HomeMy WebLinkAbout419 W. MOUNTAIN AVE. - MAJOR AMENDMENT - 42-02 - CORRESPONDENCE - (3)or Owner's Certificati
OWNER'S CERTIFICATION
The undersigned does/do hereby certify that Uwe are the lawful owners of
real property described on this site plan and do hereby certify that I/we accept the
conditions and restrictions set forth on said site plan.
Owner (signed)
(State of )
( )SS
(County of )
Subscribed and sworn to before me this
WITNESS my hand and official seal.
Notary Public
Address
My Commission Expires
Date
day of , 20 , by
Add tAjj S jr4+v^k,
block- f -o 4-*, S&e
Show and label location of existing curb stop and meter. Curb stop and meter pit may not be located
in sidewalk
Department: Water Wastewater Issue Contact: Roger Buffington
Topic: Landscape/Site Plan
20
Is the sewer service shown existing or proposed?
21
Will the additional living unit connect to the existing water/sewer services?
Department: Zoning
Topic: zoning
Issue Contact: Peter Barnes
1
Their "Request for Modification" narrative needs to mention that the project is to constuct an addition
in order to convert the existing duplex into a triplex. The narrative also needs to state the specific
side setback modification requested. For example, "the modification request is to reduce the required
side setback along the west lot line from 5' to 3.25' and along the east lot line from 8' to 3.5"'. (The
east lot line along the alley is considered to be an interior side lot line, and the required east setback
is 8' instead of 5' since 4.7(E)(4) requires a minimum of 5' setback for the first 18' in wall height, and
then an additional 1' setback for each additional Tor fraction of extra height. Since the new wall
height on the east side appears to be 23', an 8' setback is required). It appears that the narrative is
relying on the hardship criteria rather than the equal to or better than. But the east side setback
modification could be considered under the equal to or better than since the purpose of the side
setback is promoted equally well since the east side abuts an alley rather than a residential lot.
2
The site plan needs to include parking information - number of parking spaces. This should be added
to the list containing the other land use information. (it appears there are 7 spaces counting the one
in the garage).
Be sure and return all of your redlined plans when you re -submit.
If you have any questions regarding these issues or any other issues related to this project,
please feel free to call me at (970) 221-6750.
our Truly,
i
TRPY N S'
City PI ner
Page 5
Department: Light & Power Issue Contact: Doug Martine
Topic: Electric
3
Builder needs to coordinate power system with Light & Power Engineering (221-6700). Electric
development and system modification charges will apply. '
Department: Natural Resources Issue Contact: Doug Moore
Topic: Landscape/Site Plan
18
Not all of the required planting notes are included on the plan. Contact Tim Buchanan, City Forester
at 221-6361 for information on the notes needed.
19
Tree Preservation Specifications will need to be followed and the added to the plan. 3.2.1(G)
Department: Park Planning
Topic: General
6
Park Planning - No Comments.
Issue Contact: Craig Foreman
Department: Police Issue Contact: Joseph Gerdom
Topic: Electric
4
Would suggest wheel blocks at end of each stall to prevent landscape damage. No info on
landscaping of south end esmt. Change Isanti to Barberry in parking lot area. Need some type of low
lighting along west sideyard walk.
Department: Streets
Topic: General
8
Streets - OK.
Department: Stormwater Utility
Topic: Stormwater
14
No Comments.
Department: Traffic Operations
Topic: General
9
Traffic Operations - No Comment.
Issue Contact: Beth Sowder
Issue Contact: Wes Lamarque
Issue Contact: Eric Bracke
Department: Transportation Planning Issue Contact: Mark Jackson
Topic: General
15
Increase width of walkway connection to existing sidewalk from 3.0' to a preferred 4.0'-4.5'
16
Provide pedestrian walkway from parking lot to triplex. Provide separation for pedestrians per LUC
3.2.2 (D).1
Department: Water Wastewater Issue Contact: Jeff Hill
Topic: General
17
Page 4
Any finding made under subparagraph (1), (2) or (3) above shall be supported by specific
findings showing how the plan, as submitted, meets the requirements and criteria of
said subparagraph (1), (2) or (3).
37
Please revise the modification request to address the criteria. Also, note the zoning comments
regarding the modification request.
Department: Engineering Issue Contact: Katie Moore
Topic: General
22
If the ROW at the corner of the alley and Mountain has already been dedicated to the city, then the
property line should be shown as the diagonal edge of that ROW. Please provide the reception
number for the dedicated ROW
23
According to the Larimer County Urban Area Street Standards, a garage setback of 8' from the ROW
is only allowed if the fence/wall is set back at least 8' as well. See Figure 7-11 F. A variance request
is required concerning the placement of the garage door. It is recommended that the door be brought
flush with the wall of the building (closer to the alley), and that the variance request be addressed in
this manner. The variance request must be submitted according to LCUASS standards, and signed
and stamped by a professional engineer.
24
A variance request is also required because of the requirement to have an 8' utility easement beyond
the alley ROW.
25
When looking at the utility/site plan and the elevations, the statement that the building footprint will not
change does not appear to be true. Please show the accurate building envelope on the plans.
26
The two legal descriptions provided on the site plan do not match; they refer to two different blocks.
27
Please add the indemnification statement and the PE statement to the plans. A licensed professional
engineer (hired by you) must sign and stamp the plans at the time of approval.
28
If any cuts must be made into the alley or the street, they must be repaired according to standards.
Department: Excel Energy Issue Contact: Len Hilderbrand
Topic: General
11
EXISTING 4" PED MAIN IS 35' N. OF S. W. MTN AVE
12
EXISTING 3/4" PED SERVICE IS ON WEST WALL 25' S. OF N. WALL AND SERVICE LASY T W.
OF W. WALL
13
ANY RELOCATION OF EXISTING FACILITIES WILL BE AT OWNERS EXPENSE.
Page 3
• Something similar to the text from your written response to item (v) from your Statement
of Planning Objectives document explaining the background and history of the
development, and the lapse of office use,
• An explanation of what was approved with the building permit approval earlier this year,
• A description that explains that the request is to change the use of the building from "two-
family residential" to a "multi -family" building with three dwelling units. Explain that
there's no change to the existing southern half of the building from the approved
condition.
• Explain that the physical changes proposed are to remodel the ground floor of the
northern half of the building and to build a second story to that northern half.
• Explain in this text box that a modification to section 4.7(E)(4) is part of the request in
order to reduce the setback from the west property line from 5 feet to 3.25 feet, and to
reduce the setback from the east property line from 8 feet to 3.5 feet.
34
Increase the size of the elevation sheet to 24" x 36.". Upon approval of this major amendment both
the site plan sheet and the elevation sheet will need to be provided to us on mylar, and the only size
we accept is 24" x 36."
35
You will need to submit revisions. See the attached routing sheet for the number of copies. Because
the issues are reletavely minor, and the number of departments with issues are reletavely few, we will
reduce the review time of the re -submittal to a two -week turn around.
36
The modification request needs to justify the request in accordance with the specific criteria in the
LUC available to grant such a modification. These criteria can be found in section 2.8.2(H) of the
LUC. The specific standard citation you are requesting to modify must be stated. Section 2.8.2(H) of
the LUC states the following:
The Planning and Zoning Board may grant a modification of standards only if it finds that the
granting of the modification would not be detrimental to the public good; and that:
(1) the plan as submitted will promote the general purpose of the standard for which the
modification is requested equally well or better than would a plan which complies with the
standard for which a modification is requested; or
(2) the granting of a modification from the strict application of any standard would, without
impairing the intent and purpose of this Land Use Code, substantially alleviate an existing,
defined and described problem of city-wide concern or would result in a substantial benefit to
the city by reason of the fact that the proposed project would substantially address an
important community need specifically and expressly defined and described in the city's
Comprehensive Plan, or in an adopted policy, ordinance or resolution of the City Council, and
the strict application of such a standard would render the project practically infeasible; or
(3) by reason of exceptional physical conditions or other extraordinary and exceptional
situations, unique to such property, including, but not limited to, physical conditions such as
exceptional narrowness, shallowness or topography, or physical conditions which hinder the
owner's ability to install a solar energy system, the strict application of the standard sought to
be modified would result in unusual and exceptional practical difficulties, or exceptional or
undue hardship upon the owner of such property, provided that such difficulties or hardship
are not caused by the act or omission of the applicant.
Page 2
STAFF PROJECT REVIEW
City of Fort Collins
BRUCE FROSETH Date: 11/06/2002
524 SPRING CANYON CT
FT. COLLINS, CO 80525
Staff has reviewed your submittal for 419 W. MOUNTAIN AVE. MAJOR AMENDMENT, and
we offer the following comments:
ISSUES:
Department: AT&T Broadband Issue Contact: Dennis Greenwalt
Topic: General
AT&T Broadband does not have any problems with this Project. I would like to point out that in the
General Notes item 9 that if teh owner is responsible for the irrigation system that is in road right of
way that they will need to join UNCC so that if anyone wants to dig in this area they will be notified
and have to do locates on the system or risk the civil penalty of $200.00. Please see An Act, Senate
Bill 00-184, Section 4.,9-1.5-104.5.
Department: Post Office
Topic: General
5
Post Office - No Comments.
Issue Contact: Mike Spurgin
Department: Building Inspection Issue Contact: Rick Lee
Topic: General
10
Please find attached the various codes that the Fort Collins Building Department will enforce. This
two story construction should be provided on a new foundation or have the existing foundations's
design reviewed and approved by a Colorado licensed structural engineer.
Department: Current Planning Issue Contact: Troy Jones
Topic: General
29
Show the column locations of the front porch and front balcony supports on the site plan.
30
The Legal Description is shown in two locations on the site plan, but once it states the property is in
block 81, and once it states the property is in block 82. Which is it?
31
Don't use the Planning and Zoning Board signature block. It does not apply to this type of approval,
so take it off the Site Plan. Leave the Director of Planning Signature Block on the Site Plan, it is the
correct one to use for this type of planning approval, even though it goes to a P&Z hearing. Also add
the owner's certification block on the Sie Pan. See the attached example of an owner's certification
block.
32
There are two columns of general notes on the site plan. Label the general notes on the left as
"Utility Notes," and the ones on the right "Landscape Notes."
33
Add a text box on the site plan labeled "Project Description" that includes the following information:
Page 1