RESPONSES TO COMMENTS
To: Katie Moore
Civil Engineer, Development Review
City of Fort Collins
PO Box 580
Fort Collins, CO 80522-0580
From: Jade P. Miller, P.E.
DMW Civil Engineers, Inc.
Date: November 5, 2003
Project: 637 Cowan Street
Fort Collins, Colorado
Project No. COW: 0301.00
143S WEST 29T" STREET
LOVELAND, CO B053B
(970) 461-2661
FAX (970) 461-266S
WWW. DMWCIVILENSINEERE.COM
The following is in response to engineering related comments made by the City regarding
to the aforementioned project dated October 10, 2003.
Item # 64
Response: The barricade detail has been updated as requested.
Item #72
Response: A variance is being requested for the driveway cut-out in the Right -Of -
Way
Item #73
Response: The drainage easement was shown on the utility plan. Easement
documents are being submitted with this submittal.
Item #39
Response: The drainage easement was shown on the plans. Easement documents
are being submitted with this submittal.
Item #67
Response: Printing error. The drainage report has been updated and resubmitted
in full.