January 27, 2015
Page 3
Compliance with Article 2, Administration:
The administrative extension procedure has been exhausted and, pursuant to Section 2.2.11(0)(4)
of the LUC, the additional one year extension being requested by this letter must be approved
by the Planning and Zoning Board upon a finding that the Project complies with all
applicable general development standards as contained in Article 3 of the LUC and the zone
district standards as contained in Article 4 of the LUC. The Planning and Zoning Board must
also find that either: "(a) the applicant has been diligent in constructing the engineering
improvements though such improvements have not been fully constructed; or (b) due to other
extraordinary and exceptional situations unique to the property, completing all engineering
improvements would result in unusual and exceptional practical difficulties or undue hardship
upon the applicant, and granting the extension would not be detrimental to the public good."
East Ridge has not commenced construction of the engineering improvements within the Project.
Thus subsection (a) quoted above is not applicable.
With respect to subsection (b) The Project was initially delayed due to the economic recession.
Prior to the recession East Ridge had obtained a commitment for a development loan to pay the
cost of constructing and installing all of the engineering improvements for the Project ("the
Development Loan"). The Development Loan was withdrawn as a result of the recession.
Recently, the Project has been delayed because the. Project will be served by the East Larimer
County Water District (ELCO) and ELCO changed the manner in which ELCO calculates the
yield on Water Supply and Storage Company shares which resulted in a reduction from 84 acre
feet per share to 38 acre feet per share. Historically, ELCO has not been willing to accept cash -
in -lieu for an entire subdivision and raw water has become much more difficult to acquire.
Prospective home builders have been exploring the possibility of redesigning the water system
for the Project to include a non -potable system using water from the #10 Ditch for outdoor use to
reduce the amount of water required by ELCO. The combined cost of installing all of the
subdivision improvements as part of the initial single family residential portion of the
Project and the cost of satisfying the ELCO raw water requirements has made it very difficult
to obtain the financing necessary to develop the Project. During the past year, two home
builders made offers to purchase the Property, construct the improvements, and develop the
Project as approved but neither home builder was able to resolve theproblems associated
with ELCO's raw water requirements. The Property is now under contract to a statewide home
builder that reasonably believes ELCO's raw water requirements can be satisfied. Hartford
Homes believes that the Project needs to be revised to permit the Project to be developed in
phases and to provide for greater product diversity.
Extending the vested property rights for one additional year to allow the Project to be
redesigned and developed will not be detrimental to the public good because:
(i) The Project continues to comply with the applicable zoning standards.
Pete Wray, AICP
January 27, 2015
Page 2
for an extension, various amendments were made to the ODP to comply with the then current
LUC regulations.
On June 11, 2013, pursuant to Section 2.2.11(0)(4) Ted Shepard as Chief Planner granted a
second one year administrative extension of the vested property rights to July 13, 2014.
On May 8, 2014 the Planning and Zoning Board granted a one year extension to July 13, 2015.
Zoning and Surrounding Land Uses:
The Project is zoned L-M-N. Current surrounding zoning and land uses are:
The property to the east of the Project is zoned L-M-N and is vacant land.
The property to the northeast of the Project is zoned L-M-N and is developed as the
Waterglen PUD.
The property immediately to the north of the Project is vacant land in Larimer County
zoned FA- I Farming.
The property to the northwest of the Project is zoned M-M-N.
The property to the west of the Project is in Larimer County zoned 0-Open and I -
Industrial and is developed as both commercial/industrial and residential.
The property directly south of the Project is in Larimer County zoned I -Industrial and
used as a residence, farm and sand and gravel operation.
Project Description:
The FOP was approved as a residential subdivision consisting of 384 single family lots, 3
public parks consisting of approximately 12 acres, one large drainage, irrigation, wetlands, open
space area of approximately 17 acres ("the Drainage Detention Area"), several smaller drainage
and pedestrian easements totally approximately 3.5 acres and several tracts reserved for future
development including a neighborhood center and approximately 200-240 multi -family units.
The overall residential density when the Project is completely built out will be between 5.5 and 6
dwelling units per net acre (net of parks, streets, wetlands/open space, and commercial tracts).
I have attached a copy of page 2 of the recorded subdivision plat designated as the "Outer
Boundary" which shows the overall layout of the Project. Based on the design of the Project, it
will be necessary to install all of the subdivision improvements for the entire Project as part of
the development of the residential lots.
}
• LILEY, ROGERS & MARTELL, LLC ■
ATTORNEYS AT LAW
January 27, 2015
VIA HAND DELIVERY
Pete Wray, AICP
Senior City Planner
City of Fort Collins
Community Development and Neighborhood Services
281 N. College Avenue
Fort Collins, CO 80521
Re: East Ridge Subdivision File#33-98
Dear Pete:
I represent East Ridge of Fort Collins, LLC; a Colorado limited liability company
("East Ridge"). East Ridge is the owner of the property located at the southeast corner of the
intersection of East Vine Drive and North Timberline Road platted as East Ridge
Subdivision (the 'Property" or the "Project").
The purpose of this letter is to request a one year extension of the vested property
rights for the Project to July 13, 2016.
History and Current Status of the Project:
On February 19, 2002, the Property was annexed as the East Ridge Annexation by
Ordinance No. 021-2002. The Annexation Ordinance was recorded on May 13, 2002 at
Reception No. 2002-0052493 of the Larimer County, Colorado records. TheAnnexation Plat
was recorded the same day at Reception No. 2002-0052494.
On August 26, 2005, the Overall Development Plan (ODP) was approved by the
Planning and Zoning Board.
On July 13, 2009, the Final. Development Plan (FDP) for the Project was approved by
the Director of Planning. A subdivision plat of the Property was recorded July 13, 2009 at
reception number 20090047904 of the Larimer County, Colorado records. Pursuant to
Section 2.2.11(0)(3) of the Land Use Code (LUC) the FDP was granted a three year term of
vested property rights to July 13,2012.
On June 15, 2012, pursuant to Section 2.2.11(0)(4) of the LUC Laurie Kadrich of
Community Development and Neighborhood Services administratively granted a one year
extension of the term of the vested property rights to July 13, 2013. At the time of the request
LUCIA A. LILEY ■ JAMES A. MARTELL ■ TODD W. ROGERS ■ JOSHUA C. LILEY
THE PETER ANDERSON HOUSE ■ 300 SOUTH HOWES STREET ■ FORT COLLINS, COLORADO 80521
TELEPHONE: (970) 221-4455 ■ FAX: (970) 221-4242
Pete Wray, AICP
January 27, 2015
Page 4
(ii) The Project continues to meet all aspects of the Land Use Code. With its
application for an administrative extension submitted June 6, 2013 East Ridge
submitted a letter from Terence Hoaglund of Vignette Studios verifying that
with the amendments to the ODP made in 2012, the FDP was in compliance
with the then current applicable general development standards and the
applicable LMN zoning district standards. I am not aware of any amendments
to the LUC made within the last year that would cause the FDP to no longer
comply with the general development standards or zoning standards.
The Project will be a benefit to the public because the 17 acre Drainage Detention
Pond to be constructed by East Ridge within the Project will be a regional detention pond
and will be an essential element of the north Fort Collins master drainage plan.
Based on the foregoing, East Ridge respectfully requests that the Planning and
Zoning Board extend the term of vested property rights for the Project for one additional
year to July 13, 2016.
If you should have questions with regard to this matter or need additional
information, please do not hesitate to contact me. Thank you.
Sincerely, n�
/ r ;Ztp
James A. Martell
JAM:bkr
Enclosures
cc: Ms. Darlene Schuster (via e-mail)
Mr. Jeff Strauss (via e-mail)