of the Channelized T intersection, the relocation of the existing landscaping affected by the
proposed construction shall be coordinated with the City Forrester.
A note expressing the staff comment was added to the landscape plan within the Final
Compliance set and the construction set.
This concludes the response to the City of Fort Collins Planning Department comments.
Engineering and Utility response to comments have been provided under separate cover.
�ncer ly:
era
J e Carter
Cityscape Urban Design
6. A power point graphic of a channelized tee will be very helpful for the Planning and
Zoning Board work session.
So noted. Thank you.
Be sure that the eight -foot walk is specified on the site plan to match the utility plan east
of Building Two.
This requested change has been brought to the attention of the consulting engineers.
8. Sheet 7 of 14 should be reduced to a 24" x 36" format. Be sure to include the plan view
section per elevation as was done on the May submittal.
So noted. Thank you.
9. Please revise note number 31 in the following manner:
"Per Section 3.5.1(J)(6) of the Land Use Code, this P.D.P. is specifically conditioned such
that the placement of outdoor vending machines shall be prohibited unless screened from
view from the private drives, parking lots, public streets and residential areas by a screen
wall."
Note number 31 has been revised to read as requested.
10. Please note the following deadlines for the August 21n P & Z hearing:
One set of 81/2 x 11 reductions of the sheets 1 — 14 are due on Monday, Aug. 4`n
Nine sets of full-size sheets 1 —14 are due on Monday, Aug. 11`n.
Electronic images and graphics for the Board are due on Wednesday, Aug.13`n
The P & Z work session is scheduled for Friday, Aug. 15`n.
So noted. Thank you.
Number 35
Jeff Hill
As previously indicated, provide the required landscape and utility separation distances. Correct
standard general note on the landscape plans pertaining to landscape utility separation
requirements. Maintain 10 feet of separation between trees and water/sewer lines and 4 feet of
separation shrubs and water/sewer lines.
The Fort Collins Land use code no longer specifies that a separation distance of 10 feet be
maintained between trees and water/sewer lines. Only a 6-foot separation is required. The plans
meet this standard. Shrubs have been kept a minimum of 4 feet away from meters but not from
the water/sewer lines. The applicant's representative is not aware of a code section that specifies
such separation requirements.
Number 102
See site, landscape and utility plans for other comments
So noted. Thank you.
Number 113
August 27, 2003
Ted Shepard
City of Fort Collins
Community Planning and
P.O. Box 580
Fort Collins, CO 80522
Environmental Services
RE: Timberline Village PDP
Dear Ted,
coKn@@P(A'
urban design, inc.
3555 stanford road, suite 105
fort collins, colorado 80525
(970) 226-4074
fax (970) 226-4196
e@cityscapeud.com
Included below are the comments received from City Staff regarding the third round of
Project Development Plans for Timberline Village (Harmony School Shops). An explanation (in
italics) of how issues have been addressed follows each comment. These comments were
initially received on July 25, 2003.
The City of Fort Collins comments have been addressed on this set of Final Compliance Plans.
The City of Fort Collins redlines have been included in this submittal.
The P.D.P. is eligible for the August 21, 2003 Planning and Zoning Board meeting. The
item will be on the discussion portion of the agenda.
So noted. Thank you.
2. It is imperative that in order to remain on the August 21st agenda, a Letter of Intent be
provided from ARC to the City of Fort Collins Engineering Department for the
construction of the eight -foot wide asphalt sidewalk.
So noted. Thank you. The applicant and staff agreed that a condition of approval would be
issued with the decision of the Planning and Zoning Board. The condition would allow the walk to
be constructed within the Harmony Road right-of-way if no reasonable solution could be met with
the walk were currently proposed.
3. Harmony Road is planned for future transit service by Transfort. Therefore, in
accordance with City of Fort Collins Transit Design Standards and Guidelines, a bus
shelter needs to be secured with a financial escrow. The escrow amount is $3,500.00.
The applicant will provide a financial escrow for the future construction of a transit stop in the
amount of $3, 500.
The parapet walls for the Albertson's supermarket must feature a three-dimensional
cornice. As we have discussed, the cornice does not have to be a masonry material.
Camburas and Theodore Architects have provided the Albertsons parapet wall detail at the
request of staff.
5. The existing shrubs in the median in Timberline that will be reconstructed for the
channelized tee must be relocated or replaced.
A note has been added to sheet 2 of 14 directing the contractor to work directly with the City
Forrester on relocation and/or replacement of the plant material within the Timberline median.