HomeMy WebLinkAboutREDTAIL RESIDENTIAL - FDP - 26-01A - CORRESPONDENCE - REVISIONS396 — In the few areas where slopes exceed 4:1, a mat system of initiating and
stabilizing vegetation will be used, similar to the system used by the Colorado
Department of Transportation, and as we have coordinated with Stormwater.
We look forward to expeditiously concluding final compliance, mylars, Development
Agreement and recording.
Thank you for your assistance.
Sincerely,
W
Jo routy, President
JP/ksr
Enclosure
3944 JFK Parkway, 12E, Fort Collins, CO 80525 • (970) 226-5000 • Fax (970) 226-5125
January 11, 2005
Cameron Gloss, Director
City of Fort Collins — Current Planning Department
281 North College
Fort Collins, CO 80522
Re: Redtail - Response to May 10, 2004 Comments
Dear Cameron:
The May 10, 2004 comments have been complied with or satisfied. However, the
following additional response or explanation is provided:
Engineering — General:
305 — Utility company variance will be obtained to permit retaining wall in part of the
sewer easement along College.
461 — A copy of all off -site easements is enclosed with reception numbers indicated for
those recorded. Recording is in process for the rest.
463 — Retaining walls will not require permanent easements. We have obtained a
temporary construction easement to build the retaining wall to the north, however a
temporary construction easement will not be necessary at the west.
Engineering — Plat:
367 — Legals and exhibits will be provided on disk so the vacation process can be
initiated (for the right-of-ways and easements relating to the portion of the Cameron
Park plat being vacated).
Engineering — Utility Plans:
32 — As agreed, walls relating to structural integrity of roads have been designed. Other
walls shall be designed prior. to issuance of building permits for same.