HomeMy WebLinkAboutTIDAL WAVE CARWASH - PDP - 38-01 - SUBMITTAL DOCUMENTS - ROUND 1 - APPLICANT COMMUNICATIONTidal Wave Carwash, Submittal Summary, Page 2
2. Architectural Elevations - Attached; (6 copies, folded)
3. Site Plan Drawings - Attached; (30 copies, folded) with notes for applicable items as
indicated on plan and below:
(m) See attached separate Topographic Survey showing contours - completed by
Frederick Land Surveying
(n) #2 Canal shown on Context Diagram
(p) Existing Cottonwood trees shown on Site Plan and referenced on 8/21/01 email
from Tim Buchanan to Troy Jones authorizing removal. Fox den indicated on
Context Diagram.
(dd) Vicinity Map - Included on Plat of Super Block Holding Phase I (site), and
on Utility Plans.
4. Landscape Plan - Attached; (20 copies, folded)
Note: See note re: removal of "nuisance/cotton bearing" trees shown on site plan
and 8/21/01 email from Tim Buchanan, City Forester to Troy Jones authorizing
removal.
5. Existing and Proposed Utility systems - Attached (see Utility Plans)
6. Street Cross section Schematics - Not Applicable
7. Soils Report - Attached; (2 copies)
8. Drainage and Erosion Control Report - Attached; (4 copies)
9. Transportation Impact Analysis - Not Required per 5/09/2001 email message from Eric
Bracke to Troy Jones - email Attached
10. Modification Requests - Not Applicable
11. Plat - Attached for Super Block Holding Phase I (site); (23 copies, folded)
12. Context Diagram - Aerial Photo of site per City GIS - Site Aerial Photo Attached; (5
copies, folded)
13. Off Site Easements and Rights of Way - Not Applicable
14. Utility Plans - Attached; (13 copies, not folded)
15. Photometric Plan - Attached; (5 copies, folded)
16. Rendered Sets of Architectural, Site Plan and Landscape - Not Applicable, Type I
Review
17. PMT of all Plans - Not Applicable, Type I Review
Project Name: Tidal Wave Carwash
Project Development Plan
Submittal Summary
(1) Written Documents.
(a) Application Form and Check - Attached
(b) Legal Description - Attached as separate document and referenced on Plat of
Super Block Holding Phase I
(c) Type Review Certification - confirmation by email from Troy Jones ( 5/11/2001)
- Attached
(d) Three lists of names of property owners within 500 ft. (Troy Jones provided with
one copy of label addresses on 8/21/2001 for Neighborhood Mtg. Scheduled for
9/18/01 - Attached
(e) All Managers and Directors:
Rhey Wright is the Manager and 100% owner of Tidal Wave Carwash,
LLC.
(f) Not Applicable: There are no property owners within the boundaries of the Tidal
Wave development plan area, other than the applicant.
(g) Conceptual Review Letter and Issues Explanation - Attached
(h) Statement of Planning Objectives - Attached
(i) Development Schedule:
This is essentially a single phase construction project. No public
improvements, recreational or common space areas are known to be
applicable to the project. The following is an estimate of the Construction
timetable:
Tidal Wave Carwash
Project Development Schedule — Single Phase Project
Building Permit/Begin Grading
(subject to Planning/Bldg. Dept. review/approval schedule)
Begin Construction
Complete Construction
Dec. 1 '01
Dec 15 '01
April 15 `01
(j) Hazardous Materials Impact Analysis - Not Applicable: The carwash intends to
use only non -corrosive, biodegradable alkaline and wax products. A Phase I
Environmental Study was completed for the site and is available for review.
(k) Special Natural Area or Environmental Study - Not Applicable (see "j" above)
(1) Proposed Street names - Not Applicable
rIDAL WAVE
CARWASH
Office: 5238 Fox Hills Drive, Fort Collins, CO 80526
Phone: 223-8926 email: rheyw aahome.com
September 10,,2001
Mr. Troy Jones
City Planner
Current Planning Department
City of Fort Collins
281 North College Avenue
Fort Collins, CO 80522-0580
Dear Mr. Jones:
Please accept this letter and the accompanying documents as a Project Development Plan
application for Tidal Wave Carwash (Tidal Wave). Tidal Wave is a proposed new, state of the
art, 4 self -serve + 2 automatic bay car wash facility located at the Northwest corner of JFK and
Troutman Parkway in Fort Collins. This facility truly represents the "next generation" in car
wash design and technology and we believe Fort Collins (and the proposed site) is particularly
well suited for this type of operation.
We have prepared a "Submittal Summary" along with our application to assist with the
organization of the information. This summary follows the outline in the City's Submittal
Requirements and for each numbered item, we have provided either a short answer directly on
the Submittal Summary or indicated that the required documentation is attached or Not
Applicable. All items marked "Not Applicable" were designated based upon our understanding
of our application after our pre -submittal meeting with you on 8/21/01.
As the applicant, I am a local small business person who has lived in Fort Collins for the past 18
years. I intend for this project to be my primary livelihood and as such, I will be committed to
doing everything possible to expedite the review process. Please let me know as early as
possible during the review how I may assist with providing any information necessary.
Thank You.
Sincerely,
41_6p
Rhey Wright, Owner
Tidal Wave Carwash, LLC