3. Please consider placing swale A -A away from the surrounding building to prevent
problems, especially since there is a nearby window well.
RESPONSE:
4. To provide adequate clearance over the existing 24-inch sanitary sewer line, please
provide ductile iron pipe (DIP) instead of RCP for the storm sewer.
RESPONSE:
Please refer to the redlined plans and report for additional review comments.
PROJECT
COMMENT SHEET
City of Fort Collins
Current Planning
DATE: August 3, 2000 TO: Stormwater Util
PROJECT: #23-00 Momingside Villas Subdivision Plat
Review
All comments must be received by Ted Shepard no later than the staff
review meeting:
August 16, 2000
Note- Please identify, your redlines for future reference
Please Note: This project has previously been
reviewed as a Building Permit Review.
1. Please be aware that final approval of this project is contigent upon signed easements.
Please have the 20-foot drainage easement signed.
RESPONSE:
2. Please provide freeboard for swale A -A by analyzing the capacity for 1.33*QI00.
Please make any necessary changes to the cross-section on the plan.
RESPONSE:
(over)
Signature x ��
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVISIONS " Axi
_Plat _Site _Drainage Report _Other -Pe f WP
_Utility _Redline Utility _Landscape qWbA
City of Fort Collins
Current
PROJECT
COMMENT S
Building Permit Review
AUG 7 2000
DATE: August 1, 2000 DEPT: PFA
PROJECT: Morningside Villas Subdivision and RM Site Plan
review, (formally Great Dane Sub)
Note: Building Permit Review (old use -by -right) the site, landscape and elevations
are to be reviewed under the old RM Zoning Code.
PLANNER: Peter Barnes, Zoning
ENGINEER: Sheri Wamhoff
All comments must be received by: August 16, 2000
ADDRESS NUMERALS:
Address numerals shall be visible from the street fronting the property, and posted with a
minimum of 6 inch numerals on a contrasting background. (Bronze numerals on brown
brick are not acceptable). 97 UFC 901.4.4
WATER SUPPLY:
Fire hydrants are required with a maximum spacing of 800 feet along an approved
roadway. Each hydrant must be capable of delivering 1000 gallons of water per minute at
a residual pressure of 20 psi. UFC 901.2.2.2
REQUIRED ACCESS:
A fire lane is required. The fire lane shall be visible by painting and signage, and
maintained unobstructed. 97 UFC 901.2.2.1, 901.3; 901.4.2; 902.2.1: FCLUC
NOTE: If a fire lane can not be provided the buildings shall be fire sprinklered.
SPRINKLER REQUIREMENTS:
These proposed buildings shall be fire sprinklered.
97 UFC 1003.2.9
NOTE: A Fire Lane is unattainable as proposed, thus rendering the buildings out of
access. These buildings will be required to be fire sprinklered.
Date: 8 - g — z C`o v Signature
Check ere if you wish to receive copies of revisions
Plat _ Site _ Drainage Report _ Other:
Utility _ Landscape _ Redline Utility
PROJECT
COMMENT SHEET
City of Fort Collins Building Permit Review
Current PlanninE
DATE: August 1, 2000 DEPT: AT&T
PROJECT: Morningside Villas Subdivision and RM Site Plan
review, (formally Great Dane Sub)
Note: Building Permit Review (old use -by -right) the site, landscape and elevations
are to be reviewed under the old RM Zoning Code.
PLANNER: Peter Barnes, Zoning
ENGINEER: Sheri Wamhoff
All comments must be received by: August 16, 2000
AT&T Cable Services will not plan to service this project until a Broadband Utility Easement, also called a
Service Agreement, is completed with our Commercial Accounts Executive Reneta Santro. She maybe
reached at (970)-419-3106 Monday through Friday 8a.m.-5 p.m..
Dater Signature:
Chec ere 1 y u wishto receive copies of revision '
'/Plat _ Site _ Drainage Report _ Other:
_ Utility � Landscape — Redline Utility
City of Fort Collins
Current
PROJECT
COMMENT SHEET
Building Permit Review
DATE: August 1, 2000 DEPT: Post Office
PROJECT: Morningside Villas Subdivision and RM Site Plan
review, (formally Great Dane Sub)
Note: Building Permit Review (old use -by -right) the site, landscape and elevations
are to be reviewed under the old RM Zoning Code.
PLANNER: Peter Barnes, Zoning
ENGINEER: Sheri Wamhoff
All comments must be received by: August 16, 2000
RECEIVED
AUG 10 2000
CURRENT PLANNING
Date: F 'F .0n Signature:/'eYz'/ 1/'_
Pec=t you wisn to receive copies of revisions
Plat _ Site _ Drainage Report _ Other:
Utility _ Landscape _ Redline Utility
PROJECT
COMMENT SHEET
City of Fort Collins Building Permit Review
Current Planning
DATE: August 1, 2000 DEPT: Engineering
PROJECT: Morningside Villas Subdivision and RM Site Plan
review, (formally Great Dane Sub)
Note: Building Permit Review (old use -by -right) the site, landscape and elevations
are to be reviewed under the old RM Zoning Code.
PLANNER: Peter Barnes, Zoning
ENGINEER: Sheri Wamhoff
All comments must be received by: August 16, 2000
Morningside Villas Subdivision August 15, 2000
Plat
Where is the off -site drainage easement in the process? Who is working on this, stormwater? Parks?
Utility plans
For the ramp on the east side of the driveway you are indicating that need to use vertical curb. That is great, I think the no
should read: "vertical curb & gutter taper curb from 1/2"to 5"" instead of "6" vertical curb & gutter taper curb from 6" to
5"". Since the curb height will be 1/2" at the driveway and 5" high at the beginning of the ramp. This is shown on several
sheets, so the change needs to be made on all of them. Would also recommend a note: "vertical curb and gutter taper curb
from 6" to 5"" for the piece between the curb chase and the existing curb.
Date: �� Signature•7S
1 /�;
Check ere if you wish to receive copies of revisions tj
Plat _ Site _ Drainage Report _ Other:
Utility _ Landscape — Redline Utility
PROJECT
City of Fort Collins COMMENT SHEET
Current Planning BUILDING PERMIT REVIEW
DATE: August 1, 2000 DEPT: Water & Wastewater
PROJECT: Morningside Villas Subdivision and RM Site Plan
Review, (formally Great Dane)
Note: Building Permit Review (old -use -by -right) The
site, landscape and elevation are to be reviewed under
the old RM Zoning Code
PLANNER: Peter Barnes, Zoning
ENGINEER: Sheri Wamhoff
All comments must be received by: August 16, 2000
➢ No bends are allowed on fire line laterals.
➢ In order to provide maximum separation between storm sewer and
sanitary sewer use 16" D.I.P. in place of RCP.
➢ Correct all plan sheets to reflect the change in storm sewer pipe
size/material.
➢ Original plans show and indicate the abandonment of the existing
sanitary sewer services, which extend from the end of Morningside
Drive. All existing services must be used or abandoned.
➢ See site, landscape and utility plans for other comments.
Date: IL 7- OU Signature:
CHECK HERE IF YOU WISH TO RECEIVE COPIES OF REVI IONS
X PLAT X SITE _DRAINAGE REPORT —OTHER\
X UTILITY X REDLINE UTILITY X LANDSCAPE 9^61� Z��
City of Fort Collins
City of Fort Collins
Current PlanninP
PROJECT
COMMENT SHEET
Building Permit Review
DATE: August 1, 2000 DEPT: Parks
PROJECT: Morningside Villas Subdivision and RM Site Plan
review, (formally Great Dane Sub)
Note: Building Permit Review (old use -by -right) the site, landscape and elevations
are to be reviewed under the old RM Zoning Code.
PLANNER: Peter Barnes, Zoning
ENGINEER: Sheri Wamhoff
All comments must be received by: August 16, 2000
0 C- /,k.,,lf���
,/,/ w; l/ tip- � �
�V Air
r
Aa-'A �'-7
Date: %S - 2sx" Signature: do,", 40�-
Checic�i youwito o receive copies of revisions
Plat _ Site _ Drainage Report _ Other:
Utility _ Landscape _ Redline Utility
If you should have any questions regarding these comments or if you need to meet to go over them
please feel free to contact the department representative that made the comment or myself.
Sincerely,
Sheri Wamhoff
Civil Engineer II
Attachments
cc: Peter Barnes
Ted Shepard
Georgiana Deines
Dick Rutherford, Stewart and Associates, Inc.
file
Transportation Services
Engineering Department
City of Fort Collins
August 24, 2000
Brett Larimer
1600 W Horsetooth Road
Fort Collins, Co 80526
Dear Mr Larimer,
For your information, attached are copies of the staffs "Building Permit Review/Utility Plan Review"
comments concerning the Morningside Villas Subdivision and RM Site Plan Review.
The plans submitted were reviewed by numerous City departments and other agencies. The
comments are offered by Staff to assist you in preparing final plans for building permit issuance and
Utility plan approval.
Section 2.2.11 of the Land Use Code requires that an applicant submit revisions based on this letter
within 90 days or the project application becomes null and void. Your response to the City's
concerns is due by November 24, 2000. A 30-day extension to this deadline is available. All
requests for an extension should be directed to the Current Planning Director. If remaining issues
are those that do not require plan revisions, a status report verifying continuing efforts toward
resolving the issues is required within the same timeline.
Mylars for signature can be submitted provided the following are done or have occurred prior to
submittal: 1) The plat has had an administrative hearing and received approval. 2) The off -site
easement for the storm drain line on the City property has been granted, and 3) All of the comments
being returned have been addressed and the utility plans, site and landscape plans have been
updated.
Once this has occurred please submit a mylar of the site plan, landscape plan, elevations and the
utility plans, return all redlined plans and provide 2 blueline site plans, 2 blueline landscape plans,
1 blueline set of utility plans, and 3 drainage reports for review and approval. The site, landscape
and elevation mylars will be kept by the City for filling, the utility plans upon approval will be returned
for to the developer, who at such time shall make a mylar copy and 5 blueline sets (stamped and
signed by the Engineer) of the signed utility plans and submit them to the City. Please note, if all
the comments have not been adequately addressed the mylars will be returned until the plans are
updated and/ or the issue(s) resolved.
In addition fill out and return "Information for Development Agreements" sheet. Upon receipt of this
I will start drafting the development agreement for this project.
Ted Shepard with the Current Planning Department is in the process of scheduling the type 1
hearing for the plat associated with this project. Please contact him if you have any questions
regarding this.
281 North College Avenue • P.O. Box 580 • Fort Collins, CO 80522-0580 • (970) 221-6605 • FAX (970) 221-6378