HomeMy WebLinkAboutPEAK VIEW SUBDIVISION - PDP (RE-SUBMITTAL) - 26-00 - SUBMITTAL DOCUMENTS - ROUND 2 - PROJECT NARRATIVERock must be light gray in color (i.e. river rock). Multicolored rock (i.e. ping
granite, dark red lava rock or other colors are discouraged). Large six-inch (6")
in diameter or greater river rock, moss rock, or other "feature" rock may be
used as part of the landscape.
Wood mulch and rock should be placed over a weed barrier fabric and be kept
in place with steel, plastic or brick edges. All edges should be installed in such
a way as to prevent damming of water near the foundation. The additions of
concrete curb -type edges are discouraged.
Roofs
The ARC shall approve all roof material
HAZARDOUS MATERIALS
Corrsives, flammable liquids, reactive or toxic materials (as defined in the
Uniform Fire Code) if
used, or stored, or handled on site must have a
Hazardous Materials impact Analysis (HMIA) completed and supplied to the
Planning department and the Fire
Department. FCLUC3.4.5(C)
WATER SUPPLY
Fire hydrants are required with a maximum spacing of 600 feet along an
approved roadway. Each hydrant must be capable of delivering 1500 gallons of
water per minute at a residual pressure of 20 psi. Hydrant shall be of an
approved type as defoned by the water department and the fire department. No
building can be greater than 300 feet from a fire hydrant. 97FC901.2.2.2
SPRINKLER REQUIREMENTS
These multi -family proposed buildings shall be fire sprinklered.
color, and texture. Replacement material shall be the same quality or better,
unless otherwise approved by the ARC, and shall match the original texture and
color. Roof pitches shall be a minimum of 5:12 on primary structures and 4:12
on secondary structures. Roof overhangs shall be a minimum of 18" on primary
structures and 12" on secondary structures.
yards. At the time of, but not later than (1) year following the closing of first
occupancy of a home, whichever occurs first, the rear and side yards shall be
suitably landscaped with grass, shrubs and trees.
Fencing
Fencing at Peak View Estates is subject to review and approval by ARC. Fencing
is allowed to provide a sense of security, provide confinement for family activity,
and yet avoid complete physical and visual enclosure. It is intended that plant
material integrate the fencing into the community to enhance desired visual
enclosure. When used fences shall be considered architectural extensions of a
home. Fencing is prohibited in the front yards of homes. Side yard fencing shall
not extend more than 4' beyond the face of the primary structure.
Site Drainage and Grading
Structure and landscaping elements shall be placed on the property so that the
existing topography shall not be disturbed. Finish grading shall prevent
pounding or washing of water into the site or adjacent propertied. Drainage
shall be directed away from all structures. Newly graded areas shall be
protected agents soil erosion. Owners are encouraged to utilized soil engineers
and landscaping professionals to help ensure proper drainage is maintained.
Plant Materials
Plant materials used in the landscaping should be native or naturalized to the
area. Plant material selection should be made from locally available nursery or
garden center stock. The Colorado Nurseryman's Association Rocky Mountain
Plant Guide lists acceptable Materials.
Lawn
Lawn areas should be kept at least six (6) feet away from the foundation of the
home or as recommended by a professional soil engineer or landscape
professional, to ensure proper drainage is maintained.
Foundation Planting
Planting beds should surround the foundation of each structure and provide a
minimum of two (2) feet of planting area from the homes' foundation to the lawn
areas to ensure proper drainage. In all instances, watering near the foundation
should be a minimal (e.g. drip irrigation systems) to avoid possible structural
damage to the dwelling unit.
Front Yards and Edging
Landscaping in the front yards of Traditional Single-family homes shall be
installed by the home builder, and shall be maintained by the homeowner in a
condition at least as good or as better than the condition at the time of
installation. The additions of concrete curb type edges are discouraged.
Rock and Mulch
Planting beds visible from an internal public right-of-way or private street may
utilize wood mulch or rock. Wood mulch provides a favorable environment for
plants, reduces irrigation requirements and minimizes long-term maintenance
cost.
silver finished aluminum doors and windows are not acceptable. Architectural
"add-ons" appliques or obvious simulation materials are not accepted.
Building Projections
All projections including, but not limited to, chimney flues, vents, gutters, down
spouts, porches, railings and exterior stairways, shall match the color of the
surfaces from which they project or shall be an approved color. Vents are to be
painted to blend with the roofing.
Garages
Garage doors shall be painted the same color as most of the dwelling not a
contrasting color.
Antennas/Satellite Dishes/Solar Panels
ARC allows one satellite dish per home, as approved. Large satellite dishes are
prohibited in favor of the smaller (18") mini dish varieties unless otherwise
approved by the ARC. Solar panels shall be ground mounted or laid flat on
same plane as the roof. Solar panel shall not project above the pitch of the roof.
Exterior mounted antennas are prohibited.
Building Code
All structures will conform to all applicable building codes and ordinances.
Approval by the ARC does not constitute or imply compliance with such codes
and ordinances.
LANDSCAPE DESIGN
Purpose and Intent
The landscape design criteria is intended to supplement the Site Planning and
Architectural Design criteria in order to integrate residential structures into the
community. Additionally, landscaping should have compatibility with adjacent
properties. The project's streetscape, and ultimately transition into perimeter
landscaping. The ARC reserves the right to require landscape components as a
part of the architectural approval, if in the option of the ARC, the architectural
design needs specific assistance to meet the intent of the design guidelines.
Timing and Components
Front yard landscaping for the Traditional Single Family and multi -family
dwelling units shall be provided by the homebuilder as part as the initial sales
package. All other landscaping for traditional single family homes (i.e. rear and
side yard landscaping) shall be obligation of the homeowner and shall be
installed within one year of the property purchase.
For traditional single-family homes, all landscaping, including front, side and
rear yards, shall be the obligation of the homeowner and shall be installed
within one year of property purchase.
All individual homeowners shall maintain all landscaping on individual
residential lots. The ARC requires complete landscaping plans for rear and side
accessory structures must be painted the same as the primary structure, and
utilize the same roofing materials.
Concrete Driveways
Concrete driveways and parking areas are not to be expanded without prior
written approval of the ARC. No RV front yard on -site parking will be allowed.
Dog Runs
Dog runs will be allowed if they can be reasonably isolated and screened from
adjacent properties. Local ordinances regarding noise, order and other
nuisances will be in effect.
Gardens
Vegetable gardens will be allowed in the rear yard only, except as approved by
the Architectural Control Committee. Flower gardens are encouraged in the
front or side as a compliment to the landscape installed by builders.
Architectural Design
The architectural character of the homes in Peak View is intended to reflect
regional character with a variety of interesting and compatible relationships of
form, texture and style. Additionally, economic factors, environmental concerns,
and construction practices prevalent in the industry are important influences.
These DAS are intended to promote a high level of design quality, assure
compatibility between residential products within the community, and quiet
character and form. Together, these key components comprise an essential part
of the Peak View image.
There is not single "correct" architectural style for homes or commercial
structures in Peak View, yet all design elements are expected to be related
clearly to one another in order to establish a unified design theme.
This identification and compatibility with in the established architectural theme
will be achieved at all levels of design identification, including individual
dwellings, commercial center structures and "street scenes," to create a totally
unified and architecturally harmonious community.
Color
The color of exterior material will generally be subdued to blend with the color
of the natural landscape. Generally muted color tones are recommended,
although occasionally accent colors used judiciously and with restraint may be
allowed. Use of highly chromatic or "bright" colors is to be avoided.
Materials
The front of each single family and multi -family home shall have a minimum of
25% brick, stone or dryvit, excluding the area of the garage door. Exterior
surfaces shall blend and be compatible with the community and the landscape.
Use of brick, wood stucco and stone is preferred. Exposed concrete blocks,
painted concrete, multicolored masonry, mirrored glass, metal siding,
prefabricated metal buildings, simulated brick, unnatural brick tones, and
Purpose and Intent
The following Design and Architectural Standards ("ADS") have been prepared
to ensure that the goals and vision are realized for properties in the Planned
community known as Peak View. The purpose of these ADS is to provide
specific design criteria for the subsequent improvement or modification of
landscape within the community. The ADS are designed to establish and
maintain a quality community appearance, assure compatibility, direct
character and form, and enhance value.
All residential development within Peak View Estates is to abide by the
applicable criteria established by these DAS in addition to the development
standards established by the City of Fort Collins.
Community Concept and Character
The community design concept for Peak View Estates provides for a
development of single family and attached multi -family dwelling units, centered
by a common open space. An extensively landscaped perimeter treatment is
punctuated by bicycle path
connecting West Elizabeth to Overland Park.
Relationship of the Design and Architectural Standards (DAS) to other
regulations
The DAS is not intended to supersede applicable federal, Colorado, or Fort
Collins codes or ordinances. In case of conflict or discrepancy or for subjects
not addressed in the DAS, the more restrictive DAS, governing agencies, coeds
and/or regulations shall take precedence.
The DAS are to be used by owners when modifying or upgrading homes or
landscaping on individual residential properties within Peak View Estates.
The DAS will also be used by the Peak View Estates Architectural Review
Committee ("ARC') in reviewing proposals to determine their relative
conformance to the overall design objectives and criteria. The Homeowners
Assoc. shall be FHA Certified by an Attorney.
The DAS are intended to cover each site -specific or lot -specific issue, and
community issues such as edge treatments, and relationships to adjacent land
uses.
SITE PLANNING AND DESIGN
Accessory Structures
Accessory structures, i.e., "storage sheds," are not allowed on any property
without specific approval of the ARC. The home builder and homeowner is
encouraged to provide for storage space in garages; provided, however, such
storage may not interfere with the primary use of garages. Any accessory
structure must be architecturally compatible with the residence or home,
EXCEPTIONS TO REGULATORY REQUIREMENTS AND CODES
Peak View PUD will comply with all City of Fort Collins Standards, with the
following exceptions:
The lot size for single-family residential lots shall be a minimum of 4,000 S.F.
with an average lot size of approximately 5535 S.F..
Front setback for the traditional homes shall be minimum of 15' and 0' rear
setback to the garage.
Side setbacks of single-family detached homes shall be a minimum of 5' with a
minimum of 10' between adjacent structures.
Side setbacks of traditional multi -family dwelling units shall be zero -lot line on
each side.
IMPLEMENTATION
It is anticipated that this project will be developed over a 2-3 year period
beginning in the spring of 2001 and competed in the fall of 2004. The master
declaration of covenant controls and restrictions shall govern the entire Peak
View Estates PDP Subdivision. This project subject to the Peak View Estates
PDP Subdivision Architectural Guidelines and Control Committee. All
applications for a letter of approval shall accompany building permits related to
architecture from the Architectural Control Committee.
ARCHITECTURAL AND RESIDENTIAL LOT DEVELOPMENT STANDARDS
For information only, these standards will not administered by the City of Fort
Collins, but will be reviewed and approved by the Architectural review
Committee.
The following is intended as an outline of architectural and residential lot
development standards that will apply to the construction if single family and
multi -family dwelling units with Peak View Estate, PDP Subdivision.
Prototypical Architectural Elevations have been prepared with these plans to
help illustrate the aforementioned design standards for the traditional multi-
family dwelling units. The covenants for the development will require that a
homeowner or builder submit to Architectural Review Committee, plans and
specifications for their review and approval prior to the construction of any
improvements on any single family detached lot.
The applicant must submit to the Building Department a letter of approval
issued from the Architectural Review Committee, related to all said
construction, prior to receiving a Building Permit from the City of Fort Collins.
INTRODUCTIONS
will be oversized to accommodate any surface runoff from the southern portion
of this development. On site drainage will be detained and allowed to discharge
at the 100-year historic undeveloped rate per the drainage master plan.
LANDSCAPING
The project will be landscaped with regionally appropriate plant materials. In
open space and buffer yard areas a naturalistic design approach shall be used.
These areas shall include informal plantings of coniferous and deciduous trees
with large drifts of shrubs. Turf areas will incorporate low water use draught
tolerant seed and sod varieties.
Along the entry streets and streets that border the subdivision green,
Incorporating a detached walk and tree lawn, the developer shall plant
deciduous street trees at approximately 40' on center. A variety of street tree
species shall be used throughout the development for visual interest and
horticultural stability, thus creating a canopy effect as the project matures.
The proposed street tree planting is intended to draw attention to common
greens that are located in the center of the development.
Each individual homeowner shall be responsible for residential lot landscaping
and maintenance. Homeowners shall be required to submit a landscape plan
for the entire property to the Architectural Review Committee for their approval
prior to doing any landscaping. No more than 20% of the lot (excluding
building footprint) can be non -Irrigated planting.
Homeowners adjacent to the tree lawn areas shall be responsible for planting
the tree lawn with Bluegrass Sod (no other plant material will be allowed) and
maintaining the tree lawn sod and the street trees.
The developer shall plant the tree lawn with street trees as shown on the
landscape plan. In addition, the home builder of each lot shall be responsible
for planting one additional tree per lot In the front of each home and two
additional trees per lot for all corner lots, one in front and one on the side of
each home. The location of these trees are at the homeowners discretion, but
must be illustrated on the landscape plan submitted to the Architectural
Review Committee for approval prior to planting the trees.
All common open space areas, landscape medians, landscape within the public
right-of-way, streetscapes, parked, detention ponds, and entry features shall be
planted and irrigated by the developer and maintained by and common
Homeowners Association.
The developer may investigate the potential for utilizing raw water sources for
open areas irrigation purposes.
Project entry sign walls will be constructed at each of the project entries as
shown on the plans. Each of the entry sign walls shall incorporate a consistent
project entry theme utilizing a stone entry wall. Appropriately sized project
signage shah be applied to each wall, at each entry. For added visual interest
and nighttime visibility, the primary entry sign walls may be illuminated.
Local Residential roads shall be 36' wide within a 57' right-of-way. These
roadways shall include 10' travel lanes and 8' shared parking and on -street
bike lanes on each side. All internal residential roads have 6' tree lawns with
detached sidewalks on both sides of the road, within the right-of-way.
Public Facilities Providers
Police City of Fort Collins
Fire and Rescue Poudre Fire Authority
Schools Poudre Valley School District
Parks City of Fort Collins
Public Utilities
All basic utilities required for this development have been extended to the site
or are near the property and are available for extension to the property.
Adequate capacity currently exists within the City's infrastructure utilities to
serve the project.
Water - City of Fort Collins
Existing 18" water main in West Elizabeth. Water mains will be installed in all
streets and connected with water mains in Pleasant Valley to complete the
internal looping of the service.
Sanitary Sewer - City of Fort Collins
Service - 8" sanitary sewer service exists in Pleasant Valley road on the west
and east side of the proposed development. On -site sanitary sewer will be
routed to a future sanitary sewer connection located at the southeast corner of
the development, located in Pleasant Valley Road.
Electric - City of Fort Collins
Service - service exist in West Elizabeth Street and will be extended along
internal residential streets and distributed to the site.
Gas - Public Service of Colorado
Service - service exists in West Elizabeth Street and will be extended along
internal residential streets to bring service the site.
Telephone - OWest (US West)
Service - service exists in West Elizabeth Street and will be extended to internal
residential streets and distributed to the site.
Storm Drainage
On -site and off -site storm drainage will be routed to an on -site detention pond
via a system of surface swales, area inlets, roadways and storm sewer pipe.
Storm drainage will be detained in a grass lined detention pond and discharged
into an existing off -site conveyance system in Overland Park. These off -site
facilities have been sized to account for the Peak View drainage. No offsite
drainage improvements are anticipated because the necessary on -site detention
Project Development Plan Narrative
Project Location
Peak View Estates, PDP is a 9.206-Acre Planned Residential Community located
in western Fort Collins, bounded on the north side by West Elizabeth Street
located between the Siena PUD subdivision on the east and Lory Ann Estates
on the west. Overland Park and Pleasant Valley Road bound the south.
Land Use
Peak View Estates features a diverse offering of housing opportunities. The
plan includes spacious single family home sites and alley access multi -family
dwelling units. The community is situated around open spaces between multi-
family units and with walking corridors lined with canopy street trees. The
main entrance from Elizabeth includes.
pedestrian corridors for access to Overland Park, detached sidewalks with tree
lawns for landscaping buffers that insure a high level of visual quality for
residents as well as the local community.
The traditional neighborhood is characterized by multi -family dwelling units
with garages in the rear of the dwelling units, which are accessed by a private
roads. The streetscape is designed for people, with detached sidewalks and
tree -lined colonnades. Residential setbacks are minimized so that the
architecture of the multi -family dwelling units with their front porches and
entries create opportunities for social interaction with the neighborhood,
creating safer and more active streets for people. Shorter, walk able blocks with
frequent intersections help to slow and calm traffic.
Peak View Estates is conveniently accessible to all areas of Fort Collins with its
many retail, restaurant and shopping services and schools. Peak View Estates
is within walking and biking distance to the Colorado State University and
public trail system. Peak View Estates is also within walking distance of
Overland Park. The developer of Peak View Estates is committed to building
homes of quality value and distinction as well as building a community "worth
coming home to".
Circulation
Peak View Estates primary access shall be from West Elizabeth Street with
inter -connectivity with Siena PUD and Overland Tail Farms Phase II via
Pleasant Valley Road.
Extensive road improvements to the south half of West Elizabeth are proposed
adjacent to the development. This will facilitate vehicular, pedestrian and
bicycle access to and from the site. These improvements will be made along the
entire frontage of the development from Lory Ann Estates to Siena PUD.
Internal vehicular, pedestrian and bicycle circulation shall be accomplished
with the development of local residential roads. Public roadways shall be
developed and private drives will be included to allow rear -access garages.
Alleys will be included to allow rear -access garages. The alley will be a 16' wide,
public access roadway.
Development Phasing Schedule
The developer proposed to install the north 1/3 and the south 1/3 of the development in
phase one and the middle 1/3 in phase two of the roads, storm sewer, sanitary sewer,
sidewalks, common area landscaping, and balance of utilities at the same time over the
entire site. The developer will obtain the respective permits for site development and
erosion control prior to the start of construction to insure all local government agency
permitting is in place prior to construction.
There will be two phases for the infrastructure pertaining to this site. Single Family
Homes and 35 of the 48 Multifamily Dwelling Units will be built in phase one and the
balance of the Multifamily will be built in phase two. The proposed build -out for the
development is projected within 3 to 4 years for 100% completion.
Developer and Owner Names
Vicki Wagner, General Manager
BLS Development, LLC
2402 Cedar Wood Drive
Fort Collins, Colorado 80526
Bus. No.: (970) 493-7309
Aug-16-00 10:35A Frederick Land Surveying 970 669 3725 P_02
PEAK VIEW SUBDIVISION
A tract of land lying in the Southwest 1/4 of Section 16, 'lownssip 7 North,
Range 69 West of the 6th Principal Meridian, Fort Collins. Larimer County,
Colorado being more particularly described a follows:
Assuming the North line of the Southwest % of Section 16, Township 7
North, Range 69 West of the 6th Principal Meridian bears S 89"24130" E
with all bearings herein relative thereto.
Commencing at the West'.% corner of Section 16, Township 7 North, Range
69 West of the 6th Principal Meridian thence run S 8912430" E along the
North line of the Southwest '4 of Section 16, Township 7 North, Range 69
Wcst of the 6th Principal Meridian for a distance of 864.00 feet to the
POINT OF BEGINNING; thence continue S 89124'30" E for a distance of
460.07 feet; thence leaving said North line run S 00°05'09" W for a distance;
of 869.02 feet; thence run S 89°36'48" W for a distance of 458.76 feet,
thence run N 00°00'01" E for a distance of 876.87 feet to the Point of
Beginning.
CONTAINING 9.206 acres, more or less, and being subject to all existing
easements and/or rights of way of record.
Table of Contents
Application
Legal Description
Developer and Owner Names
Development Phasing Schedule
Project Development Plan (PDP) Narrative
Sketch Plan Review Responses
Multi -Family Attached Housing, Architectural Elevations
Lighting Plan Narrative
PEAK VIEW SUDIVISION
A tract of land lying in the Southwest '/4 of Section 16, Township 7 North, Range 69
West of the a Principal Meridian, Fort Collins, Larimer County, Colorado
Project Development Plan Submittal
To
Planning Department
City of Fort Collins
281 North College Avenue
Fort Collins, Colorado
Prepared for
Vicki Wagner, General Manager
BLS Development, LLC
2402 Cedarwood Drive
Fort Collins, Colorado 80526
M
Design Development Consultants
2627 Redwing Road, Suite 350
Fort Collins, Colorado 80526
April 22, 2001