HomeMy WebLinkAboutFORT COLLINS VOLUNTEERS OF AMERICA, ELDERLY HOUSING - PDP - 14-01 - SUBMITTAL DOCUMENTS - ROUND 1 - PROJECT NARRATIVEPROPOSED PROJECT SCHEDULE Fort Collins 202 Elderly Housing Project Fort Collins, Colorado TSP Project No. 0500002 June 5, 2000 Revised October 31, 2000 Revised February 5, 2001 Tasks Date Complete PDP for City of Fort Collins Planning February 19, 2001 City review of PDP (4 weeks) February 20 — March 26, 2001 Design Development Drawings and Specifications for the Project Complete March 2, 2001 Cost estimate of DD's by Brown Const./ Review of DD's by VOA (3 weeks) March 3 — March 23, 2001 Preparation of Construction Drawings (6 weeks) March 3 — April 13, 2001 Revisions to PDP (2 weeks) March 27 — April 9, 2001 City review of revised PDP (3 weeks) April 10 —April 30, 2001 Review of CD's by VOA/ Review of CD's by The Building Department (3 weeks) April 14 — May 4, 2001 Revisions to CD's and resubmit to the Building Department (2 weeks) May 5 — May 18, 2001 Public Hearing (bi-weekly) May 21, 2001 Bidding and Negotiations by Brown Const. (3 weeks) May 19 — June 8, 2001 Preparation for HUD submittal (4 weeks) June 9 — July 6, 2001 HUD Review (4 weeks) July 7 — August 3, 2001 Possible construction start date/ Closing Date (4 weeks) August 31, 2001 Possible construction completion date (12 months) August 31, 2002 Possible Warranty Inspection of the Work (11 months) July 31, 2003