Comment Number: 8 Comment Originated: 01/20/2015
02/10/2015: There are still line over text issues. See redlines.
01/20/2015: There are line over text issues. See redlines.
Department: Traffic Operation
Contact: Martina Wilkinson, 970-221-6887, mwilkinson@fcqov.com
Topic: Site Plan
Comment Number: 1 Comment Originated: 01/23/2015
01/23/2015: Please add directional ramps at the sidewalk across the new
parking lot north of the school.
Topic: Traffic Impact Study
Comment Number: 2 Comment Originated: 01/23/2015
01/23/2015: The TIS shows that four auxiliary turn lanes are warrented but not
constructed within the study area. One lane (NB right at Taft/Horsetooth) is not
impacted by this proposal. One lane (WB right at Horsetooth and Silver Trails)
will be done by the City with striping after the overlay project this summer. The
two remaining lanes (SB rights from Taft onto Bronson and Horsetooth) are
impacted by school traffic. If GVA proposes to not build the lanes, please
provide a variance request with narrative and justification. Thanks.
Department: Water -Wastewater Engineering
Contact: Wes Lamarque, 970-416-2418, wiamargue@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 01/23/2015
01/23/2015: A swivel tee is required for the connection with the fire line.
Comment Number: 2 Comment Originated: 01/23/2015
01/23/2015: Please provide all water details that are being proposed.
Department: Zoning
Contact: Noah Beals, 970416-2313, nbeals@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 01/20/2015
01/20/2015: Along the south side on new south parking area there should beat
least two trees include in the landscaped setback.
Comment Number: 2 Comment Originated: 01/20/2015
01/20/2015: The mechanical equipment both on the ground and on the rooftop
should be screen? Please provide screening.
Comment Number: 4
Comment Originated: 01/21/2015 y
01/21/2015: PUBLIC -SAFETY RADIO AMPLIFICATION SYSTEM
New buildings or building additions require a fire department, emergency
communication system evaluation after the core/shell but prior to final build out.
For the purposes of this section, fire walls shall not be used to define separate
buildings. Where adequate radio coverage cannot be established within a
building, public -safety radio amplification systems shall be designed and
installed in accordance with criteria established by the Poudre Fire Authority.
Poudre Fire Authority Bureau Admin Policy #07-01
Department: Stormwater Engineering
Contact: Jesse Schlam, 970-218-2932, ischlam@fcgov.com
Topic: Erosion Control
Comment Number: 1
Comment Originated: 01/13/2015
02/10/2015: Repeat - Saw note.
01/13/2015: The site disturbs more than 10,000 sq-ft, therefore Erosion and
Sediment Control Materials need to be submitted for FDP. The erosion control
requirements are in the Stormwater Design Criteria under the Amendments of
Volume 3 Chapter 7 Section 1.3.3. Current Erosion Control Materials
Submitted does not meet requirements. Please submit; Erosion Control Plan,
Erosion Control Report, and an Escrow / Security Calculation. If you need
clarification concerning this section, or if there are any questions please contact
Jesse Schlam 970-218-2932 or email @ jschlam@fcgov.com
Contact: Wes Lamarque, 970-416-2418, wlamargue@fcgov.com
Topic: General
Comment Number: 2
Comment Originated: 01/23/2015
01/23/2015: Please provide a drainage letter describing the drainage
improvements and showing conformance with the approved drainage report for
Global Village Academy.
Comment Number: 3 Comment Originated: 01/23/2015
01/23/2015: Please provide a grading plan.
Comment Number: 4 Comment Originated: 01/23/2015
01/23/2015: Please provide all storm water and LID details that are proposed.
Department: Technical Services
Contact: Jeff County, 970-221-65885 icounty@fcgov.com
Topic: Landscape Plans
Comment Number: 11 Comment Originated: 02/10/2015
02/10/2015: IRRIGATION PLANS: There are line over text issues. See
redlines.
Comment Number: 12 Comment Originated: 02/10/2015
02/10/2015: IRRIGATION PLANS: The lighter text & linework marked is not
acceptable. It will not scan or reproduce. Please darken it up. See redlines.
,i Department: Light And 1-- .ar
Contact: Rob Irish, 970-224-6167, rirish@fcgov.com
Topic: General
Comment Number: 1 Comment Originated:
01/20/2015: Light & Power installed anew 3-phase 277/480v transformer with
the construction of Global Village Academy 1. Any relocation or modification to
the existing electric facilities will be at the owners expense.
Comment Number: 2 Comment Originated:
01/20/2015: If the applicant anticipates a need to increase/change there
existing electric load please contact Rob Irish w/Light & Power Engineering at
970-224-6167. Any change to existing electric load would require submittal of a
C-1 Form and One -line diagram to Light & Power Engineering.
Department: PFA
Contact: Jim Lynxwiler, 970416-2869, ilynxwiler@poudre-fire.orq
Topic: General
Comment Number: 1
01/20/2015
01/20/2015
Comment Originated: 01/21/2015
01/21/2015: HYDRANT
Another hydrant is required to meet minimum coverage. Site plans show a new
hydrant located just north of new addition. This is an acceptable location.
Comment Number: 2 Comment Originated: 01/21/2015
01/21/2015: FIRE LANES
Fire lanes shall be provided to within 150' of all portions of the building. This
requirement will have been met with the addition of the drive aisle on the north
side of the building being dedicated as an Emergency Access Easement. No
other access issues remain unless the building addition is to exceed 30' in
height. Fire lane specifications are provided below.
Comment Number: 3
Comment Originated: 01/21/2015
01/21/2015: FIRE LANE SPECIFICATIONS
A fire lane plan shall be submitted for approval prior to installation. In addition to
the design criteria already contained in relevant standards and policies, any
new fire lane must meet the following general requirements:
> Shall be designated on the plat as an Emergency Access Easement.
> Maintain the required 20 foot minimum unobstructed width & 14 foot minimum
overhead clearance.
> Be designed as a flat, hard, all-weather driving surface capable of supporting
40 tons.
> Dead-end fire access roads in excess of 150 feet in length shall be provided
with an approved area for turning around fire apparatus.
> The required turning radii of a fire apparatus access road shall be a minimum
of 25 feet inside and 50 feet outside. Turning radii shall be detailed on
submitted plans.
> Be visible by painting and/or signage, and maintained unobstructed at all
times.
> Additional access requirements exist for buildings greater than 30' in height.
Refer to Appendix D of the 2012 IFC or contact PFA for details.
International Fire Code 503.2.3, 503.2.4, 503.2.5, 503.3, 503.4 and Appendix
D; FCLUC 3.6.2(B)2006 and Local Amendments.
Comment Number: 5
Gomment Originated: 01/21/2015
01/21/2015: A DCP or excavation permit will need to be obtained prior to
starting any work on the site.
Comment Number: 6 Comment Originated: 01/21/2015
01/21/2015: Please add the following note to the Utility plan and site plan:
Any damaged curb, gutter and sidewalk existing prior to construction, as well as
streets, sidewalks, curbs and gutters, destroyed, damaged or removed due to
construction of this project, shall be replaced or restored to City of Fort Collins
standards at the Developer's expense prior to the acceptance of completed
improvements.
Comment Number: 7
Comment Originated: 01/21/2015
01/21/2015: Please add our standard signature block to the utility and drainage
plans and our standard LCUASS notes to the utility plan set. Please contact me
for a copy of our standard utility plan set notes.
Department: Forestry
Contact: Tim Buchanan, 970-221-6361, tbuchanan@fcgov.com
Topic: Landscape Plans
Comment Number: 1 Comment Originated: 01/21/2015
01/21/2015:
The two north most street trees along Taft Hill Road have not been installed or
cannot be accurately identified as existing. there is space for only one street
tree in this area but there is an open space for another street tree to the south.
Please indicate on these phase to plans that these two missing street trees will
be planted and show the locations where they will be planted. Contact the City
Forester to obtain a permit for the planting of these two street trees.
Comment Number: 2
Comment Originated: 01/21/2015
01/21/2015:
The Iseli Fastigiate Spruce are shown on the plan as 5 gallon size. Specifying
them as 6 foot B&B would be consistent with Fort Collins LUC standards.
Comment Number: 3
Comment Originated: 01/21/2015
01/21/2015:
The existing street trees planted in phase one are showing varying amounts of
transplant stress. City Forestry staff will inspect the street trees in the spring to
determine if the development will need to replace any of the existing street trees
planted in 2014. If replacements need to occur the development will be notified
to replace dead or dying street trees. Please contact the City Forester, Tim
Buchanan at 2216361 or tbuchanan @fcgov.com with any question about the
City inspection and acceptance process for City Street Trees.
City of
F6rt Collins
Community Development and
Neighborhood Services
281 North College Avenue
PO Box 580
Fort Collins, CO 80522
970.221.6750
970.224.6134 - fax
tcgov. com/developmentreview
February 11, 2015
RE: Global Village Academy II, SPA150001, Round Number 2
Please see the following summary of comments from City staff and outside reviewing
agencies for your submittal of the above referenced project. If you have questions about
any comments, you may contact the individual commenter or direct your questions through
the Project Planner, Ted Shepard, at 970-221-6343ortshepard@fcgov.com.
Comment Summary:
Department: Engineering Development Review
Contact: Tyler Siegmund, 970-221-6501, tiegmund@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 01/21/2015
01/21/2015: Does the bus lane need to extend towards Bronson this close to
the drive approach? It appears that if you end the bus lane further into the
property you will reduce the amount of new pavement added to the site and
minimize the bus and car conflict at the drive approach off of Bronson.
Comment Number: 2 Comment Originated: 01/21/2015
01/21/2015: With the addition of the paved lanes interior to the property and the
new curb and gutter along the private drive a grading plan will need to be
submitted for review as part of the project. Will the existing inlet (near Bronson)
be relocated?
Comment Number: 3 Comment Originated: 01/21/2015
01/21/2015: Please submit the temporary access easement vacation
documents and the new emergency access dedication documents (legal
description and exhibits for both easements). There will be an additional
TDRFee due to vacate and dedicate easements by separate document. You
can contact me or visit http://www.fcgov.com/engineering/devrev.php for
additional information on the process to vacate and dedicate easements by
separate document.
Comment Number: 4 Comment Originated: 01/21/2015
01/21/2015: Please remove the approximate patching limits on Bronson and
Silver Trails from the Utility plan. This is existing from phase I.