Colorado
design
Mason Street Urban Design
Fort Collins, Colorado
a
��`a / • --'r ' ICI I �� ' � . �Il 'y ! j, �'f�
IBM "N
i —!Is.—
Mason Street Urban Design
Fort Collins, Colorado
DOOR OPTION
I.
DOOR PROPOSED OFFICE BUILDING
3 STORIES
Flagpole. typical 71,513 S.F.
Flower Pot, typical
5anch, typical
Planting Bed, typical
MASON STREET Seat Wal,
Low Iron Fence Street Light
70
-Bicycle Rack
Ornamental Pedestrian Light
6-
W] 11
xosrx o r is u
Mason Street Urban Design
Fort Collins, Colorado
Q
-1 f-
I I I I
0 PROPOSED OFFICE BUILDING
H - _ 3 STORIES _ � \
_ Flagpole, typical 71,515 S.F. 6'
coo Flower Pot, typical ' _
I--j - Bench, typical -
Ch[1�-7 Planting Bed, typical
H ,\,.
MASON STREET seat wall Bicycle Rack
Seat Wall
Low Iron Fence Street Light Ornamental Pedestrian Light
i�u�
X02TR o r it u
den�o
Conceptual Master Plan
Fort Collins, Colorado
/1 i�u^
NORTH o IT u i,o
design
No Text
MAPLE STREET (PUBLIC)
LAPORTE STREET (PUBLIC)
/1 romml
n lR
u 1
ROR}R 0 M N O
PROIRCT DEVHLOPMM PLAN _ LIGHTING PLAN
CIVIC CENTER OFFICE BUILDING
FORT COLLINS. COLORADO
SHEET 6 OF S
DRCRM BER T. 1999
R HWD F H. a
' rrrrrl 11 11 1� rl Ir rl n rl i/ 111 1■ ■1 i \7 .1; a F a N • i;IC M n u Ill ii ii 11 11
norm ii N ME iirl RE MH iiiii RO ME Irrl inl Im IBM in ii u
I- �alrrn:i r 11 1 1 �� o h i nr i i mu, ,! aE i of
m unmlrn�url;,�url.�ii7� �lll ti'Filaalrrl: urrrurlmlrngllrn n u
ii ii i; M1 M ill ii I M ii
ii 11 ME Irrl un Irrl
■® ON zip an
n n �ulun_�rn�nn
I rl Ir rl_ 1li Ii1 Irll 11 J!
Irrl Irrl Irrl Irrl Ire:
..............
un nn m_m
n u u o Inl Irn m Irl nre•;
hli�i
n 3! n n ': �Irn�liGi�nl�ul��nre•��
PROJECT DEVELOPMENT PLAN _ CONTEXT DIAGRAM
FORT COLLINS OFFICE BUILDING
FORT COLLIMS. COLOIiADO
SHEET 3 OF 6
YLRROARY 1l 3000
F
am
• sr
s.
I
nvw
•an oR x.a
min
nAIM EAMAU IIn
v
Nelr.r
...
s
.a.. •I.
w�PY
�.1.l.wl..ylti�
frN�
N
Y/1.' 1
r.�r�.HwM
! eu.w rlr yw•
yn.lwyrw
v �
N
W yw u
�R Y.,.b
N.vla
Y4�v
N
�/w
T.�iIVI./0►7y1.
1.4T
N
Y~i�
fA91111N ,nR[.
nIY M...vy..•W. Y/
Accmw.rr
•Y. M.pe
.r IRE
N
YM
Ibxrr
On.w
•Y•r
Y
♦aG
P
,0.�.•n
�•
�Y•v
fi•
iv et
nw�ivw•'wln..r
Yb PM..w
o1yb+...n.w..
••..v
f^
u'ec
Y'OG
Nl.Iba�W •Y.v
ur slm avw�....wra.'rla�. Nl.r
na.•s •....
fw
Gil
xw l.p�i. � F.ya�
4y.�
..11v Yr •�Y
.Y.n
�
Y�
F..�a
Nr.•svaR•aPpr �Nr
fi
roc
rw• n...... •.Pi
m
AENCA l IICDm
ODECIpY]b 54ApE *F£E
OLgJAMEMY *ra;e
CFT.fiERp+S *i€E
.,u� EEscuE eoo
, yNep�..bx....Pwrm.Fa...Y.Ira.la.IF.,.
wl—Y iM, b.6�ilYWY.x b M1. Fpgw.WP�M w �,JwaYe Oy
.4� Fgyninn nN>Ru pbr In •. )i.vev W. wbro pvnn
T PbM1tlN WYIgrtlxM Mwn. rwC
1 .'vvN.�btl b P PtlM NM l• aqN uCv w.li. W .rC
1 P y4eM n pvw.l Y.eb
.. Ynb YVY. NII b.rMIO M.I'1.1r
�vpyMp.R !M rb� s.�.a,. amv M1P,9M'.'W.pwrw a x rp.
I•lb pnM., lOw �ln 1wn.nbwJ.i'.9.•'0 ✓'.e b.ro
M,rom IrrMr M..A N.rr.M u,wro
1M Y'.0 P.eM.C.M. wv. M IN. 0.xllvu 64�6.
l � v�+r P mope Ira N W aw ✓an
I.W x bW a IM pM v. Y1P•LL Pn� v rs.� F M.
Pu! R� M Yy
..rxa.FW...__._.I.
4r e.JT Ma.uP lN,v�rv•x.w lv 0.\MY.r
MIM M •...IVYb a. c..xxu> owowvl
vWUP....11e.rt� ... bFn>•an•n.P.
usw.g rw P rw•Pe a •. W a Rx car.w rx...lxa
M Y�ra.yw: w. n.. P �IY.Iw) Mcas M r.
x r•��•9.9�nuu.+qq. ��w.Pwm�PCbv��v�M�b.Y JTL.
✓nY N PPc W v .ry .r
W � erowvtl ,v Yv W vv.x ipl..p,•vgw.tw
R LuxR .�.1a.PP^.b Gybw.�fw Pam'. x.•Wrl.
N. f0•W rw NII P IMw1 b. r.w lv�.
a1 ]O' Irm vu�R 4.6 r�T� ally. MUW a VM
IANDWAN CATMOM
uox�.E
unmle) loll rmvl .••.1
.R.N!•1�M ! >•N! •I
YN! 11R! tl!
/, I' cAL , r.s'
RORIS O or IQ BY
PROIDCY DIV®APMUNT PLAN - PIAWMG PLAN
CIVIC CENTER OFFICE BUILDING
FORT C04-11IN9. COLORADO
;u a®
SHEET a OF O
DECEMBER ]. 1909
RSVISEI) FER. I/'E
1 �in
Iff
\
I
II
\�
I loft,
m
LAPORTE
R9,.. G.DI. YfIR
re r wv®ro
CMAIGIm Y wMR
QMATGIO
rI.IWr fNBI NblGr
VICUffff KAIP
^n
LAND USE DATA
...cw v.e oc°PrPa wmrea.�ae�oe+.c,
.rweY.,Ww nYYv
.n.,a.rnYe,eDx..i..� W •rGm�
. �nccn w,nm u uw. x.
..•reo . x.o.Go�
-vrfm ue..�wr�.on rm na..Ga�
nsr r, we r.r.w. se
v.ra'wcwee.raa a. a.ernGw w
t014 eLiCi! IYtW WI! fiBi y
GVLZNALNOTU xmr.a J.»P /mw
w wYer«Yi•.isYw Ysti W_�~•~r_1
r�t, .. .
OW.rW YY�y Y•Y..•Y'r W.
n�w•�✓�� x�iie �ir••Y��wnr wW..�r
.ram �� .Yrf...r... ».»..w...-w..
r.y.�wrµ�y grr..cr.wr eY
r�sr.•`if1~ MrrO wir.Ni..Y«Yi rrq r�...r
Nws vY� �Mrw»wlfWv«W.tiw.Y«!M1
G± N \YY�eer 1r. M M MM Ilw Ilw MIW fJli. w Lw I w
/YYrYY..Pv.rMeY YstiW .wr. r•YM�rr /••
LRQAL DescRv77ON
OWNUSEOPURrincum
M I.ialfOd DC�eM 1C®. G9YfI,' Tu, we ut M IaY,LL DY6e
Q• RLL FllTBR1' Df13.lm Gl em MR R/w MG M �l4D. QR,..
M.i IY.Ga1 M fdOrtYltl rG lfllYC,�G! Yl Iul,u w On0 YR Rya
tlTO WI.I fLIIW
e. rn./imrcw
MM.®Y i0lbleY
m• Lni.RPK.
.imr.
M YC.f.OW w,weva Yw YY�rcM_ o
ro m e.avY. w
v r"'mY�iro ro� �xx
W POWW AND ZON M BOARD Clw4LPACATWN
frivfD.m s. M r...fYw yo rareu norm a o M an a raer cai.w
BOULCTOR OF PLANNM
(6�.CD q.1wDY.lCL� [�YYMNW OMGI.OKR1 Gx1M
•aven..w ID.If_.
I�
Ic t.nRl
■ORT■ 0 6 r r
PROJECT DL'VVIDPMENT PLAN - SITE PLAN
CIVIC CENTER OITICE BUILDING
FORT COLLLNS. COLORADO
W�1�1�(:1► _a'Ae®
.mr v
S H 6 S T 1 OF 5
DECRLR[R 1. 1999
N6V1S6D FEB
112000
I
RE
Civic Center Office Building, Project Development Plan # 29-99
March 2, 2000 P & Z Hearing
Page 16
architectural design of the building entrance, and by providing more
trees than required.
RECOMMENDATION:
1. Staff recommends approval of the request to modify section
4.12(E)(5)(a) of the LUC.
2. Staff recommends approval of alternative compliance request to
section 3.2.1(D)(2) of the LUC.
3. Staff recommends approval of the Civic Center Office Building Project
Development Plan, #29-99.
Civic Center Office Building, Project Development Plan # 29-99
March 2, 2000 P & Z Hearing
Page 15
questions about the alley, and the impacts this project might have on his
property.
FINDINGS OF FACT/CONCLUSIONS
After reviewing the Civic Center Office Building Project Development. Plan, #29-
99, staff makes the following findings of fact and conclusions:
1. The proposed land uses are permitted in the (D) Downtown zone
district.
2. The Project Development Plan complies with all applicable district
standards of Section 4.12 of the Land Use Code, (D) Downtown zone
district except 4.12(E)(5)(a) for which a modification is being
requested.
3. The Project Development Plan complies with all applicable General
Development Standards contained in Article 3 of the Land Use Code
except 3.2.1(D)(2) for which alternative compliance is being requested.
4. The granting of the modification to section 4.12(E)(5)(a) would not be
detrimental to the public good because the Transportation Planning
staff and Engineering staff have explained that it would be safer for
pedestrians to not have the mid -block crossing of Mason Street.
5. The proposed modification request does not impair the primary
applicable stated purpose of section 4.12(E)(5)(a), which is to provide
for quality development that maintains pedestrian -oriented character,
by providing well defined crosswalks at the Laporte/Mason &
Maple/Mason intersections:
6. The strict application of section 4.12(E)(5)(a) would result in unusual
and exceptional practical difficulties because the railroad track goes
down the center of Mason Street and because the Mason Street
Corridor (not designed by the applicant) has a two-way designated
bicycle corridor along the west side of Mason Street that is separated
from the adjacent automobile and train traffic by a low wall.
7. The alternative compliance request to section 3.2.1(D)(2)
accomplishes the purposes of this Section equally well or better than
would a plan which complies with the standards by emphasizing the
Civic Center Office Building, Project Development Plan # 29-99
March 2, 2000 P & Z Hearing
Page 14
(d) Base and Top Treatments [3.5.3(D)(6)] — The
elevations depict the required top and base
treatments, thereby satisfying this standard.
E. Transportation and Circulation [3.6]
1. Master Street Plan [3.6.1] —Laporte Avenue and Mason Street are
both identified as arterials on the Master Street Plan. Maple is
identified as a local street. The existing right-of-way widths for
these streets meet the required standards.
2. Transportation Level of Service Requirements [3.6.4] — A combined
Traffic Impact Study was done for all the projected civic center
projects (including the Civic Center Parking Structure, the Justice
Center, the Civic Center Office Building, the Transit Center, the
current Courthouse, the Library and other Government Office
Building) in September of 1998. City staff representing Traffic
Operations and Transportation Planning have reviewed the TIS in
relation to this Project Development Plan and have indicated the
transportation Level of Service standards are met for automobile
traffic, bicycles, pedestrians.
3. Transit Facilities Standards [3.6.5] — Directly across Mason Street
to the east of this site is currently a major Transfort hub called the
Downtown Transit Center. This Downtown Transit Center is
planned to be expanded to not only accommodate local busses, but
also national/regional busses, taxis, and bicycle check-out services.
F. Compact Urban Growth Standards [3.7]
1. Adequate Public Facilities [3..7.3] — As required, the level of service
standards are satisfied for the following public facilities:
transportation, water, wastewater, storm drainage, fire and
emergency services, and electrical power.
4. Neighborhood Information Meeting
A combined neighborhood information meeting was conducted on September 13,
1999 for this project and the,proposed Transit Center project. Minutes of the
neighborhood meeting are attached. There were primarily only questions about
how the building will look, stormwater issues, traffic impacts, and the timing of
construction. The owner of the glass store just west of this site had a few
Civic Center Office Building, Project Development Plan # 29-99
March 2, 2000 P & Z Hearing
Page 13
(a) Orientation to a Connecting Walkway [3.5.3(B)(1)]
- The main entrance of the building faces and
opens directly onto a street sidewalk, thereby
satisfying this requirement.
(b) Orientation to Build -to Lines for Street -front
Buildings [3.5.3(B)(1)] — The building is set back
10 feet from the property line of both Mason Street
and Laporte Avenue which is in conformance to
the setback requirements along arterial streets.
The location of the build -to line allows the building
to form visually continuous, pedestrian -oriented
street -fronts with no vehicle use areas between
the primary building faces and the streets.
• Variation in Massing [3.5.3(C)] — The project provides the
required variation in massing by integrating changes in
height and structural projecting and recessed elements
both vertically and horizontally along the building
facades.
• Character and Image [3.5.3(D)] —
(a) Site -Specific Design [3.5.3(D)(1)] - As required
the building contributes to the uniqueness of
the Civic Center Subdistrict of the Downtown
Zoning District.
(b) Minimum Wall Articulation [3.5.3(D)(2)] — The
building bays are clearly articulated by
architectural features such as fenestration
patterns, columns, and column -like ribs,
thereby providing the required architectural
interest and visual variety to the facades.
(c) Entrances [3.5.3(D)(4)] — The primary entrance
is clearly articulated with a major columned
portico -type entry feature and thereby satisfies
this standard.
Civic Center Office Building, Project Development Plan # 29-99
March 2, 2000 P & Z Hearing
Page 12
1. Historic and Cultural Resources [3.4.7] — The new building is in
character with existing historic structures of the downtown area, but
as required is not an imitation of historic styles. The use of the
brick, sandstone, lintels, and articulated cornices help to blend in to
the established character of the historic architecture primarily
present in the historic commercial store fronts along College
Avenue in the downtown area.
D. Building Standards [3.5]
1. Building and Project Compatibility [3.5.1]
• Architectural Character [3.5.1(B)] — As required, the
development is compatible with the established
architectural character of the downtown area.
• Building Size, Height, Bulk, Mass, Scale [3.5.1(C)] —As
required, the building is similar in size and height to the
mass and scale of other structures on adjoining blocks
(i.e. Justice Center & Civic Center Parking Structure).
• Building Orientation [3.5.1(D)] —The primary fagade and
primary entry are oriented toward Mason Street, thereby
satisfying this requirement.
• Building Materials [3.5.1(F)] — Building materials are
similar and compatible to the materials already being use
in the neighborhood. Windows are individually defined
using a variety of frames, sills and lintels for adequate
articulation.
• Outdoor Storage Areas/Mechanical Equipment [3.5.1(J)]
— Utility meters, mechanical equipment, trash enclosures,
transformers, vaults and conduits have all been located
to minimize visual impacts, and have been adequately
screened.
2. Mixed Use, Institutional and Commercial Buildings [3.5.3]
• Relationship of Buildings to Streets, Walkways and
Parking [3.5.3(B)]
Civic Center Office Building, Project Development Plan # 29-99
March 2, 2000 P & Z Hearing
Page 11
occupancy. The proposed parking lot provides 0.88
parking spaces per 1000 square feet, therefore the plan
satisfies this requirement. The on -site parking is intended
for fleet parking and customer parking only. Staff parking
will be accommodated in the Civic Center Parking
Structure.
• Handicap Parking [3.2.2(K)(4)] — Based on the total
number of parking spaces provided in the parking lot, 3
handicap parking spaces are required. The site plan
provides 4, thereby satisfies this requirement.
• Parking Stall Dimensions [3.2.2(L)] — All spaces in the
proposed parking lot meet or exceed the required
minimum parking stall dimensions.
3. Site Lighting [3.2.4] — The lighting design as well as required
maximum and minimum lighting levels are in accordance with the
requirements of this section.
B. Engineering Standards [3.3]
1. Lots [3.3.1(B)] —The general layout of lots, roads, driveways,
utilities, drainage facilities and other services are designed in a way
that allow in interconnected street system to occur and
accomplishes the intent and purposes of the LUC.
2. Water Hazards [3.3.3] — The Stormwater Capital Projects staff has
designed and construction is underway for the Howes Outfall which
will ultimately be an underground stormwater drainageway that will
mitigate much of the flooding of the downtown area. The
stormwater development review staff have reviewed the proposed
project development plan, ensured that it is coordinated with the
Howes Outfall project, and also have ensured that it meets all
applicable Stormwater development review standards.
3. Engineering Design Standards [3.3.5] — This project complies with
all design standards, requirements, and specifications for all of the
commenting departments and agencies.
C. Environmental, Natural Area, Recreational and Cultural Resource
Protection Standards [3.4]
Civic Center Office Building, Project Development Plan # 29-99
March 2, 2000 P & Z Hearing
Page 10
• Access and Parking Lot Requirements [3.2.2(D)] —
Vehicles can enter the parking lot from a one way
entrance off Mason Street, or from the alley. All exiting
vehicle traffic is directed to the alley. Access
requirements are therefore met. The parking lot is
properly paved, and adequately lit in accordance with this
standard.
• Parking Lot Layout [3.2.2(E)] — As required in this
section, the proposed parking lot addresses the following
issues:
(a) The circulation routes within the parking lot are
well defined.
(b) Standard traffic control signs are used to direct
traffic where necessary within the parking lot.
(c) Landscaped islands with raised curbs are used to
define parking lot entrances, the ends of all
parking aisles and the location of internal access
drives. These islands also provide pedestrian
refuge areas and incorporate walkways.
(d) Points of conflict between pedestrians, bicycles
and vehicles are minimized, and where they
conflict, proper crossing enhancements have been
provided.
(e) As required, there are no parking bays that extend
more than fifteen spaces without an intervening
landscape island or landscape peninsula.
• Setbacks [3.2.2(J)] — The proposed parking lot is setback
from the Mason Street and Maple Street by more than 15
feet, and is setback from the alley by more than 5 feet.
The parking lot setbacks therefore meet the standard set
forth in this section.
• Required Number of Spaces for Type of Use [3.2.2(K)] —
General office uses allow a maximum of 3 parking
spaces per 1000 square feet of gross leasable of the
Civic Center Office Building, Project Development Plan # 29-99
March 2, 2000 P & Z Hearing
Page 9
bicycle areas by the use of separated sidewalks, grade
separations, pavement markings, refuge areas within
landscape islands in the parking lot, and designated on -
street bike lanes.
• Curbcuts and Ramps [3.2.2(C)(2)] —Ramps are located
where sidewalks meet the crosswalks at street
intersections, where the sidewalks cross driveways, and
where sidewalks cross the alley, and therefore this
standard is being met.
• Bicycle Facilities [3.2.2(C)(4)] —Adequate bicycle parking
is being provided in locations and designs consistent with
the requirements of this standard.
• Walkways [3.2.2(C)(5)] — Walkways within the site
directly and continuously connect points of pedestrian
origin and destination. Where primary pedestrian ways
cross the parking lot, priority is placed on the pedestrian
realm by locating the walkways primarily within
landscaped islands, and providing painted crosswalks
where the walkway crosses parking lot drive aisles. This
standard is therefore satisfied.
• Direct Access to Pedestrian and Bicycle Destinations
[3.2.2(C)(6)] — The transit center will be located directly to
the east of this site across Mason Street, the Justice
Center is located directly to the south of this site, and the
employee parking is located in the Civic Center Parking
Structure located southeast from the site diagonally
across the intersection of Mason Street and Laporte
Avenue. Enhanced pedestrian crosswalks are provided
across the intersections of both Mason Street and
Laporte Avenue to get pedestrians from the site to the
destinations listed above. City Hall is located a block to
the east of the site. A major east -west pedestrian spine
is planned for the mid -block connection of this building to
City Hall. The on -site portion of this pedestrian spine is
provided. A modification of standard has been requested
to the requirement of a mid -block crossing of Mason
Street (see comments on Division 4.12 above).
Civic Center Office Building, Project Development Plan # 29-99
March 2, 2000 P & Z Hearing
Page 8
• Minimum Species Diversity [3.2.1(D)(3)] — Based on the
total proposed number of trees of 64, the applicant would
be allowed to have up to 16 of any one species, but has
only proposed a maximum of 14 of a single species,
therefore the landscape satisfies the minimum species
diversity requirement.
• Foundation Plantings [3.2.1(E)(2)(d)] — All high visibility
sections of building walls have planting beds at least 5
feet in width along more than 50% of the high -visibility
walls. The landscape plan therefore satisfies the
foundation plantings requirement.
• Parking Lot Perimeter Landscaping [3.2.1(E)(4)] — The
parking lot abuts both Maple Street and Mason Street.
Trees are provided along the parking lot's frontages with
these two streets at the required ratio of one tree per 25
lineal feet of street frontage. The parking lot is also
screened by plant material along the alley by shrubs in
accordance with the requirements of this section. The
landscape plan therefore satisfies the parking lot
perimeter landscaping requirement.
• Parking Lot Interior Landscaping [3.2.1(E)(5)] — The
parking lot area on the site plan is required to devote at
least 6% of the area of the parking lot to landscaped
areas. The proposed parking lot devotes 8.3% of its area
to landscaped areas.
• Screening [3.2.1(E)(6)] — Landscape and building
elements are placed to adequately screen areas of low
visual interest and visually intrusive site elements
including the loading dock and trash enclosure areas.
• Utilities [3.2.1(K)] —The required separations are
provided between trees and utilities (street lights,
underground water lines, underground sewer lines, etc.).
2. Access, Circulation and Parking [3.2.2]
• Safety Considerations [3.2.2(C)(1)] —As required,
pedestrian areas are separated from vehicle areas and
Civic Center Office Building, Project Development Plan # 29-99
March 2, 2000 P & Z Hearing
Page 7
in not being requested (providing 30 foot spacing
where 40 foot spacing would otherwise satisfy the
spacing criteria).
(b) Staff agrees with the applicant that providing an
unobstructed view corridor to the main entrance
from Mason Street will enhance the visual quality
and continuity within and between developments.
Adjacent and nearby developments include the
transit center to the east, the Civic Center Parking
Structure to the southeast, the Justice Center to
the south, and City Hall to the west.
(c) The issues of screening and mitigation of potential
conflicts, the enhancement of outdoor spacing, the
reduction of stormwater runoff, and the mitigation
of air pollution are all equally well addressed with
the same given number of trees regardless of
whether two of the trees are located in front of the
main entrance or elsewhere on the site.
Section 3.2.1(N)(2) Alternative Compliance Review
Criteria states that "in reviewing the proposed alternative
plan for the purposes of determining whether it
accomplishes the purposes of this Section, the decision
maker shall take into account whether the alternative.
preserves and incorporates existing vegetation in excess
of minimum standards, protects natural areas
neighborhood continuity and connectivity, fosters
nonvehicular access, or demonstrates innovative
design and use of plat materials and other landscape
elements." Because the reason for the alternative
compliance request is to emphasize the architectural
design of the building entrance, and because the
alternative plan provides more trees than otherwise
would have been required to be provided, staff has
determined that the proposed alternative plan does
in fact demonstrate innovative design and use of
landscape elements.
Civic Center Office Building, Project Development Plan # 29-99
March 2, 2000 P & Z Hearing
Page 6
well or better than would a plan which complies with
the standards of this section.
The applicant has intentionally left out street trees in the
area adjacent to the main entrance along Mason Street in
order to emphasize a significant level of architectural
detail of the entry architecture. There are no physical
constraints that would prevent the standard from being
met. The applicant is seeking alternative compliance for
the tree spacing standard to create an unobstructed view
of the main building entrance from Mason Street. The
street tree standard requires the applicant to provide
street trees at least every 40 feet in the parkway between
the building and Mason Street. Mitigation is provided in
two ways. First, although the spacing can be as far apart
as 40 feet spacing intervals, the applicant is proposing
the street trees in the remaining area between the
building and Mason Street to be spaced at 30 foot
spacing intervals. Second, the applicant is provided
additional trees around the on -site water quality pond.
The "purpose" of the section to which the alternative
compliance language refers, is listed in Section 3.2.1(B),
which states, "the intent of this Section is to require
preparation of landscape and tree protection plans that
ensure significant canopy shading to reduce glare and
heat build-up, contribute to visual quality and continuity
within and between developments, provide screening and
mitigation of potential conflicts between activity areas and
site elements, enhance outdoor spaces, reduce erosion
and stormwater runoff, and mitigate air pollution.
Staff has determined that the alternative design satisfies
the purposes of this Section equally well as a plan that
satisfies the standards:
(a) Glare and heat build-up are reduced equally well,
on the average across the site, with a
redistribution of more than the required minimum
amount of trees in various locations across the
site. The heat build-up along the Mason Street
sidewalk will be addressed by having a tighter tree
spacing in the areas where alternative compliance
Civic Center Office Building, Project Development Plan # 29-99
March 2, 2000 P & Z Hearing
Page 5
design for the Mason Street Corridor (not designed by
the applicant) has a two-way designated bicycle corridor
along the west side of Mason Street that is separated
from the adjacent automobile traffic lane by a low wall.
The transportation planning department has made it clear
that a mid -block crossing in this location would not work
well with the bike lane and low wall design.
3. Article 3 of the Land Use Code — General Development Standards
The Project Development Plan complies with all applicable General
Development Standards as follows:
A. Site Planning and Design Standards [3.2]
1. Landscaping and Tree Protection [3.2.1]
• Full Tree Stocking [3.2.1(D)(1)(c)] — Full tree stocking is
required in all landscaped areas within 50 feet of any
building along high use or high visibility sides. Full tree
stocking is formal or informal groupings of trees planted
at 30' to 40' spacing intervals for canopy shade trees, or
at 20' to 30' spacing intervals for coniferous evergreens
or ornamental trees. The proposed site plan satisfies this
standard.
• Street Trees [3.2.1(D)(2)] — The applicant is requesting
alternative compliance to Section 3.2.1(D)(2)(a) of the
Land Use Code where it states, "whenever the sidewalk
is separated from the street by a parkway, canopy shade
trees shall be planted at thirty-foot to forty -foot spacing
(intervals) in the center of all such parkway areas. Such
street trees shall be placed at least eight (8) feet from the
edges of driveways and alleys, and forty (40) feet away
from any street light." Section 3.2.1(N)(1) Alternative
Compliance. Procedure states that upon the request by
the applicant, the decision maker may approve an
alternative landscape plan in lieu of a landscape plan that
meets the standards of this section if the decision
maker finds that the proposed alternative plan
accomplishes the purposes of this Section equally
Civic Center Office Building, Project Development Plan # 29-99
March 2, 2000 P & Z Hearing
Page 4
The applicant argues and staff concurs that eliminating
the east -west civic spine mid -block pedestrian
crossing across Mason Street would not be
detrimental to the public good. Transportation
Planning staff and Engineering staff have explained that
it would be safer for pedestrians to not have the mid -
block crossing in this location, therefore the granting of
the modification would not be detrimental to the public
good.
The applicant argues and staff concurs that the granting
of the modification would not impair the intent and
purposes of the LUC. The "purpose" of the section for
which the modification is requested, states in section
4.12(A) of the LUC, "The Downtown District is intended to
provide a concentration of retail, civic, office and cultural
uses in addition to complementary uses such as hotels,
entertainment and housing.... The development
standards for the Downtown District are intended to
encourage a mix of activity in the area while providing for
quality development that maintains a sense of history,
human -scale and pedestrian -oriented character." The
intent to provide a pedestrian -oriented character is not
impaired by the granting of the modification request
because the alternative plan provides well defined cross-
walks at the Laporte Avenue/Mason Street and Maple
Street/Mason Street intersections. The provided
crosswalk locations are not as direct as the mid -block
crossing would be, however the pedestrian -oriented
character of the project is not impaired with the
alternative design.
The east -west "Civic Spine" is shown in the Downtown
Civic Center Master Plan to cross Mason Street at a mid -
block location half way between Laporte Avenue and
Maple Street. The applicant argues, and staff concurs
that there are two reasons why this pedestrian
crossing is not possible. The first reason is that there
is a railroad track that goes down the center of Mason
Street, and the railroad company has made it very clear
that they do not want pedestrians to cross the tracks in
any location other than at the designated crosswalks at
street intersections. The second reason is that the
Civic Center Office Building, Project Development Plan # 29-99
March 2, 2000 P & Z Hearing
Page 3
B. Dimensional Standards [4.12(D)(2)] — The Project Development
Plan complies with the required lot dimensions, FAR, setbacks, and
height restrictions.
The PDP meets the applicable Development Standards [4.12(E)] as
follows:
A. Facades [4.12(E)(2)] — The proposed facades comply with these
requirements because there are no blank walls proposed, because
the building is designed to promote outdoor activity in an entry
arcade/courtyard, and because the windows are individually
defined.
B. Site Design [4.12(E)(3)] — As required, parking lots to not dominate
the frontage of Mason Street or Laporte Avenue which are both
pedestrian -oriented streets. The parking lot is located in the side
yard (north side) of the building.
C. Special Provisions — Civic Center Subdistrict [4.12(E)(5)]
• Civic Spine [4.12(E)(5)(a)] - The applicant is requesting
a modification to Section 4.12(E)(5)(a) of the Land
Use Code where it states, 'All development shall
incorporate the concept of the `civic spine' as described
in the Downtown Civic Center Master Plan, allowing for
continuous north -south and east -west pedestrian
connections."
Section 2.8.2(H) of the Land Use Code states that the
Planning and Zoning Board may grant a modification
request if they find that the granting of the modification
would:
(a) not be detrimental to the public good, and
(b) not impair the intent and purposes of the LUC, and
(c) by reasons of extraordinary and exceptional
situations unique to such property, the strict
application of the standard sought to be modified
would result in unusual and exceptional practical
difficulties, provided that such difficulties are not
caused by the act or omission of the applicant.
Civic Center Office Building, Project Development Plan # 29=99
March 2, 2000 P & Z Hearing
Page 2
5. The alternative compliance request to section 3.2.1(D)(2)
accomplishes the purposes of this Section equally well or better than
would a plan which complies with the standards of this section.
COMMENTS:
Background
The surrounding zoning and land uses are as follows:
N: D (Civic Center Subdistrict); Maple Street, Vacant city
owned property,
S: D (Civic Center Subdistrict); La Porte Avenue, Larimer
County Justice Center, City and County office
buildings,
SE: D (Civic Center Subdistrict); Intersection of La Porte Avenue
& Mason Street, Civic Center Parking Structure,
D (Old City Center Subdistrict); Retail, offices, municipal
court,
E: D (Civic Center Subdistrict); Mason Street, existing rail road
tracks & railroad switch, historic freight depot,
restaurant, retail, car wash, city offices,
W: D (Civic Center Subdistrict); existing retail, city offices,
Washington Park, City Hall,
The property is located in block 32 of the original City of Fort Collins which
was platted in January, 1873.
2. Division 4.12 of the Land Use Code. (D) - Downtown Zone District
The proposed use of "offices" are permitted in the Civic Center Subdistrict
of the (D) - Downtown zoning district subject to Type 1 administrative
review (this application is being reviewed by the Planning and Zoning
Board due to a request for a modification of a standard to the LUC, and
because the building is larger than 50,000 square feet).
The PDP meets the applicable Land Use Standards [4.12(D)] as follows:
A. Floor Area [4.12(D)(1)] — Because the total proposed floor area is
greater than fifty thousand square feet the Project Development
Plan is subject to Planning and Zoning Board review.
ITEM NO. 7
MEETING DATE 3 2 00_
STAFF Troy Jones
City of Fort Collins PLANNING AND ZONING BOARD
STAFF REPORT
PROJECT:
APPLICANT:
Civic Center Office Building, Project Development
Plan, #29-99
Roger Sherman
BHA Design
4803 Innovation Drive
Fort Collins, CO 80525
OWNER: City of Fort Collins
Project Manager - Jack Gianola
117 Mason Street
Fort Collins, CO 80524
PROJECT DESCRIPTION:
fo
y�(o/ao
�j 155'L5 to
C;J;( 5PIy-&
Z\ Sit lfaS
3iJDtf'eL+ Arce5s +o
5 i c M cl.e Pt S+I"0+tPAS
This is a proposal to build a 71,515 square foot office building at the northwest
corner of Mason Street and La Porte Avenue. Because of the size of the
building, it will be subject to Planning and Zoning Board review. The site is in the
Civic Center Sub -district of the (D) - Downtown Zoning District.
RECOMMENDATION: Approval
EXECUTIVE SUMMARY:
1. The proposed land uses are permitted in the (D) Downtown zone
district.
2. The Project Development Plan complies with all applicable district
standards of Section 4.12 of the Land Use Code, (D) Downtown zone
district except 4.12(E)(5)(a) for which a modification is being
requested.
3. The Project Development Plan complies with all applicable General
Development Standards contained in Article 3 of the Land Use Code
except 3.2.1(D)(2) for which alternative compliance is being requested.
4. The modification request to section 4.12(E)(5)(a) satisfies the
requirements and criterion established in 2.8.2(H) for the granting of
modifications.
COMMUNITY PLANNING AND ENVIRONMENTAL SERVICES 281 N. College Ave. PO. Box 580 Fort Collins, CO 80522-0580 (970) 221-6750
PLANNING DEPARTMENT