HomeMy WebLinkAbout1005 LAUREL STREET, WIRELESS TELECOMMUNICATIONS FACILITY - PDP/FDP - 28-00 - CORRESPONDENCE - CITY STAFFDonnie Dustin - Comments on Nextel Page IJI
From:
Link Mueller
To:
Donnie Dustin
Date:
Wed, Sep 13, 2000 8:24 AM
Subject:
Comments on Nextel
1. The 10 foot almost 25 feet further east than was shown on the last submittal in March. While it won't
nix the project, Utilities would like to know if the easement could be jogged to the east on Sportsman's
property instead of encumbering more land on the City side.
2. Need for Nextel to coordinate the construction of both the tower and the control building with the Locust
Street Project. In November/December the project will be providing a temporary access to Sportsmans
through the area the control building is proposed. The access should only be needed for 4 weeks. Nextel
can coordinate with Link Mueller, Project Manager, at 224-6039.