HomeMy WebLinkAbout300 SMITH STREET, OLD TOWN COMMONS - FDP - 39-03B - CORRESPONDENCE -Steve Olt Fwd Final Plan Checklist anc pmittal Requirements Page 1
From: Steve Olt
To: Bachmann & Associates, Inc.
Date: 03/30/2005 2:32:36 PM
Subject: Fwd: Final Plan Checklist and Submittal Requirements
Rosita,
Attached are the Final Plan Submittal Requirements and the Final Plan Checklist to follow for your 300
Smith Street, Old Town Commons - Final Compliance submittal to the City. They are for reference
only. You do not have to do a line -by-line response to these submittal requirements.
Please submit only the number of copies of each document as shown on the Final Compliance Review,
Project Routing Sheet that I provided to you on March 16th. That is the sheet with yellow highlights and
red ink showing that you must submit the following:
* 12 Site Plans
* 8 Landscape Plans
* 3 Building Elevations
* 5 Utility Plans
* 4 Drainage Reports
Also, there are the standard Development Review Application and Final Plan Development Review Fee of
$1,000.00 that must accompany your submittal. When you submit the Final Complinace plans we will do a
2-week turnaround on the first round of review.
Steve
CC: Marc Virata; Shelby Sommer