#35-01 B Centerpoint Plaza
Building A Major Amendment, Type I
I&A
POL
1 inch
1 /20/2005 N
600 feet
Centerpoint Plaza PDP, Building A - Major Amendment, #35-01 B
March 30, 2005 Administrative Hearing
Page 7
RECOMMENDATION:
Staff recommends approval of the Centerpoint Plaza PDP, Building 'A' - Major
Amendment - #35-01 B.
Centerpoint Plaza PDP, Building A - Major Amendment, #35-01 B
March 30, 2005 Administrative Hearing
Page 6
The north elevation of the building will be oriented to Midpoint
Drive, a collector street to the north, and will be 12' from the street
right-of-way.
Build -to Line. Section 3.5.3(B)(2)(c) stated that:
Buildings shall be located at least 10' and no more than 25'
behind the street right-of-way of an adjoining street that is
larger than a two -land arterial that does not have on -street
parking.
The west elevation of the building will be oriented to South
Timberline Road, a major arterial (6-lane) street to the west, and
will be 19' from the street right-of-way.
5. Neighborhood Information Meeting
The Centerpoint Plaza PDP, Building 'A' - Major Amendment contains a
proposed land use that is permitted in the E — Employment Zoning District
subject to an administrative (Type 1) review. The proposed use is a new
mixed -use building. The LUC does not require that a neighborhood
meeting be held for a Type I development proposal and a City -facilitated
neighborhood meeting was not held to discuss this proposal.
FINDINGS OF FACT/CONCLUSIONS
After reviewing the Centerpoint Plaza PDP, Building 'A'- Major Amendment, staff
makes the following findings of fact and conclusions:
1. The proposed land uses are permitted in the E — Employment Zone
District.
2. The Major Amendment complies with the procedure/criteria set forth in
Section 2.2.10(B) Major Amendments of the Land Use Code.
3. The Major Amendment plan complies with all applicable General
Development Standards contained in Article 3 of the Land Use Code.
4. The Major Amendment plan complies with all applicable Land Use and
Development Standards contained in Article 4, Division 4.22 of the Land
Use Code.
Centerpoint Plaza PDP, Building A - Major Amendment, #35-01 B
March 30, 2005 Administrative Hearing
Page 5
C. Division 3.5, Building Standards
1. Section 3.5.1, Building and Project Compatibility
The building height identified on the previously approved
Centerpoint Plaza, PDP is 1 story and 23'-6". This Major
Amendment request is proposing that the height of the 3-story
building, at its highest point on the ridgeline, be 39'-11' .
Section 4.22(D)(4)(a) in the E - Employment District in the
LUC states that the maximum height for all nonresidential
buildings shall be 4 stories.
2. Section 3.5.3, Mixed Use, Institutional and Commercial Buildings
The proposal satisfies all Relationship of Buildings to Streets,
Walkways and Parking standards.
Orientation to Build -to Lines for Streetfront Buildings. Section
3.5.3(B)(2)(a) states that:
To establish "build -to" lines, buildings shall be located and
designed to align or approximately align with any previously
established building/sidewalk relationships that are
consistent with this standard. Accordingly, at least thirty (30)
percent of the total length of the building along the street
shall be extended to the build -to line area. If a parcel, lot or
tract has multiple streets, then the building shall be built to at
least two (2) of them according to (b) through (d) below, i.e.
to a street corner.
The north elevation of the building will be oriented to Midpoint
Drive, with 30% of the south elevation located 12' from the right-of-
way for Midpoint Drive. The west elevation of the building will be
oriented to South Timberline Road, with 100% of the west elevation
located 19' from the right-of-way for Timberline Road.
Build -to Line. Section 3.5.3(B)(2)(b) states that:
Buildings shall be located no more than 15' from the right-of-
way of an adjoining street if the street is smaller than a full
arterial or has on -street parking.
Centerpoint Plaza PDP, Building A - Major Amendment, #35-01 B
March 30, 2005 Administrative Hearing
Page 4
d. The proposal complies with Section 3.2.1(E)(5) in that it
provides at least 6% interior landscaping in the parking area
(containing less than 100 parking spaces), satisfying the
minimum requirement.
2. Section 3.2.2, Access, Circulation and Parking
a. The proposal complies with Section 3.2.2(C)(4)(a) in that it
provides secure and conveniently located bicycle parking in the
amount of 11.6% of the total number of automobile parking
spaces on -site, satisfying the minimum requirement of 5%.
b. The proposal complies with Section 3.2.2(C)(5) in that it
provides direct, safe, and continuous walkways and bicycle
connections to major pedestrian and bicycle destinations in the
surrounding area.
c. The proposal complies with Section 3.2.2(D) in that it provides
for safe, convenient, and efficient bicycle, pedestrian, and
vehicular movement to and through the site. Vehicular access
will occur via one existing curb cut from Midpoint Drive, one on
the east side of the proposed building to the proposed surface
parking area.
d. The proposal complies with Section 3.2.2(K)(2) in that it
provides 43 parking spaces for the 21,822 square feet of
leasable floor area for the office, medical clinic, and print shop
uses. This is approximately 25 spaces under the maximum
number of spaces allowed for the proposed land uses.
B. Division 3.3, Engineering Standards
,1. Section 3.3.5, Engineering Design Standards
The proposal complies with the design standards, requirements,
and specifications for the services as set forth in this section.
Centerpoint Plaza PDP, Building A - Major Amendment, #35-01 B
March 30, 2005 Administrative Hearing
Page 3
Lot 1 of the Centerpoint Plaza, PDP was previously platted and approved
in September, 2003. Building A (Phase 1) was approved as a 1-story
building containing 7,062 square feet of leasable floor area.
2. Division 4.22 of the Land Use Code, Employment Zone District
Offices, medical clinics, and print shops are permitted in the E —
Employment Zoning District, subject to administrative review.
This Major Amendment request complies with the purpose of the E District
as it is a primary workplace that includes office, medical clinic, and print
shop uses in a planned business park.
3. Article 2 of the Land Use Code - Administration
This Major Amendment request complies with the Procedure/Criteria set
forth in Section 2.2.10(B) Major Amendments.
4. Article 3 of the Land Use Code — General Development Standards
The Major Amendment request complies with all applicable General
Development Standards as follows:
A. Division 3.2, Site Planning and Design Standards
1. Section 3.2.1, Landscaping and Tree Protection
a. The proposal complies with Section 3.2.1(D)(1)(c) in that it will
provide "full tree stocking" within 50' of the new Building Won
Lot 1, according to the standards set forth in this section.
b. The proposal complies with Section 3.2.1(D)(2)(b) in that
existing canopy shade (street) trees are provided at a 35' - 40'
spacing in the parkways (between back of curb and sidewalk)
along South Timberline Road and Midpoint Drive.
c. The proposal complies with Section 3.2.1(D)(3) in that no one
species of trees on the development plan exceeds 33% of the
total of 26 trees on the plan.
Centerpoint Plaza PDP, Building A - Major Amendment, #35-01 B
March 30, 2005 Administrative Hearing
Page 2
permitted uses and standards located in Division 4.22 - Employment
District of ARTICLE 4 - DISTRICTS.
Offices, medical clinics, and print shops are permitted in the E — Employment
Zoning District, subject to administrative review. The purpose of the E District is:
Intended to provide locations for a variety of workplaces including light
industrial uses,. research and development activities, offices and
institutions. This District also is intended to accommodate secondary uses
that complement or support the primary workplace uses, such as hotels,
restaurants, convenience shopping, child care and housing.
Additionally, the Employment District is intended to encourage the
development of planned office and business parks; to promote excellence
in the design and construction of buildings, outdoor spaces, transportation
facilities and streetscapes; to direct the development of workplaces
consistent with the availability of public facilities and services; and to
continue the vitality and quality of life in adjacent residential
neighborhoods.
This proposal complies with the purpose of the E District as it is a primary
workplace that includes office, medical clinic, and print shop uses in a planned
business park.
COMMENTS:
Background
The surrounding zoning and land uses are as follows:
N: E; approved planned commercial center (Spring Creek Center
PUD)
S: I, T; existing single family residential property and planned
mixed -use (Johnson Property ODP)
E: E; existing employment / industrial park (Prospect Park East,
Prospect Industrial Park)
W: E, I; existing undefined storage and City facility (large storage
tanks, Light & Power station)
The property was annexed in September, 1973 as part of the East
Prospect Street First Annexation.
ITEM NO.
MEETING DATE
STAFF toe" Dlt
City of Fort Collins HEARING OFFICER
STAFF REPORT
PROJECT: Centerpoint Plaza PDP, Building 'A'- Major Amendment -
#35-01 B
APPLICANT: Eastpoint Studios, LLC
c/o Don Brookshire
141 South College Avenue, #103
.Fort Collins, CO..80524.
OWNER: Frazier & Company Ventures
141 South College Avenue, #103
Fort Collins, CO. 80524
PROJECT DESCRIPTION:
This is a request for an increase in the building height, from 1 story to 3 stories,
and an increase in the amount of leasable floor area, from 7,062 square feet to
21,822 square feet, in a new mixed -use building on a portion of Lot 1 of the
Centerpoint Plaza Project Development Plan (PDP). The proposed uses are
professional offices, print shops, and medical clinics. The pad site is located at
the southeast corner of South Timberline Road and Midpoint Drive. The property
is in the E — Employment Zoning District.
RECOMMENDATION: Approval
EXECUTIVE SUMMARY:
This Major Amendment complies with the following applicable requirements of
the Land Use Code LUC , more specifically:
the process located in Division 2.2 - Common Development Review
Procedures for Development Applications of ARTICLE 2 -
ADMINISTRATION;
" standards located in Division 3.2 - Site Planning and Design
Standards, Division 3.3 — Engineering Standards, and Division 3.5 -
Building Standards of ARTICLE 3 - GENERAL DEVELOPMENT
STANDARDS; and
COMMUNITY PLANNING AND ENVIRONMENTAL SERVICES 281 N. College Ave. P.O. Box 580 Fort Collins, CO80522-0580 (970) 221-6750
PLANNING DEPARTMENT