If meter pits, curb stops and fire hydrants for phase one are constructed within phase two then provide bollards
to protect them from traffic. Include a bollard detail on the detail sheet.
Response: Guard posts have been shown the Overall Utility Plan and a detail has been provided on sheet 24.
Number: 102 Created: 7/24/2003
See site, landscape and utility plans for other comments
Response: The comments on the utility plan redlines have been addressed. Please refer to Cityscape's
response letter for the site and landscape plan comments.
Number: 117
Created: 9/11/2003
Water services must remain the same size from the main to a point 5 feet downstream of the meter pit. Correct
all water services to reflect this.
Response: Water services have been corrected as requested.
Number: 118 Created: 9/11/2003
Provide utility easements for all water services up to and including the curb stop as well as fire hydrants.
Response: Utility easements have been provided as requested.
Number: 120
Created: 9/11/2003
Include 1 1/2"- 2" meter pit detail, concrete encasement detail and bollard detail on the detail sheet with the next
submittal.
Response: Details have been added as requested.
Department: Zoning
Topic: zoning
Number: 114
No comments.
Issue Contact: Peter Barnes
Created: 9/4/2003
If you have any questions regarding these issues or any other issues related to this project, please feel free to
call.me at (970) 491-9888.
Sincerely,
01/-�-
Xff Paulsen
JR Engineering
JP/sdr
Page 6
Topic: Plat
Number: 119
Created: 911112003
The maintenance note on the plat seems to indicate that the City will be responsible of maintaining all facilities
within a drainage easement on the site, while the City has only agreed to maintain the pond and the storm sewer
from Harmony to the detention. Please modify the note, to that effect and add that the City would only maintain
the detention pond after certification and acceptance of that pond, and after the two-year warranty period.
Response:
Topic: Utility Plans
Number: 112
Created: 7/28/2003
Please add the abbreviation labeling of Roof Drain, R.D. to the abbreviation list as well as that of Domestic
Service, D.S.
Please specify what type of pipe will be used for the drainage coming off the roof of Building 1. Provide a
cleanout at the bend.
Response: The requested abbreviations have been added. See note #17 on the cover sheet regarding roof
drains. Cleanouts have been provided.
Number: 121 Created: 9/11/2003
Please clearly call out that the inlet and storm sewer along Harmony Rd. will be built with Phase 1.
Add note to storm sewer profiles that all storm sewers to use watertight joints. Storm sewer installation to be
inspected by City of Fort Collins. Pipe B only to be maintained by City of Fort Collins, all other pipe to be
maintained by property owner.
Response: This is called out in note 4 on the utility plans. Additionally we have added phase 1 labels to
certain utilities for clarification. The requested notes have been added.
Department: Transportation Planning
Topic: Transportation
Number: 116
No further comments.
Department: Water Wastewater
Topic: Landscape
Number: 35
Issue Contact: Tom Reiff
Created:9/10/2003
Issue Contact: Jeff Hill
Created: 3/31/2003
9/10/03 As previously indicated, provide the required landscape/utility separation distances. Correct standard
general note on the landscape plans pertaining to landscape utility separation requirements. Maintain 10 feet of
separation between trees and water/sewer lines and 4 feet of separation shrubs and water/sewer lines.
Response: Joe Carter of Cityscape and Jeff Paulsen of JR Engineering met with Jeff Hill and Jeffs
concerns have been addressed.
Topic: Utility Plans
Number: 91
Created: 6/6/2003
9/10/03 As previously indicated, show and label all location of proposed as well as existing curb stops and
meter pits. All existing water services must have a curb stop attached to them or there is no way to control the
water.
Response: All meter pits and curb stops have been labeled.
Page 5
-Please create an existing and proposed striping plan for Harmony Road. The proposed striping plan sheet
should label/indicate striping to remain and proposed striping areas. In addition, indicate "existing bike lane
striping from taper to intersection to be refreshed". On the existing striping plan, show with cross -hatching
areas of striping which are to be removed.
Response: A demolition plan, sheet 17b, has been added for Harmony Road showing the limits of striping
removal. The existing bike lane striping has been shown to be "refreshed".
-Please provide what the building square footages are for the existing gas station and school uses that would use
this development for circulation. This will be filled in item 11 of the access permit.
Response: The square footages have been calculated based on the survey information. The gas station is
1,900 SF and the school is 12,810 SF.
-As a "heads -up", at the time the plans are approved and signed off, 5 copies (signed and stamped for the
construction plan) of the following sheets will need to be provided for CDOT's purposes:
>Cover Sheet
>General Notes
>Horizontal Control Plan
>Grading Plan
>Existing and Proposed Harmony Road Striping Plan
>Details Sheets
>Cityscape's Site & Landscape Plan
(also, 3 additional copies of the proposed and existing striping plan for CDOT is needed)
Response: Noted
Department: Stormwater Utility Issue Contact: Basil Hamdan
Topic: Erosion Control
Number: 64 Created: 4/7/2003
Please provide an erosion control escrow calculation in the text of the report.
Response: The erosion control cost estimate has been added to Appendix E of the drainage report.
Fourth Review
September 8, 2003
Same comment as last time.
Third Review
July 23, 2003
Please schedule a meeting with Bob Zakely to discuss this plan.
Response: Randall Provencio met with Bob Zakely and Bob's comments were resolved.
Second Review
June 3, 2003
The plan is still incomplete and difficult to follow, please correct.
Response: Randall Provencio of JR Engineering met with Bob Zakely and Bob's comments were resolved.
Page 4
2. Indicate curb type along the medians for the channelized-T proposed and provide a detail
3. Turning movements for large vehicles (WB-50) need to be verified on this design, especially because of
commercial trucks using this to serve the site and it allows them to head east on Harmony Road.
3. The proposed design is considered safe from a Traffic Operations standpoint, provided that the work north of
Timberline (as being designed by North Star Design) is completed concurrently. The channelized-T without
these improvements is a safety issue. It is required that this offsite design is approved concurrently with these
plans if not already approved with the Caribou Apartments project. This may involve needing to place the plans
from North Star into this submittal or getting North Star to separate this plan set out from the Caribou
Apartments design to be approved independently. In addition, this offsite construction will need to be done
prior to or concurrent with the channelized-T construction. As Caribou Apartments is under final compliance
review, this may not be a concern, but if that project does not move forward, the construction would need to fall
upon this development; there would be reimbursement available from Street Oversizing for this.
[7/23/03] After review of the submitted turning movements for a WB-50 and further analysis of turning
movements using the provided CAD drawings, please "shave off' portions of the medians as redlined. This
would appear to make the turning movements easier for these larger vehicles.
[9/16/03] Please be aware that Caribou Apartments has not completed final compliance review. As such, the
development agreement will need to obligate the developer of both design and construction of the offsite
improvements north of the channelized-T should Caribou Apartments not have these respective items
completed relative to the desired schedule of Harmony School Shops 4th.
Response: A southbound approach taper design has been provided that will provide a safe transition to the
channelized-T intersection.
Number: 105 Created: 7/28/2003
There is some concern on the amount of cross slope from the crown to the east side of Timberline directly in
front of Milestone Drive, it appears relatively flat. Please explore raising the east side of this median to achieve
greater fall across Timberline. It seems counterintuitive that the elevation noted at STA 15+97.25 is higher than
the spot elevations on either side. Please see redlines on plan view and cross section sheets.
[9/16/031
Please look at further raising the east side of the median from STA 17+50 to 18+50 to provide more of a cross
fall, it would be preferred if the slopes can at least match existing slopes. Also, please show street patching as
shown on the redlines with the typical street patching note. In addition, please show patching limits of 6' past
(half the lane width) where curb and gutter is to be added and add the same note regarding limits of repair that is
shown on Sheet 5.
Response: The cross slopes for Stations 17+50 through 18+50 have been increased to match the existing
cross slope. The minimum proposed cross slope is 1.5% where the existing cross slope is less than 1.5%. The
limits of street paving, shown on sheet 20, have been revised per the redlines and the requested note has been
added.
Number: 115 Created: 9/10/2003
Based on conversations with CDOT in processing their access permit, please address the following items:
-Add a note to Sheet 8 indicating that the access opening onto Harmony Road is to be centered upon the 35'
opening in the deeded access control line.
Response: The requested note has been added.
Page 3
2. Plat does not meet requirements of Sections 1.2.2 and 1.2.4 in Appendix E-6 of the Larimer County Urban
Area Street Standards.
3. Comments from March 26, 2003 Sheet have not been addressed. (#2 & #6)
4. If lot lines to be vacated were removed the plat would be cleaner.
5. Drainage/detention area at NEC of plat needs a Tract #.
6. Some easements are not locatable.
[7/28/031
Technical Services offered the following comments:
1. Plat needs sheet No. 1 of 2 and 2 of 2.
2. Some easements are not locatable.
3. The title (subtitle) of the plat is wrong - ("being a replat of lots 2 & 3 Harmony School Shops 1st...)
4. Is there a way to identify the lot corners (new) with a symbol? Lot lines are hard to distinguish.
(9/16/031
These comments are left as unresolved because of the plat being revised by the applicant.
Response: Comments dated 7128103 were partially addressed in the August 25, 2003 response but the plat was
in the process of being re formatted and so several issues remained outstanding. The issues should be
addressed with the current submittal.
Specfic responses follow:
1. Plat needs sheet No. 1 of 2 and 2 of 2.
This comment was because both sheets were labeled] of 2'. The plat has been reformatted to have
a total of three sheets and all are now labeled correctly.
2. Some easements are not locatable.
I believe all easement lines have been labeled and tied down by offset or bearing and distance so all
easements should now be locatable
3. The title (subtitle) of the plat is wrong — ("being a replat of lots 2 & 3 Harmony School Shops
151... )
I didn't understand what was wrong with the subtitle as written however; it has been revised and
hopefully addresses the concern.
4. Is there a way to ident6 the lot corners (new) with a symbol? Lot lines are hard to distinguish.
The interior lot corners have been identified with a solid dot. Found corners are identified with an
open circle, and set monuments are identified with a smaller dot and two concentric rings as shown
on the legend. I thing the format revision of breaking into 3 sheets has helped a lot in clarifying lot
lines, lot corners, and monuments.
Number: 110
Created: 7/28/2003
In general, it is difficult to follow the information on the plat. The lot lines within the platted boundaried are
hard to follow. The plat labels a 20' utility, drainage, access easement (Reception# 97028752) which seems to
point at a hatched area designated as an emergency access easement and there are other labels which are
difficult to place where they are defined.
[9/10/031 This comment is left as unresolved as the applicant has indicated an updated plat is still forthcoming.
Response: Similar comment as item 90. Concerns are addressed in the above comments
Topic: Utility Plans
Number: 76 Created: 5/22/2003
Based upon discussion among City Transportation on 6/5, the horizontal alignment of the channelized-T design
is satisfactory. The following items related to this design though, does need to be addressed.
1. Cross sections along the channelized-T at 50' intervals (as well as critical point such as median noses) are
needed to verify drainage patterns and vertical "ride". Also provide spot elevations on any plan view.
Page 2
November 12, 2003
Mr. Ted Shepard
CITY PLANNER — CITY OF FORT COLLINS
Current Planning
281 N. College Avenue
P.O. Box 580
Fort Collins, CO 80522-0580
V
J-R ENGINEERING
A Subsidiary of Westrion
RE: TIMBERLINE VILLAGE PDP - TYPE II (LUC) & FINAL COMPLIANCE #10-03
Dear Mr. Shepard:
ISSUES:
Department: Engineering
Topic: General
Number: 51
Issue Contact: Marc Virata
Created: 4/1/2003
Utility, access, and landscape permits are likely to be required by CDOT as the project continues.
[6/4/03]
It should be verified who will be working on the permit for CDOT to underground the overhead line within the
development. Because I believe the line is Xcel's, they likely need to be working with the Developer for that
portion of the utility permit.
[9/16/031
This comment is left as unresolved just as a heads -up for the applicant.
Response: Noted
Number: 54
Created: 41212003
Letters of intent are required for all offsite easements prior to the scheduling of a hearing. This appears required
for the property to the northeast as well as southwest.
[6/4/03]
The owner of the mobile home park also needs to sign a letter of intent for the sidewalk connection.
[7/23/031
A letter of intent from ARC was not received with the submittal, only a legal description of the area.
[9/9/03]
As neither a letter of intent or the actual easement has been provided for the proposed design, final compliance
has not been met and the drawings cannot be finalized for approval and signature. It is my understanding that
an alternative design for the trail is being looked at, this needs to be provided on the construction plan set.
Response: Noted
Topic: Plat
Number: 90 Created: 6/5/2003
Technical Services offered the following comments:
1. Boundary & legal closes
2620 Fast Prospect Road, Suite 190, Fort Collins, CO 80525 Page 1
970A91-9888 • Fax: 970-491-9984 • w Jrengineeringxorn
P�"inNAL C OM PL tANGE