urban design, inc.
Number:72 Created:6/18/2003
Clearly define whether the 2 existing sets of water and sewer services are to be used or abandoned. If
they are to be abandoned include the standard general note to abandon them at the main and to
coordinate abandonment with the City Utilities.
See the site, landscape and utility plans for other comments.
Response: Added Note #5 to Sheet 3. Both existing sets of services are to be used..
We look forward to your prompt and favorable review of this project. Please do not hesitate to contact
me directly if any additional issues arise or are found to be outstanding. We will do our best to make
any necessary changes as expeditiously as possible.
Sincerely,
Kimberly Straw, ICP
Project Manager
Copy to: George Holter
Jack Blake, Stewart & Assoc.
Page 10
urban design. inc.
Number:105 Created:6/27/2003
Please change water quality orifice holes to be one 1/4-inch hole per row for five rows spaced 5-inches
apart instead of 4-inches. This is a non-standard design needed to accommodate for the 2 foot high
structure that is associated with such a small water quality volume and surface area. The 1/8-inch
holes were looked at as probably clogging much more regularly.
Response: Revised WQ orifice holes to be 1-1/4" per row at 5" apart.
Number:106 Created:6/27/2003
Please consider a little less landscaping at the WQ outlet structure. At full plant maturity, there should
be no blockage of outlet structure and access for maintenance.
Response: Landscaping in this area has been pulled back from this point. The plants that remain in
the area are a clump -style ornamental grass (Blue Oats Grama) that should work well in this situation
and not cause any blockage.
Topic: Sediment/Erosion Control
Number:73 Created:6/25/2003
1. The erosion control notes on the plan are not City of Fort Collins notes, please correct.
Response: Done.
2. 1 can find no BMP's on the erosion control plan.
Response: The WQCD is a BMP.
3. Your report states that "...The foundation will be installed prior to overlot grading for erosion
control." I don't understand.
Response: Report has been revised to clarify
Department: Transportation Planning Issue Contact: Tom Reiff
Topic: Transportation
Number:74 Created:6/25/2003
No further comments.
Department: Water Wastewater Issue Contact: Jeff Hill
Topic: General
Number:12 Created:3/3/2003
6/18/03 Coordinate the location of the fire line with the mechanical engineer to extend the fire line into
mechanical room. Include the standard general note to extend the fire line and domestic water line into
a mechanical room where a backflow device shall be installed.
Response: Added "Standard General Note" to Overall Utility Plan Sheet 3.
Page 9
ao�Y�O@pi�
urban design, inc.
Department: PFA Issue Contact: Ron Gonzales
Topic: Fire
Number:108 Created:7/1/2003
The fire lane requires a dedicated emergency access easement on the plat (or dedicated through
separate document) per FCLUC 3.6.6.
Response: This easement is shown, and documents to create this are in process.
Number:109 Created:7/1/2003
The building is required to be fire sprinklered.
Response: OK — noted on utility plan Sheet 3, Note #7.
Number:110 Created:7/1/2003
Landscape matter shall not encroach into the fire lane airspace.
Response: The required 13'6" clearance will be maintained. The ornamental trees have been
replaced with larger canopy trees which should diminish this concern to some degree; additionally a
note has been added that requires pruning of any overhanging branches to a minimum clearance of
13'6".
Number:111 Created:7/1/2003
Address numerals shall be visible from the street fronting the property.
Response: OK
Department: Police Issue Contact: Joseph Gerdom
Topic: General
Number:107 Created:6/27/2003
Recommend providing reinforced view ports on access doors on south, west and north
Response: This suggestion has been passed on to the architects.
Department: Stormwater Utility Issue Contact: Wes Lamarque
Topic: Drainage
Number:31 Created:3/14/2003
Drainage easements are required for both detention ponds and both storm sewers. An off -site drainage
easement is required for the storm sewer that is on the property to the south, as well as a temporary
construction easement. Repeat Comment 6/25/03 - Reminder for final plan approval.
Response: Easements are in the process of being dedicated, along with a temporary construction
easement.
Number:104 Created:6/27/2003
Please combine area inlet 1 detail and water quality orifice/well screen detail together and better clarify
how this is to be constructed. Rebar should be used for structural integrity due to one of the sides of
the area inlet being partially removed for the well screen and water quality orifice plate.
Response: The area inlet detail and WQ orifice detail combined on Sheet #6 (utility plans). Rebar is
shown.
Page 8
C u
O�M@ a o
urban design, inc.
Number:97 Created:6/26/2003
Sheet 2 - Remove contours.
Response: Removed from overall utility plan Sheet 3 and the FP Site and Landscape plans.
Number:98 Created:6/26/2003
Sheet 2 - The manhole is located too close to the pedestrian access ramp in the NW corner. How will
this work?
Response: We believe that the manhole is appropriately located in reference to this walk/ramp and
there shouldn't be any conflict.
Number:99 Created:6/26/2003
Please show the approximate area of construction for all proposed street cuts and add the street cut
note:
"Limits of street cut are approximate. Final limits are to be determined in the field by the City
Engineering Inspector. All repairs to be in accordance with City street repair standards."
Response: There will be no cuts in Mason Street, except for the 6" fire line. A note has been added to
Sheet 3 regarding this. Approximate cut lines in both existing access drives are shown.
Number:101 Created:6/26/2003
What are all the lines representing in the NW corner?
Response: Existing improvements.
Number:102 Created:6/26/2003
Grading Sheet: Provide spot elevations at all lot comers.
Response: Done.
Number:103 Created:6/26/2003
Legend: Incorrect ped access ramp shown.
Response: Ramp detail has been crossed out, no new ramp was added because they vary — see City
Detail.
Department: Light & Power Issue Contact: Doug Martine
Topic: Light & Power
Number:71 Created:6/6/2003
Developer will need to coordinate power requirements and a location for a pad type transformer on the
site with Light & Power Engineering (221-6700).
Response: This has been coordinated — the transformer location is shown at the NW corner of the
building.
Page 7
CJ�Y7WP(j�
urban design, inc.
Number:89 Created:6/26/2003
Cover Sheet: Corrections to the sheet numbering required. The plat may be included for reference
only but it cannot be numbered as part of the set.
Response: Done.
Number:90 Created:6/26/2003
Provide the General Construction notes as shown in Appendix E2. Please call Bob Zakely for the
erosion control notes.
Response: Done — see Sheet 2.
Number:91 Created:6/26/2003
Reference required to the updated or current soils investigation report, E2, D.2.
Response: Done.
Number:92 Created:6/26/2003
Cover Sheet: Correct the spelling error in the Engineer's Statement.
Response: Done.
Number:93 Created:6/26/2003
Grading Sheet: Provide the statement per Appendix E4, III.E.
Response: Done. — see grading plan.
Number:94 Created:6/26/2003
ROW, property lines and easements must be dimensioned and labeled off the CL.
Response: Easements are legals that are tied to the boundary lines of the parcel, and the ROW
indicates distance from the centerline. This is how they have been dimensioned.
Number:95 Created:6/26/2003
Remove all references to "Phase 2". This appears to be a single phase project only.
Response: Done.
Number:96 Created:6/26/2003
Label/dimension all curb return and fire lane radii. Provide spot elevations around curb returns off
Mason so that we can determine if the minimum grades are being met.
Response: On utility plans, curb return radii are labeled on Sheet 3. The fire lane radii are labeled on
Sheet 7 (Easement Exhibit). PC, PT, and mid -point spot elevations are provided on Mason Street's
flowline radii. Also, fire lane radii are noted on the site and landscape plans of the Final Plan.
Page 6
conywpi�
urban design, inc.
limited to "streets". These include, but are not limited to, curb/gutter/sidewalk, parking lots, pedestrian
ramps, etc. Please call me at 221-6605 if you are ever confused about what is meant by a comment
so that you can get it cleared up immediately rather than wait until the next round of review. This will
help you get through the review process much quicker.
Response: This has been addressed.
Number:51 Created:3/14/2003
Update all the old details to the new details. Provide details 701, 707, 708, 710, 1601, 1602, 1606, and
the Greeley detail for the truncated domes now required for all access ramps. See attached.
6/27/3: Repeat comment but do not include the Greeley detail. The City has determined that they will
use our standard detail until further notice.
Response: Revised details to most current City standard.
Number:52 Created:3/14/2003
See redlines.
Response: Redline comments have been addressed.
Number:84 Created:6/26/2003
Cover Sheet: Correct the project title to match the Site and Landscape Plans. Should be "Garth
Commercial Plaza, Lots 3 and 4"
Response: Done.
Number:85 Created:6/26/2003
Cover Sheet: Provide the legal description (township, range, etc) under Fort Collins, Colorado.
Response: Done.
Number:86 Created:6/26/2003
Cover Sheet: Provide the current date under the project title.
Response: Done.
Number:87 Created:6/26/2003
Cover Sheet: Correct note 41.
Response: Done.
Number:88 Created:6/26/2003
Cover Sheet: Note 48 - A variance request will be distributed to the various utility agencies requesting
the overlapping sidewalk and utility easement. If approved, this variance will need to be listed here.
You will need to state the code section, the original requirement and then what the variance was
granted for.
Response: Added to note 48 the overlapping sidewalk onto the other easements
Page 5
urban design, inc.
Number:83 Created:6/26/2003
Are you meeting the 10' min distance as stated in note 21?
Response: Yes.
Topic: Site
Number:77 Created:6/26/2003
Relabel the 24' access drive easement on the north side of the property to read "24' Public Access
Drive."
Response: All easements are identified based upon information provided by the engineers on their
plans.
Number:78 Created:6/26/2003
Relabel the 20' Fire Lane to read "20' Emergency Access Drive."
Response: Done.
Number:79 Created:6/26/2003
What do all the lines in the NW corner represent?
Response: Existing curb and asphalt — additional labels have been added for clarity.
Number:80 Created:6/26/2003
Please confirm that the fire lane has a 25' inside radius and a 50' outside radius.
Response: Dimensions are noted on the plans.
Number:82 Created:6/26/2003
General Notes:
Remove #1 as previously requested. This information must be shown on the Site plan.
#2 - "exact geometry" is not shown on the utility plans as stated.
#13 - Utility sheets say "painted" and the Landscape plans do not match either.
#14 - Which easements are existing and which are proposed? Currently all plan sets are unclear.
Response: Notes have been revised or removed.
Topic: Utility Plan
Number:36 Created:3/14/2003
The utility plans that were submitted are expired and must be resubmitted to current standards
(October 1, 2002 LCUASS). You may revise the older set and bubble out everything that's changed
but it would much easier, faster, and cleaner to resubmit a new plan set under another name that's
different than the expired set. Please see chapter 3 and Appendix E for submittal and design
requirements. Please complete and submit Appendix E4 with the next submittal. Quite a lot of
information was left off this submittal. Expect more comments in the next round if not designed in
accordance with the current street standards.
6/20/3: Your response indicated confusion with what I meant by "current street standards." I was
referring to LCUASS - Larimer County Urban Area Street Standards in short form (as mentioned in the
first sentence of the previous comment). These standards govern all public improvements and are not
Page 4
o
urban design, inc.
Number:46 Created:3/14/2003
Provide off -site drainage and temporary construction easements for all work occurring outside the
project boundary.
6/27/3: Response acknowledged. This item will remain open until complete.
Response: All required off -site easements are being submitted to your office for the dedication
procedure.
Number:47 Created:3/14/2003
Provide all necessary onsite drainage and utility easements by plat or separate document.
6/27/3: Your response is acknowledged. This item will remain open until complete.
Response: All required off -site easements are being submitted to your office for the dedication
procedure.
Number:81 Created:6/26/2003
Label all existing easements as "existing" and label the recep#. If proposed, label as "proposed". If
vacating, then label as "to be vacated" and hatch in the area lightly showing the area to be vacated.
Response: An Easement Exhibit has been added on Sheet 7 of the utility plans, however this
information has not been added on the overall or drainage plan as it is not relevant to those plans, and
they are already too cluttered. Cityscape does show this information on their site and landscape plans
as appropriate.
Number:100 Created:6/26/2003
See Appendix E6 for scanability requirements.
Response: Plans are scanable now. If you see something that isn't, please make Stewart &
Associates aware so they can fix it.
Topic: Landscape Plan
Number:49 Created:3/14/2003
Show all existing and proposed utility and drainage easements.
Response: All easements are identified based upon information provided by the engineers on their
plans.
6/27/3: Repeat comment. Coordinate with the site and landscape plans and see comment 81 under
"General."
Response: All easements have been noted on the plans.
Number:50 Created:3/14/2003
Correct all overlapping labeling. This sheet is very hard to read.
6/27/3: Better, but the overlapping labeling still needs to be corrected. See redlines.
Response: Done.
Page 3
urban design. inc.
Carl Jenkins, Post Office [6/10/03] - No Comment
Number:113 Created:7/1/2003
The site plan, landscape plan, and elevations are all part of a set of drawings that will be file together.
Please label them, starting with the site plan, sheet 1 of 3, 2 of 3 and 3 of 3.
Response: Done.
Number:114 Created:7/2/2003
There are only a few small items to clear up before we can go to hearing. Current Planning comment
#60 needs to be resolved to staffs satisfaction, all off -site easements need letters of intent, and the
timing of the vacation of the drainage easement relative to the date of the hearing needs to be
coordinated with Engineering and Stormwater. Coordinate with me (Troy Jones) on the revised
landscape plan, and coordinate with Susan Joy on the easement issues. After hearing we will require
a final compliance submittal. The final compliance application will require an application form, a $1000
application fee, 4 site plans, 4 landscape plans, 4 utility plan sets, 1 drainage report, all signed
easements, and all redlines.
Response: OK
Topic: Landscape Plan
Number:60 Created:3/17/2003
[7/1/03] Although the re -submittal clarified the sizes of the various landscape areas, the comments is
still not addressed. The "6% landscaped areas requirement' [required by 3.2.1(E)(5)] applies to the
parking lot only, and not the entire site as a whole. The method to calculate the limits of the parking lot
is clarified in the LUC in the attached photocopy of Figure 1 from Article 3 page 12. Also, see the
purple line depicted on the redlined a copy of the landscape plan. This issue needs to be resolved
prior to going to hearing.
[3/17/03] It appears that less than the required amount of parking lot interior landscaping is being
proposed. Refer to the purple line sketched onto the redlined landscape plan from Current Planning.
This line, represents the vehicular area of which 6 percent must be landscaped area. Include a chart
on the landscape plan that clarifies the square footage of this vehicular area, and also clarifies how
much of that area, in square footage, is devoted to landscaped areas. It is required to be at least 6
percent, and must be communicated on the landscape plan as such [3.2.1(E)(5)].
Response: The illustrative graphic which was faxed to you the day I received this comment has been
incorporated into the Landscape Sheet for better clarification that we meet this standard.
Department: Engineering Issue Contact: Susan Joy
Topic: General
Number:40 Created:3/14/2003
Coordinate the various plan sets so that they present the same information.
6/27/3: The Landscape, Site and Utility plans still do not present the same information. Please
perform some quality control prior to your next submittal.
Response: Continued coordination between the various parties should alleviate the bulk of any
discrepancies. However, note that all these plans do not necessary present the same information
based upon varying checklist requirements and the intent of the plan.
Page 2
12 August 2003
Troy Jones
Current Planning
City of Fort Collins
281 N. College Ave.
Fort Collins, CO 80521
RE: GARTH COMMERCIAL PLAZA #20-02B
Troy-
C�o� �caa o 0
urban design, inc.
3555 stanford road, suite 105
fort collins, colorado 80525
(970) 226-4074
fax (970) 226-4196
e@cityscapeud.com
Based upon the recent approval for the PDP for this project and review comments received on 7/02/03,
the plans have been revised and are being submitted now as Final Compliance Plans. The comments
below are taken from that 7/02/03 comment letter and, where applicable, we have indicated our
response and any revisions we have made. Please review these responses as well as the new plan
set at your earliest convenience. We look forward to completing this Final Plan review process as
quickly as possible so that Mr. Holter can begin construction yet this season.
Department: Current Planning Issue Contact: Troy Jones
Number:112 Created:7/1/2003
The following departments and agencies forwarded hand written comments directly to me as follows:
Tim Buchanan, City Forester [6/26/03] - Add these notes to the landscape plan:
"A free permit must be obtained from the City Forester before any trees or shrubs as noted on this plan
are plated, pruned or removed in the public right-of-way. This includes all areas between the sidewalk
and curb and street medians. This permit shall approve the location and species to be planted.
Failure to obtain this permit may result in replacing or relocating trees and a hold on certificate of
occupancy."
"The developer shall contact the City Forester to inspect all street tree planting at completion. All trees
need to have been installed as shown on the landscape plan. Approval of street tree planing is
required before final approval. Failure to obtain approval by the City Forester for street tree planting
shall result in a hold on certificate of occupancy."
Response: These notes have been added to Sheet 2, as Notes # 20 & #23.
Len Hilderbrand, Xcel Energy [6/17/03] - No Comment.
Response: Comment was received at the Administrative hearing on 7/29/03 regarding a concern
about the location of the gas line in relation to the public sidewalk along Mason St. We met with Mr.
Hilderbrand on 7/31/03. He was satisfied with the proposed situation where the existing gas line will
remain about 1' to the west of the edge of that walk.
Page 1