HomeMy WebLinkAboutTIDAL WAVE CARWASH - PDP - 38-01 - CORRESPONDENCE - (6)Department: Water Wastewater Issue Contact: Jeff Hill Topic: Utility Plans 120 Is gas and electric mains laid in the same trench along Troutman Parkway? Typically the gas main is located 4' behind sidewalk. If gas main is behind walk then it will be in conflict with curb stop and meter pit. 121 Water services must remain perpendicular to the main from the main to a point downstream of the meter pit. Department: Zoning Issue Contact: Jenny Nuckols 4 9/28/01 Is this all self -service. What is done in the auto bays? Will there be employees on site? Where do they park? 5 9/18/01 Please provide bicycle parking 12-19-01 - Maybe I just am not seeing it, but I don't see any bicycle racks being provided. Please show one near the building entrance. 6 9-18-01 Are there going of be directional arrows directing people which way to go? Will they be painted on the ground, small signs - please clarify and show on site plan. 12-19-01 site plan shows the traffic flow, but I think it would also be wise to have them painted on the ground. What is being shown just appears to be for our information. 8 9/18/01 No street trees are being shown along JFK. Need to have street trees. 3.2.1(D)(2) 12-19-01. It looks like one more street tree could be located along JFK. Double check with eng as far as any site distance issues. Be sure and return all of your redlined plans when you re -submit. If you have any questions regarding these issues or any other issues related to this project, please feel.free to call eat (970) 221-6750. i Yours Truly, i TROY JaVES City Plane r ; •� Page 5 19 1st Round 10/16/01: Cover Sheet - Update the General Notes (E-1) and Construction Notes (E-2). 2nd Round 01/02/02: General Notes provided as requested. Still need the Construction Notes, E-2. Please see attached or download from the Larimer County Website. 29 1st Round 10/16/01: Grading Sheet - Add the statement: `The top of foundation elevations shown...". See the Checklist in Appendix E-4. 2nd Round 01/02/02: Provided on the Drainage and Erosion Control sheet (which is good) but still needs to be added to the Grading sheet as well. Department: Excel Energy 76 10/26/01 No trees planted within 4' of gas lines. Department: Natural Resources Issue Contact: Len Hilderbrand Issue Contact: Doug Moore Topic: Possible Wildlife Conflict 109 The applicant has agreed to work with the Natural Resource Department to resolve any possible conflicts at time of construction. Department: Stormwater Utility Topic: Drainage 119 No Comments Department: Transportation Planning Issue Contact: Wes Lamarque Issue Contact: Tom Reiff Topic: Site Plan 118 Work closely with the Engineering dept. regarding the portions of sidewalk that need to be replaced. A continuous six foot wide sidewalk is preferred instead of 5 foot sections with a one foot ribbon and joint. Department: Water Wastewater Issue Contact: Roger Buffington 62 Previous comment: provide easement for sanitary sewer which extends onto the site. Page 4 Topic: Landscape Plan 112 Trees along Troutman do not meet the 4' minimum seperation distance from the gas line and Connie Woodard/Xcel Energy stated this is unacceptable. She can be reached at 225-7843 if you have any questions. The sidewalk will need to be moved north and reconstructed to 6' wide. The existing tree on the south corner of the driveway and JFK needs to be trimmed back to eliminate potential sight distance conflicts. Topic: Site Plan 39 1 st Round 10/16/01: Provide a legend to include the different line weights, etc. 2nd Round 01/02/02: Add the ROW and Property Line weights to the Legend. Remove the contour lines from the Site Plan and remove the contour lines from the Legend. 115 Remove the directional arrows from the plan. Topic: Site/Landscape Plan 41 1st Round 10/16/01: Show ROW, easements, etc and dimension off the centerline. Line weights are too similar and unlabeled. 2nd Round 01/02/02: ROW and easements are shown and dimensioned with exception of the drainage easement mentioned in #116. However, the line weights still need a little work. Existing features should be shown in a ghosted or dashed line weight. See the Utility Plans for a good example of how this should be done. Add the ROW and Property line weights to the Legend. 110 Add "Remove and Replace Existing Ramp and apron with a new" to the ADA Ramp label (or something to that effect) on the NE corner. ill The two ramps on the south side of the property are shown as existing on the Utility Plans. Which plan set is correct? If this is a new ramp, please label accordingly (like the ramp in the NE corner). If this is existing, please ghost the line weight. 113 Remove all contour and grading layers. 116 Show and label the new drainage easement in the southwest corner. Topic: Utility Plans 13 1 st Round 10/16/01: Provide the ROW dedication and Utility Easement by separate document. Plat shows old 100' standard, not the current 115' required by the city. See the attached sheets. 2nd Round 01/02/02: Thank you for sending in the ROW dedication, unfortunately it is not on the correct form and must be redone. Exhibit A of the Drainage easement does not close. Could be typo - west instead of east? Please see attached. Also, please provide the originals. 15 1st Round 10/16/01: Site/Landscape/Utility: Ramp on the NE corner does not meet ADA -should be replaced. 2nd Round 01/02/02: The corner of the ramp's apron does not meet ADA - too steep, and will need to be replaced as well. Please see redlines. Page 3 x 11" on a seperate paper, but I need to know the exact square footage of the vehicle area and the exact square footage of the landscape areas within that vehicle area. This analysis needs to be included in the project's file, thus the need for the diagram. 103 10/26/01 The circulation routes within the vehicular use areas need to be well-defined in accordance with the LUC Section 3.2.2(E)(1). 1/10/02 While the arrows you've provided showing the circulation routes on the site plan are helpful, it's just too much info for one sheet. Please provide an 8.5" x 11" diagram titled "On -site Circulation Routes," showing this information rather than having it on the site plan. The only circulation elements that should remain on the site plan are any striping that will be painted on. 107 10/26/01 The site plan, landscape plan and elevation are all part of the same planning set of documents. They should be numbered in the lower right corner ....page 1 of 3, 2 of 3, and 3 of 3. All three of these sheets should title the project the same, which should be "Tidal Wave Carwash P.D.P." The lighting plan, plat and topographic map are stand alone documents that are all sheet 1 of 1 by themselves. The utility plan set is also it's own set of documents, and are numbered correctly. 1/10/02 The lower right corner is where we need this info! The landscape plan has it at the upper right corner. Please move the title of sheet to the lower right corner too. When 24x36 drawings are all folded, the lower right corner of the page is the only part of the drawing that is visible. It saves time and confusion to be able to identify a folded drawing without having to unfold every sheet to find the title and the page number. 108 A re -submittal is required within 90 days of the date of this letter addressing the comments herein or the application becomes null and void. One 30-day extension is allowed and must be requested prior to the expiration of the application. 125 We're ready to schedule for Type 1 Hearing. It has been scheduled for Monday, January 28, 2002 at 4 p.m. in the conference rooms at 281 North College. The Hearing Officer does not make a formal decision at the hearing, but rather has 10 business days after the hearing to render a written decision. The next step after hearing is a process called Final Compliance Review. This entails submitting the final version of all drawings, another application and a $1000 filing fee. Call me to coordinate. 124 Please see the attached redlines from the Current Planning Department. Please return all redlined drawings when you resubmit. Department: Engineering Issue Contact: Susan Joy 117 The ROW and Utility easements were not clearly marked or labeled on the first submittal and the plans now show a conflict between the building location and the 15' Utility easement. Please note that no part of the building (including footings, eaves, awnings, etc) may encroach into the utility easement. The Site Plan now shows the roof overhang in the easement so you'll need to shift the building back a little to accomodate the footings and roofline. Coordinate the Site/Landscape/Utility Plans to reflect the new placement. 123 The 1' sidewalk addition along JFK will no longer be required because it was felt that it would become a maintenance problem. Please remove and replace any broken concrete to the existing 5' width and submit a variance request which we will support. Thank you and sorry for the confusion! Page 2 6a STAFF PROJECT REVIEW City of Fort Collins RHEY WRIGHT Date: 01/11/2002 TIDAL WAVE CARWASH, LLC 5238 FOX HILLS DRIVE FORT COLLINS, CO 80526 Staff has reviewed your submittal for TIDAL WAVE CARWASH, PDP, #38-01, and we offer the following comments: ISSUES: Department: Current Planning Issue Contact: Troy Jones 86 10/26/01 Label the surface materials shown on the site plan including asphalt, concrete, curbs, sidewalks, landscaped areas, etc. 1/10/02 Asphalt, on site curbs, and drainage trickle pans are still not labeled on the site plan. 94 10/26/01 Take off the "section showing self serve bay truss," and the "section showing typ. wall between auto bay and equipment room" from the elevations. The interior of the building is not part of the Project Development Plan review. 1/10/02 This comment may not have been entirely clear, but it applies to the building's representation on the site plan as well. The landscape plan shows the building the way it needs to be represented. The building should be shown on the site plan exactly the same way as you have shown it on the landscape plan (except . Take off the roof lines from the site plan. It may make sense to put a diagram of the roof plan on the elevation sheet to help visualize the massing of the building and to help read the elevations accurately, but the roof plan should not be on the site plan. See redlines. 95 10/26/01 Show the proposed on -site light poles on the elevations. 1/10/02 Although you did provide specification sheets for each of the lighting fixtures (thank you), I still need to see elevations of the freestanding lighting poles, and they need to be represented on the elevation sheet. These pole locations should also be shown and labeled on the site plan. 102 10/26/01 By definition in Article 5 of the LUC, a parking lot is an off-street parking area or vehicular use area. Although you do not propose any parking spaces, the vehicular use area is considered a parking lot by definition. Zero parking spaces is less than 100 spaces, so Section 3.2.1(E)(5) of the LUC requires that at least 6% of the square footage of the vehicular use area be devoted to landscaped areas. See the redlined landscape plan from the Current Planning Department. The purple line indicates the area of the vehicular use area, and the green areas indicated the areas that qualify toward the 6% requirement. Please create a diagram that clarifies the square footage of the area outlined in purple and the square footage of the area shaded in green. If the green area does not equal at least 6% of the purple outlined area, then you need to add more landscaped areas. The redlined plan has a few suggestions of places on the site plan that may work well for additional landscaped areas within the vehicular use area. 1/10/02 Your responce letter to my comments states, "existing interior landscaping is 6% based upon the redline site plan drawing provided by Current. Planning which identifies 'qualifying' landscape areas." As I requested before, "please create a diagram that clarifies the square footage of the area outlined in purple and the square footage of the area shaded in green." This diagram can be on 8.5" Page 1