HomeMy WebLinkAboutRIVERBEND - PDP - 39-01 - CORRESPONDENCE - (10)If you have any questions regarding these issues or any other issues related to this project, please feel
free to call me at 221-6341.
Yours Truly,
Steve Olt,
City Planner
Page 5
Number: 169 Created: 5/9/2003
Correct the limits of the street cut out to the centerline of the street. See redlines. Also, Lance
Newlin will waive the pavement impact fees if you patch and then mill and overlay the entire half of
the street.
Number: 171 Created: 5/9/2003
Overall Utility Sheet - add a note to the concrete sidewalk culvert to "see detail D12"
Department: Light & Power Issue Contact: Doug Martine
Topic: Electric
Number: 156 Created: 4/28/2003
"There appears to be little or no room for installation of electric facilities, especially to the most
easterly building. A utility coordination meeting will be required before approval of this plan.
Number: 157 Created: 5/8/2003
Existing electric is at the N.E. comer of Timberline & Countryside Rd. The developer will need to
provide off -site easements along the north side of Countryside Rd.
Number: 158 Created: 5/8/2003
Light & Power will need to cross Countryside Rd. If this street already exists, Light & Power will
need to bore (if possible) or open cut the street and the developer will need to provide Light & Power
with a street cut permit, pay permit and impact fees, pay additional costs to cut asphalt, and replace
asphalt as necessary.
Number: 159 Created: 5/8/2003
Electric utility facilities will need to be shown on the Utility Plan, and Light & Power will need to
sign the Utility Plan.
Department: Stormwater Utility Issue Contact: Wes Lamarque
Topic: Drainage
Number: 173 Created: 5/ 13/2003
Still need copies of all required drainage and grading easements.
Department: Transportation Planning Issue Contact: Tom Reiff
Topic: General
Number: 175 Created: 5/15/2003
Minor correction: The dimensions identified for the landscaped parkway width and sidewalk along
Countryside Drive is incorrect. Please change to the following numbers - parkway width is 5'6", and
the sidewalk is 5'. This road is classified as a collector on the Master Street Plan and will eventually
function as the frontage road for Mulberry St.
This development proposal has been scheduled for an administrative (Type I) public hearing to
be held on the evening of June 12, 2003. The issues expressed in this comment letter must be
addressed and resolved or staff will have to be assured that they can and will be resolved prior to the
item going to public hearing. The primary outstanding issue is the acquisition of the necessary utility
easement along the north side of Countryside Drive for the purpose of providing electric service to
this development. Please be sure and return all of the City staff red -lined plans when you submit the
Final Compliance plans.
Page 4
Number: 176 Created: 5/20/2003
From Technical Services: Information missing in legal (Larimer County).
Number: 177 Created: 5/20/2003
From Technical Services: The parcel to the south of this site is City Owned. The proposed
"easements" may need to be called "alignment areas". Also, there appears to be an existing easement
already in place over some of that area.
Topic: Site Plan
Number: 165 Created: 5/8/2003
Remove the contour lines.
Number: 167 Created: 5/8/2003
Correct Note 11.
Number: 168 Created: 5/8/2003
Correct Tracts A and B to include and/or read "Public Access" easement instead of just "access"
easement.
Topic: Utility Plans
Number: 145 Created: 11 / 18/2002
11/18/02: Per the utility coordination meeting held on 9/25/2:
1. Show the existing ROW and utility easements, if any, on the east -west portion of Countryside
Drive.
2. Obtain a 9' utility easement (or greater if necessary) on the north side of Countryside Drive for the
electric line in the ultimate location. This has also been an outstanding comment since 2/26/2.
3. Show all meter locations (gas & electric) and electric line as determined in the above meeting.
4. Show the bore or street cut necessary to install the electric line across Countryside. Show the
approximate limits of construction. Provide the street cut note:
Limits of street cut are approximate. Final limits are to be determined in the field by the City
Engineering Inspector. All repairs to be in accordance with City street repair standards.
5/8/3:
1. Response from Engineer - there are no existing easements so none are shown. Issue closed.
2. Repeat comment.
3. Repeat comment.
4. Bore location is now shown. Issue closed.
5. Extend the approximate limits of construction to include making the sanitary sewer connection in
Countryside Dr. Note is shown as requested, thanks!
Page 3
grading easement. However, you must keep the proposed grading within this existing easement or
you will have to obtain an additional grading easement from Natural Resources. All the easements to
bring in the electric along the north side of Countryside are still required. See comment #166.
Number: 166 Created: 5/8/2003
Correct the project limit boundary along the north side of Countryside Drive on the Site, Landscape
and Utility plans. This project will be required (per the Utility Coordination Meeting held on 9/25/2)
to bring in the electric service through here and it must be installed in the ultimate location. It will
require an off -site utility easement, grading easement and temporary construction easement in order
to do this. As stated under other sections, the plans can not go to hearing until a Letter of Intent is
provided from the affected property owner and can not be approved until these easements are
obtained and recorded.
Number: 178 Created: 5/20/2003
Correct the project title on all plan sets to read "Riverbend PDP"
Topic: Landscape Play:
Number: 144 Created: 11 / 18/2002
11/18/02: Show all utilities, including gas and electric.
5/8/3: Repeat comment. Show individual services off the main lines. Label all utilities.
Number: 161
Remove the contour lines.
Created: 5/8/2003
Number: 162 Created: 5/8/2003
Show and label all easements, ROW, and Tracts.
Number: 163 Created: 5/8/2003
Coordinate the comments with the various plan sets so that they present the same information.
Number: 164 Created: 5/8/2003
Note 11 shows phasing. There is only one phase to this project.
Topic: Plat
Number: 150 Created: 11/18/2002
11/18/02: Correct the plat as redlined. See attached Plat Language Document.
5/8/3: Repeat comment. Please correct the plat language per the attached Plat Language Document.
Please correct 2002 to read 2003 in all locations used.
Number: 160 Created: 5/8/2003
Correct the access easement label to read "public access" easement in the tract notes, both locations.
Coordinate this with the other plan sets.
Number: 172 Created: 5/9/2003
An offsite utility easement required on the north side of Countryside Dr. Please provide this
easement by separate document and label the reception number on the plat or at minimum, label with
"by separate document". See comment 146 and 166.
Page 2
STAFF PROJECT REVIEW
Citvof Fort Collins
HOORAZ, LLC ' Date: 5/21/2003
c/o Vignette Studios
144 North Mason Street, Suite 2
Fort Collins, CO. 80524
Staff has reviewed your submittal for RIVERBEND PDP, #39-01, and we offer the following
comments:
ISSUES:
Department: Current Planning Issue Contact: Steve Olt
Topic: Utility Plans
Number: 179 Created: 5/21 /2003
Len Hilderbrand of Xcel Energy offered the following comments:
a. The gas meter locations will need to be located on sides of garages, near sidewalks. Gas
mains are on front lot lines.
b. Contact Connie Woodward for estimates and design.
C. No trees may be planted within 4' of gas lines.
d. There is an existing 3" high pressure gas line located along and near Countryside Drive on the
west side of this project. This line may need to be converted to lower pressure.
e. The utility plans do not show the existing high pressure line.
Number: 180 Created: 5/21 /2003
Mike Scheid of ELCO has marked 4 trees on a red -lined Landscape Plan (attached) that may be or are
too close to the water line. Trees must be 10' clear of a water line.
Department: Engineering Issue Contact: Susan Joy
Topic: General
Number: 124 Created: 3/19/2002
See redlines for other comments.
Number: 143 Created: 11 / 18/2002
Coordinate the various plan sets so that they all present the same information. All plan sets need to
show the off -site temporary construction easements, grading easements, utility easements, drainage
easements, etc.
5/8/3: Repeat comment.
Number: 146 Created: 11 / 18/2002
All off -site easements must be provided before this development can go to hearing.
5/8/3: Repeat comment. The off -site easements from Natural Resources to rework the grades in
order to install the sidewalk along the south side of Countryside is no longer required per Ron
Mills/Real Estate Services and Carrie Daggett/City Attorney as long as you stay within the existing
Page I