The following S. College improvements shall be constructed in
phases indicated:
Phase I
• Interim landscaping as per Interim Landscape Plan.
• Temporary grading at east boundary of project adjacent
to S. College. See Utility Plans and Interim Landscape
Plan.
• Temporary asphalt sidewalks at east boundary of project
adjacent to the Fossil Blvd. retaining wall along S.
College as shown. See Utility Plans and Interim
Landscape Plan.
• All S. College improvements shall be completed prior to
first C.O. for Phase I, except for construction of the
balance of the concrete sidewalk and all final grassed
and irrigated parkway landscaping, landscaping irrigation
and retaining wall at east boundary of project adjacent to
S. College, which shall be complete in Phase II. See
Utility Plans and Interim Landscape Plan.
Phase II
• Construction of the balance of the concrete sidewalk and
all final landscaping, landscaping irrigation and retaining
wall at east boundary of project adjacent to S. College.
See Utility Plans and Final Landscape Plan.
Steve Olt - Redtail Phasing Note Page 1
From: "Cathy Mathis" <cmathis@vfavfr.com>
To: "Kaye Vincent" <lagunitas@frii.com>, "Steve Olt" <solt@ci.fort-collins.co.us>, "Susan
Joy' <sjoy@fcgov.com>
Date: 06/28/2006 4:43:34 PM
Subject: Redtail Phasing Note
Hi Steve and Susan,
Attached is the word-smithed phasing note that Jon and I worked on this
afternoon. If you are agreeable, then this is what we'll put in on the
final site and landscape sheets.
Steve, I will also forward to you the Plant Notes