HomeMy WebLinkAboutFOSSIL LAKE P.U.D. - PRELIMINARY - 33-01D1 - SUBMITTAL DOCUMENTS - ROUND 2 - DRAINAGE REPORTN VI91 !TY MAP
1 =000
Page 6
Preliminary Drainage Report
Fossil Lake P.U.D.
REFERENCES
1. Larimer County Storm -Water Management Manual, Circa August 18,
1978.
2. Urban Drainage and Flood Control District Urban Storm Drainage
Criteria Manual, Wright -McLaughlin Engineers, Denver, Colorado,
March, 1969.
3. Larimer County Road Policy & Standards Manual, Circa August 24,
1972
Page 5
Preliminary Drainage Report
Fossil Lake P.U.D.
Upstream ends of all storm piping installed as part of the road construction will be protected
by straw bales immediately following final street grading and slope mulching. All project mulching
will be applied at a rate of 2 tons of blown straw per disturbed acre.
Silt fencing will be placed at the toe of any fill slope when practicable, following mulching
activities.
Areas of cuts will require installation of straw bale dikes in flow lines as will be shown on the
construction details. This activity should occur shortly following mulching.
Installation of detention ponds should occurimmediately following utility and road
construction activities. Protection of the outlet will be provided by a straw bale dike around the pipes
upstream end as soon as grade and mulching allows (12 weeks or less).
Preliminary grading within the multiple detention areas mentioned should occur immediately
following the installation of utilities. Care will be taken to not disturb any other erosion control
measures installed before this activity. Grading of the temporary detention/ water quality areas will
be a field decision, though pipe inverts where required will dictate grading. Following the preliminary
grading of the detention areas mulch will be placed in all areas of disturbance.
- Areas used for storage of soils will need a silt fence around the downhill side of the stock pile
to reduce impact to adjacent ground.
Any temporary berm required as part of this construction activity will be protected from
erosion by a layer of mulch when that berm is graded.
Areas next to any wetland, if applicable, will require additional protection methods to ensure
water quality. Beyond any methods identified and required above, straw bale walls ( a continuous
length ) will be required at the upstream side of wetlands. Diversions or temporary sedimentation
ponds will be required at the ends of such structures to exclude direct surface runoffs from entering
those sensitive areas.
Maintenance of these facilities should occur bi-weekly or following any rainfall of 3/4 inches
in 24-hours or more according to which ever event dictates.
Page 4
Preliminary Drainage Report
Fossil Lake P.U.D.
What is evident is that sites topographic conditions will not present itself as the principal element
driving the storm drainage design. Rather the street layout and aesthetics will be the key to the
ultimate site character.
Four types of density are being proposed for the project, single family, large lots, rural lots
and estate lots. Based on the LCS-WMM runoff coefficients were determined for each density to be
0.4, 0.4, 0.35 and 0.30 respectively. Next a multitude of typical basin geometries were averaged such
as overland length, gutter flow length and expected street slopes. The following table will summarize
those parameters.
General Basin Parameters
Designation
"C" Value
Overland
Avg. (ft)
Gutter
Avg. (ft)
TOC (2-yr)
(min)
Intensity (2-yr)
(in/hr)
Single Fam.
0.40
155.0
1150.0
20.6
1.81
Large Lots
1 0.40
155.0
1665.0
24.0
1.69
Rural Lots
0.35
170.0
550.0
18.2
1.94
Estate Lots
0.30
285.0
900.0
26.0
1.60
Note: all lots grades assumed at 2%, road grades assumed at 1.5%
Flow rate for direct runoff per acre ranged from 0.72 cfs to 0.48 cfs per acre in the 2-year
recurrence and 2.70 to 1.76 in the 100-year event, see the appendices of this report for details. These
flows were applied to the basins designated and pipe sizes determined. All pipes within the project
shall be RCP with a typical slope of 1.5%. Additionally, no detention is presumed as part of the sizing
effort, just direct runoff without surcharging.
IV. EROSION CONTROL
Residential development within the Fossil Lake P.U.D. will require two different levels of
water quality protection. First is that associated with the immediacy of the road and utility
installations. The second is related to ongoing water quality issues for the downstream receiving
waters. That first issue of construction erosion is being addressed in the following bullet list. Rather
than developing a construction sequence that would be steadfast and rigorous, sequencing of logical
methods with milestones is being proposed to allow for flexibility and judgement in the field.
Certain activities will need to proceed others', however, that is self evident to field crews as
site improvements move forward. This open sequence of erosion control methods will produce a
more responsive system and can be reviewed by field observers of the project. Please reference the
following list of methods and the associated construction milestones that accompany each.
Page 3
Preliminary Drainage Report
Fossil Lake P.U.D.
Little offsite sheet flows currently enters the project, rather, the service ditches from Muskrat and
Mail Creek which collect storm runoffs do traverse the development. Both will be augmented to
account for existing and proposed flow scenarios.
A thorough study of offshe hydrology will be completed prior to any final report to determine
precisely what flow can be expected. Currently, offshe sheet flows have been assessed for this
conceptual design effort.
Hydrologic and Hydraulic Design Criteria and References
Primary reference materials used for the development of this report include two sources the
Latimer County Storm -Water Management Manual and the Urban Storm Drainage Manuals. Both
are accepted as the basis of storm design in Larimer County and the City of Fort Collins.
General Drainage Concept
Grading on the site for this first blush concept focused on minimizing road cut and fill
associated with construction activities. When the design concepts further evolve more details will
allow for a fully developed project. Street runoff capacities throughout the project have been
enhanced by the use of "rollover" curb and gutter. Some areas include attached, detached or no
sidewalk relating to the rollover curb and gutter proposed. Arterial will be provided with vertical curb
and gutter and detached sidewalks. Most rights -of -way ( ROW) within the project will be 60 feet
wide. Arterial's adjacent to the project boundary will be provided with an additional 20 foot making
a 50 foot total ROW on this property.
Surface conveyance will be the basic method of controlling direct runoff. Detention is
anticipated but, as mentioned details of allowable release rates are still considered negotiable. Area
available for detention total near 45 acres which will not impede any future requirements. These areas
include specific detention ponds along with areas over normal WSEL in proposed water amenities.
Included in the street plans have been a minimum of rollover curb and gutter which will
provide a better means of street flow, rather than the normal borrow ditches. Curb outlet locations
shown are based on spots where street flows appear excessive. Details of outlet spacing, piping and
100-year street flow outlets are considered beyond the scope of this conceptual design.
Drainage Design Specifics
Basin sizes are small enough that the Rational Methods for internal design is an adequate
means of analysis. Site plan changes and revisions are imminent thus the lack of detail at this point
in the projects evolution.
Page 2
Preliminary Drainage Report
Fossil Lake P.U.D.
II. HISTORIC DRAINAGE
Based on the topography, historic drainage is easily explained as 90 percent of the site slope
directly to the Reservoir. Ten percent of the site drains into a seep ditch on the northeast corner of
the project which also flow into the reservoir. Using the rudimentary Rational Method for historic
runoff rates roughly 50 cfs of direct runoff is developed in the 2-year storm event. This runoff is
based on a "C" value of 0.25 and rainfall intensity of 0.74 in/hr with a time of concentration of 81
minutes. Since we are over the normal application area for the method it is generally understood to
over estimate flows. Thus the preliminary numbers for the large historic basin is slightly less
conservative as a release rate. In the existing land use no detention or water quality are being
provided. This proposal will be including both as part of the design package. When final design is
undertaken a detailed hydrologic model will be provided for both historic and developed conditions.
Negotiations with North Poudre Irrigation are being planned to address what runoff release rates can
be allowed.
3. DEVELOPED DRAINAGE
A number of assumptions have been included in the development of this report. All would be
considered as typical for the level of detail in a preliminary investigation. Developed basins are small
enough to allow for the use of the Rational Method, and average basin parameters are being assumed.
These averages are based on the preliminary data from proposed basin geometry. Typical land use -
densities, four of them, have been broken out for the residential layouts being represented. Then a
direct runoff per acre of land was determined for each density.
Additionally, pipes within the project were sized in the most conservative manner assuming
no detention being required. Sizes of RCP are based on Mannirig's Equation without the benefit of
driving head being considered. You will see however that a substantial amount of open space is
available when the details of the release rates are finalized. Pipes as shown are capable of passing the
100-year recurrence interval, again a conservative assumption. The Fossil Lake Reservoir the historic
receiving waters will experience the direct runoff increases from the intensified land use.
Developed Conditions
Storm drainage for the purpose of this preliminary analysis, will focus on the area within the
project boundary. Consideration of offsite issues will focus on the known canalized flows crossing
the project area.
Preliminary Drainage Report
for
Fossil Lake P.U.D.
Southeast Corner
of
Larimer County Road #36 and #9
Larimer County, Colorado
May 20, 1997
I. GENERAL LOCATION SITE DESCRIPTION
General Location
This report summarizes the results of a preliminary storm drainage investigation for the
residential development known as Fossil Lake P.U.D. (FL-PUD). The project is located in the
southeastern quadrant of Larimer County. Location by Section, Township and Range would be a part
of Sections 9 and 16, Township 6 North, Range 68 West. Specifically, on the southeast corner of the
intersection of Larimer County Roads #9 and #36 on the northeast end of Fossil Creek Reservoir. The
Parcel lies outside the Urban Growth Area as defined by Larimer County and the City of Fort Collins. _
Adjacent to the Fossil Creek Reservoir is a metes and bounds which allow the perpetual
access easement for the North Poudre Irrigation Company. This existing easement serves as the south
property boundary and will be enhance by the great number of buffer areas being proposed.
Site Description
This site falls outside of any existing hydrologic master plan, thus Northern Engineering
Services (NES) will be presenting a stand alone design to accommodate the project and all
hydraulically connected offsite basins. Topographically the site (±465.2 acre) would be referred to
as a "bowl " shape which encircles the Reservoir on the south boundary The surface slopes are
gradual and run generally toward the Reservoir. The property was formally in a combination of non-
agricultural rangeland and irrigated agricultural land use. Most of the service ditches within the
project area will be preserved with only rerouting occurring. This surface shape and irrigations history
lends itself to the use of surface runoff conveyance which will be the focus of the preliminary review.
Preliminary Drainage Report
for
Fossil Lake P.U.D.
Southeast Corner
of
Larimer County Road #36 and #9
Larimer County, Colorado
May 20, 1997
I. GENERAL LOCATION SITE DESCRIPTION
General Location
This report summarizes the results of a preliminary storm drainage investigation for the
residential development known as Fossil Lake P.U.D. (FL-PUD). The project is located in the
southeastern quadrant of Larimer County. Location by Section, Township and Range would be a part
of Sections 9 and 16, Township 6 North, Range 68 West. Specifically, on the southeast corner of the
intersection of Larimer County Roads #9 and #36 on the northeast end of Fossil Creek Reservoir. The
Parcel lies outside the Urban Growth Area as defined by Larimer County and the City of Fort Collins. _
Adjacent to the Fossil Creek Reservoir is a metes and bounds which allow the perpetual
access easement for the North Poudre Irrigation Company. This existing easement serves as the south
property boundary and will be enhance by the great number of buffer areas being proposed.
Site Description
This site falls outside of any existing hydrologic master plan, thus Northern Engineering
Services (NES) will be presenting a stand alone design to accommodate the project and all
hydraulically connected offsite basins. Topographically the site (±465.2 acre) would be referred to
as a "bowl " shape which encircles the Reservoir on the south boundary The surface slopes are
gradual and run generally toward the Reservoir. The property was formally in a combination of non-
agricultural rangeland and irrigated agricultural land use. Most of the service ditches within the
project area will be preserved with only rerouting occurring. This surface shape and irrigations history
lends itself to the use of surface runoff conveyance which will be the focus of the preliminary review.
Mr. Russ Legg, Planner
Larimer County Planning Office
Larimer County
200 West Oak Street
Fort Collins, Colorado 80521
May 20, 1997
RE: Fossil Lake P.U.D.
Larimer County, Colorado
Project Number: 9714.00
Dear Mr. Legg,
Northern Engineering is pleased to submit this Preliminary Drainage Report for Fossil Creek
P.U.D. for your review. It represents a preliminary study of existing and proposed storm water
characteristics of the project site.
If you should have any questions or comments as you review this report, please feel free to
contact me at your convenience.
Respectfully,
NORTHE GINEERING SERVICES, INC.
Alex V. Evonitz III, Project Manager
I hereby certify that this report for the preliminary
prepared by me (under my supervision) for the owners th
Larimer County Sto -Water Mana ment Manual.
��.,.��-IF
Mike Falcon Jones, P
State of Colorado, N
3
Professional
design of Fossil Lake P.U.D. was
19&w exceed the criteria in the
V- r
y�
W
25033
Al
PRELIMINARY DRAINAGE
REPORT
FOR
Fossil Lake P.U.D.
Larimer County, Colorado
Southeast Corner
of
Larimer County Roads #36 and #9
May 20, 1997
Prepared For:
Stan Everitt
Everitt Companies
P.O. Box 2125
Fort Collins, Colorado
80522
Prepared By:
Northern Engineering Services, Inc.
420 S. Howes, Suite 202
Fort Collins, Colorado 80521
Preliminary Drainage Report
for
Fossil Lake
P.U.D.
May 20, 1997
Prepared For:
Everitt Companies
P.O. Box 2125
Fort Collins, Colorado 80522
Prepared By:
Northern Engineering Services, Inc.
420 South Howes, Suite 202
Fort Collins, Colorado 80521
(970)221-4158
Fax(970)221-4159
Project Number: 9714.00