HomeMy WebLinkAboutINTERSTATE LAND - ODP - 49-02A - SUBMITTAL DOCUMENTS - ROUND 1 - DRAINAGE REPORTTlktf� ;-ULA oo�vtz lo"
T-tAq- MA
m 6 coUee.- A&V
I
1
1
1200 600 0 1200 2400
SCALE: 1" = 1200'
VICINITY MAP
INTERSTATE LAND
JOB NO. 39177.20
B-07-03
FIGURE 1
J•R ENGINEERING
A"I"m� rawa
asap Fal ftped Fla4 sk W-Fce cft co eon
am-�-eeae��c ero-�aE:esea�w�ia�r�room�
APPENDIX A
FIGURES
6. REFERENCES
"Storm Drainage Design Criteria and Construction Standards (SDDCCS)", Revised
January 1997, City of Fort Collins.
' "Technical Documentation for the Hydrologic Modeling of the Boxelder Creek/Cooper
Slough Basin, Volume 1, Hydrologic Evaluation for Existing Drainage Facilities,
' Technical Appendix A, B", January 25, 2002, Anderson Consulting Engineers,
Inc.
' "Technical Documentation for the Half -Foot Floodway Hydraulic Analysis of the
Boxelder/Cooper Slough Basin", Revised March 17, 2003, Anderson Consulting
' Engineers, Inc.
Urban Drainage and Flood Control District, "Urban Storm Drainage Criteria
Manual", Volumes 1-3, Revised June 2001.
I
' 8
i
4. EROSION CONTROL
' Erosion control will be provided as required by the City of Fort Collins. Erosion control
' measures will include the use of inlet filters, silt fences, straw bale barriers, sediment
traps and gravel construction entrances. Final design of the erosion control measures will
be included with Final Development Plans for the site.
5. CONCLUSION
This report complies with the City of Fort Collins "Storm Drainage Design Criteria and
Construction Standards" and the Urban Drainage and Flood Control District's "Urban
Storm Drainage Criteria Manual". Storm runoff.will be conveyed to historical drainage
paths through a system of curb & gutters, cross -pans, sidewalk chases, inlets & storm
I! drain pipe lines and detention ponds that will reduce the runoff discharge to historical 10
and 100-year discharge rates and provide water quality facilities, effectively controlling
runoff from the site and avoiding significant adverse impacts to downstream properties
due to the development of this site.
ill
quality features included in its design and this pond will discharge east into Boxelder
Creek in the southern end of the site.
The Historic Basin H2 is subdivided into Sub -basins B 1 and BOS. Sub -basin BOS is that
potion of the Historic Basin H2 that will continue to naturally runoff into Cooper Slough.
The 100-year historic discharge from Historic Basin H2 (21.7 cfs) will be reduced by the
amount Sub -basin BOS contributes (9.1 cfs) and the remainder (12.6 cfs) will be the
discharge for Detention Pond 6. All runoff from Sub -basin B1 will be collected and
discharged into Detention Pond 6. Detention Pond 6 will have water quality features
included in its design and this pond will discharge southwest into the Cooper Slough
approximately in the middle of the site.
The Historic Basin H3 is the developed Sub -basin C1. The 100-year historic discharge
from Historic Basin H3 (26.4 cfs) will be the discharge for Detention Pond 7. All runoff
from Sub -basin Cl will be collected and discharged into Detention Pond 7. Detention
Pond 7 will have water quality features included in its design and this pond will discharge
southeast into Boxelder Creek in the southern end of the site.
Portions of the proposed development are within the City and/or FEMA regulated
floodplains. An access street is proposed to cross the Boxelder Creek floodplain from
the existing I-25 Frontage Road to the proposed developed portion of the site. It is
expected that the crossing of the floodplain will be accomplished with a proposed earthen
embankment and bridge designed to pass the City's future condition flow rate of 4180cfs.
Areas proposed for development within the floodplain located adjacent to and upstream
of the proposed access street will be elevated above the floodplain by filling prior to
development in accordance with the applicable City and FEMA regulations. The
floodplain area located east of the Frontage Road will be filled in accordance with
applicable regulations.
Development of land within the floodplain caused by the backup of storm water at
Prospect Road should either be delayed until adequate storm water conveyances under
Prospect Road are constructed for Boxelder Creek and Cooper Slough or be done in a
manner that minimizes negative impacts to the floodplain. The proposed development
areas located within the backwater floodplain are expected to require fill in addition to the
conveyance improvements to eliminate the floodplain from these areas.
2
iI
' directly into existing natural drainage ways will have water quality features included in
their design.
As mentioned previously, there is an historic separation of storm runoff that discharge
into the Cooper Slough versus the Boxelder Creek. This historic separation will be
_ maintained as closely as possible. The site has been divided into three primary basins
(Basins A, B and C) along the lines of the previously mentioned three Historic Basins.
Basin A will discharge east into Boxelder Creek per Historic Basin H1. Basin B will
discharge west into Cooper Slough per Historic Basin H2. Basin C will discharge west
into Boxelder Creek per Historic Basin H3.
3.2 Specific Details
The Interstate Land development contains approximately 111 developed acres divided
between the three primary basins A, B and C for Rational Method runoff analysis. Sub -
basins Al, A2, A3, A4 and A5 will discharge east into Boxelder Creek via Detention
Ponds 1 through 5. Sub -basin B1 will discharge west into Cooper Slough via Detention
Pond 6. Sub -basin C1 will discharge west into Boxelder Creek via Detention Pond 7.
The Historic Basin HI is subdivided into Sub -basins Al through A5 and AOS. Sub -basin
AOS is that portion of the Historic Basin Hl that will continue to naturally runoff into
Boxelder Creek (see Overall Drainage Plan in Appendix). The 100-year historic
discharge rate from Historic Basin Hl (80.1 cfs) will be reduced by the amount Sub -basin
AOS contributes (16.3 cfs) and the remainder (63.8 cfs) divided between Detention Ponds
1 1 through 5.
Sub -basin Al runoff will be collected and discharged into Detention Pond 1. Detention
Pond 1 will discharge east into Detention Pond 2 without any water quality enhancement.
' Sub -basin A2 runoff will be collected and discharged into Detention Pond 2. Runoff
from Sub -basin A3 will be collected and discharged into Detention Pond 3. Detention
Ponds 2 and 3 will have water quality features included in their design and the discharge
tfrom these two ponds will be combined just prior to discharging east into Boxelder Creek
in approximately the middle of the site. Runoff from Sub -basin A4 will be collected and
discharged into Detention Pond 4. Detention Pond 4 will discharge east into Detention
Pond 5 without any water quality enhancement. Runoff from Sub -basin A5 will be
tcollected and discharged into Detention Pond 5. Detention Pond 5 will have water
1 5
I The existing Boxelder Creek and Cooper Slough conveyance structures under Prospect
Road are inadequate to convey the existing condition runoff produced by larger
' infrequent storms. Thus, in large runoff events, runoff conveyed to Prospect Road by the
Cooper Slough and Boxelder Creek, as well as runoff from the site, backs up behind and
overtops Prospect Road. According to the ACE Report, this overtopping diverts a
significant portion of the flow in Boxelder Creek from the creek and toward the Cache la
Poudre River floodplain located downstream of Prospect Road.
tBoth City of Fort Collins and FEMA regulated floodplains have been mapped on the
Interstate Land site. These floodplains are associated with the Cooper Slough, Boxelder
Creek and the backwater condition described above at Prospect Road. The City regulated
I floodplain is based on a larger flow rate than the FEMA floodplain and thus is more
restrictive. A floodway associated with Boxelder Creek has been defined by Anderson
Consulting Engineers for the City. The adoption of this floodway is currently under
consideration by the City. The boundaries of the proposed City Floodway and the City
100 year Floodplain are shown on the Overall Drainage Plan Exhibit contained in the
appendix of this report.
3. PROPOSED DRAINAGE PLAN
' 3.1 General Concept
The ACE report recommends that the site discharge the 2-year historic discharge for the
100-year developed condition. Due to the hydrograph timing, it appears from the
hydrological output data contained in the ACE report that undetained discharge from the
' Interstate Land site does not have a significant impact on the peak flow in Boxelder
Creek. The City has expressed concerns about stability issues within Boxelder Creek
should developed flows be discharged undetained into the creek. The City has indicated
that providing on -site detention of developed condition runoff from the site with peak 10
and 100-year release rates not to exceed the existing historical rates for those events
' would be an acceptable method to address this concern. Therefore, on -site runoff
produced by the developed portions of the proposed Interstate Land development will be
' routed to one of seven proposed detention ponds via curb & gutters, cross -pans, sidewalk
chases, inlets and storm drain pipe lines. These detention ponds will be designed to
discharge the 10 and 100-year developed flows at or below the predeveloped condition
(historical) peak rates for the respective storms. All the detention ponds discharging
1 4
Creek/Cooper Slough Basin, Volume 1, Hydrologic Evaluation for Existing Drainage
Facilities, Technical Appendix A, B", by Anderson Consulting Engineers, Inc. (ACE),
January 25, 2002 was consulted during preparation of this report. This report
incorporates the revised 3.67" rainfall amount for the 100-year, 2-hour storm in the
SWMM and HEC models for the drainage basin while revising the 100-year floodplain
boundary for Boxelder Creek and Cooper Slough.
1.4 Purpose and Scope of Report
This report defines the proposed overall drainage plan for the Overall Development of the
Interstate Land site and includes consideration of all on -site and tributary off -site runoff.
Included in this drainage report are preliminary design requirements for major detention
facilities. The final design of all drainage structures, including any temporary detention
and water quality facilities, required for this development will be completed with final
project development plans.
1.5 Design Criteria
This report and associated calculations were prepared to meet requirements established in
the City of Fort Collins "Storm Drainage Design Criteria and Construction Standards"
(SDDCCS), revised January 1997. Where applicable, the criteria established in the
"Urban Storm Drainage Criteria Manual" (UDFCD), revised June 2001, developed by the
Denver Regional Council of Governments, was also used.
2. HISTORIC DRAINAGE & FLOODING
Generally, the Interstate Land site drains in a southerly direction. Slopes are generally
less than 1.0% but greater than 0.5% across the site. Storm runoff is intercepted primarily
by Boxelder Creek, however there are those areas where storm runoff is intercepted by
' the Cooper Slough. Runoff from the western side of the site, Historic basin H2, flows
southwest into the Cooper Slough (see Figure 2 in the Appendix). Runoff from the
majority of the larger section, Historic Basin HI, flows southeast into Boxelder Creek.
' The remainder of the runoff from Historic Basin H1 flows to a low point on the north side
of Prospect Road where the runoff is then directed east to Boxelder Creek via a roadside
' ditch. Runoff from the primary proposed commercial site (southeast of the Frontage
Road), Historic Basin H3, flows to a low point on the north side of Prospect Road where
the runoff is then directed west to Boxelder Creek via a roadside ditch.
1 3
1. INTRODUCTION
• 1.1 Project Description
The Interstate Land project site is a proposed multi -use development that consists of
single family & multi -family residential, commercial & office space, and park & open
space areas. The Interstate Land site is located at the northwest corner of the intersection
of Prospect Road and Interstate 25 in the southeast corner of Section 16, Township 7
North, Range 68 West of the Sixth Principal Meridian in the City of Ft. Collins, Larimer
County, Colorado. The site is bounded by the Lake Canal and Crossroads East Business .
Center on the north, Sunrise Acres, Boxelder Family Estates and the Cooper Slough on
the west, Prospect Road to the south and Interstate 25 to the east (see Figure 1 in the
Appendix).
1.2 Existing Site Characteristics
The Interstate Land project site includes approximately 179 acres of land. The majority
of the site (area west of Boxelder Creek and south of the Cache La Poudre Ditch) is being
cultivated and the remainder is covered with grasses. As previously mentioned, the Lake
Canal crosses the site from west to east along the northern property line then turns south
along the west side of Interstate 25 crossing Boxelder Creek then joining with the Cache
La Poudre Ditch to pass east under Interstate 25. The Cache La Poudre Ditch crosses the
site from west to east just south of the Lake Canal crossing Boxelder Creek and passing
under Interstate 25 to continue easterly. Boxelder Creek meanders southwesterly through
the site from the northeast comer to its crossing under Prospect Road just west of the
Frontage Road. The Frontage Road bisects the southern boundary of the property and
swings east until it adjoins the west side of Interstate 25 and continues north paralleling
the interstate. The Cooper Slough crosses the site from north to south along the western
property line (see the Overall Drainage Plan in the Appendix).
The site lies within the Moderate Rainfall Erodibility Zone and the Moderate Wind
Erodibility Zone per the City of Fort Collins zone maps.
ILI 1.3 Master Drainage Basin & Other Drainage Reports
The Interstate Land site lies within the Boxelder Creek/Cooper Slough Drainage Basin.
This drainage basin continues southward where it terminates at the Cache La Poudre
River. The "Technical Documentation for the Hydraulic Modeling of the Boxelder
1 2
1J
1
1
11
[J
I
1
TABLE OF CONTENTS
PAGE
TABLEOF CONTENTS............................................................. :................................................ 1
1. INTRODUCTION................................................................................................................. 2
1.1 Project Description..................................................................................................... 2
1.2 Existing Site Characteristics...................................................................................... 2
1.3 Master Drainage Basin & Other Drainage Reports .................................................... 2
1.4 Purpose and Scope of Report ..................................................................................... 3
1.5 Design Criteria........................................................................................................... 3
2. HISTORIC DRAINAGE & FLOODING.............................................................................. 3
3. PROPOSED DRAINAGE PLAN..............................................:........................................... 4
3.1 General Concept......................................................................................................... 4
3.2 Specific Details...........................................................:.............................................. 5
4. EROSION CONTROL.......................................................................................................... 7
5. CONCLUSION......................................................................................................................7
6. REFERENCES...................................................................................................................... 8
APPENDIX A - FIGURES
APPENDIX B - HYDROLOGIC AND HYDRAULIC COMPUTATIONS
APPENDIX C - TABLES AND FIGURES
MAP POCKET - OVERALL DRAINAGE PLAN
I
1
I
1
' August 7, 2003
' Mr. Glen Schlueter
City of Fort Collins
Stormwater Utility
' 700 Wood Street
Fort Collins, CO 80521
' RE: Drainage Plan for the Interstate Land O.D.P.
Dear Glen,
' We are pleased to submit to you for your review and approval, this Overall Drainage Plan for the
' Interstate Land O.D.P. All computations within this report have been completed in compliance
with the City of Fort Collins Storm Drainage Design Criteria.
' We appreciate your time and consideration in reviewing this submittal. Please call if you have
any questions.
ISincerely,
JR ENGINEERING
' Prepared by,
Frank Feero, E.I.
Project Engineer
I
I
[1
I
Reviewed y,
cha 1 rake, P.E., L.S.
Director of Operations
1
I
I
I
1
1
I
I
I
I
I
I
I
1
OVERALL DRAINAGE PLAN
FOR THE
INTERSTATE LAND O.D.P.
Prepared by
JR ENGINEERING
2620 E. Prospect Rd., Suite 190
Fort Collins, Colorado 80525
(970) 491-9888
Preparedfor
Western VII Investment, I -LC
11859 Pecos Street, Suite 300
Westminster, Colorado 80234
(303) 469-4200
August 7, 2003
Job Number 39177.20
X:\3910000.all\3917720\Word\Reports\ODP Drainage Report.Doc
r
OVERALL DRAINAGE PLAN
FOR THE
INTERSTATE LAND O.D.P.
J-R ENGINEERING
A Subsidiary of Westrien