Campus West Theatre Redevelopment, PDP (#23-04B)
Administrative Hearing
Findings, Conclusions, and Decision
August 10, 2006
Page 8 of 8
DECISION
The Campus West Theatre Redevelopment, PDP (#23-04B) is hereby approved by the Hearing
Officer, with the following condition:
In order to receive Final Plan approval, the applicant shall:
A) Section 3.2.1 (E) (6) Screening. Provide additional landscaping on the street side of the
two trash enclosures. A relocation of the two existing nearby parking lot tree islands to
the side of the enclosure facing the street may solve this standard if sufficient under -
story plantings of groundcover, shrub and parking lot tree placement is provided in the
island to screen the enclosure sufficiently. The result will not change the number of
parking spaces and would satisfy the intent of this Standard.
Dated this 10`h day of August, 2006, per authority granted by Sections
1.4.9(E) and 2.1 of the Land Use Code.
Pete Wray
Senior City Planner
Campus West Theatre Redevelopment, PDP (#23-04B)
Administrative Hearing
Findings, Conclusions, and Decision
August 10, 2006
Page 7 of 8
Elizabeth Street and City Park Avenue consists of building facades and useable
outdoor spaces. The proposed buildings are approximately 30 feet tall, greater
than the 20 feet minimum height and less than the five -story maximum.
The Hearing Officer has concluded that the proposed PDP meets all of the District Standards.
In addition, this project will provide a positive addition to the Campus West Community
Commercial District area, representing quality mixed -use development that will foster future
redevelopment in the area.
SUMMARY OF CONCLUSIONS
A. The Campus West Theatre Redevelopment, PDP mixed -use dwellings are permitted in
the Community Commercial District, subject to an Administrative Hearing, meeting the
procedural requirements located in Division 2.1 - General Procedural Requirements,
Division 2.2 - Common Development Review Procedures for Development Applications,
and Section 2.4 - Project Development Plan located in Article 2 - Administration.
B. The Campus West Theatre Redevelopment, PDP meets the Site Planning and Design
Standards in Sections 3.2.1-5, applicability and plat requirements located in Sections
3.1.1 - Applicability and 3.3.1 - Plat Standards, Building standards in Section 3.5
contained in Article 3 - General Development Standards, with the exception of
additional landscape screening of trash enclosures noted below as a condition of
approval.
C. The Campus West Theatre Redevelopment, PDP meets the zone district standards
located in Section 4.14 — Community Commercial District, contained in Article 4 —
District Standards.
Campus West Theatre Redevelopment, PDP (#23-04B)
Administrative Hearing
Findings, Conclusions, and Decision
August 10, 2006
Page 6 of 8
use projects in the area. The design's emphasis on pedestrian spaces, outdoor
experience and more urban streetscape are tailored to this site both in terms of
its immediate context and its wider context within the zone district.
All facades exceed the minimum wall articulations. Walls have clearly defined
bays, multiple changes in plane, materials and texture, arcades, awnings and
porticos. During Final Plan Review, we will ensure that all sides of each
building have high quality materials consistent with the front fagade. During
Final Plan Review, we will also review the color scheme. Outdoor eating areas
are recessed into the building mass and entries to the shops are covered with
either an awning or portico. All buildings have been designed with appropriate
base and top treatments including copper cladding, stucco cornices and split -
face CMU veneer bases.
4. Article 4 - Compliance with Applicable CC —Community Commercial District
Standards:
A. A. Purpose: The purpose of the Community Commercial District is as
follows:
"The Community Commercial District provides a combination of retail, offices, services,
cultural facilities, civic uses and higher density housing. Multi -story buildings are
encouraged to provide a mix of residential and nonresidential uses. Offices and dwellings
are encouraged to locate above ground floor retail and services. "
The proposed project is a two-story mixed -use building that wraps the corner of
Elizabeth Street and City Park Avenue. Though the project has been
substantially reduced from the original 5-story vision and from the approved
larger 3-story plan, the project is still in alignment with the vision of the Campus
West Community Commercial District Planning Study Report and the intent of
the zone district. The project will be a much needed aesthetic improvement for
the area and will hopefully lay the groundwork for high quality future
redevelopment in the area.
B. Permitted Land Use: Mixed -use dwellings are permitted in the Community
Commercial District, subject to a Type I — Administrative Hearing.
C. Development Standards:
1) Site Planning [Section 4.14 (E)(1)]—The configuration of shops in the proposed
project orients toward the public sidewalks along Elizabeth Street and City Park
Avenue. A diagonal pedestrian connection links the storefronts with surface
parking in the interior of the site. All public entries to retail shops open onto the
street side. Useable outdoor spaces have been provided.
2) Block Requirements [Section 4.14 (E)(2)]—One building will sit on a single
replatted lot, on an existing block. More than 50% of the lot frontage on both
Campus West Theatre Redevelopment, PDP (#23-04B)
Administrative Hearing
Findings, Conclusions, and Decision
August 10, 2006
Page 5 of 8
3) Site Lighting [Section 3.2.4]—Proposed site lighting meets our lighting
standards. Light sources are concealed and feature full shielding and sharp
cutoff luminaires, protecting adjacent properties from light spill and glare.
4) Trash and Recycling Enclosures [Section 3.2.5]—Trash enclosures have been
sized appropriately to accommodate trash and recyclables. Trash enclosure
elevations will be reviewed in Final Plan Review.
B. Building Standards — [Division 3.5]
1) Architectural Character, Building Size, Mass and Scale [Section 3.5 (B) and
(C)]—The design of the project sets an enhanced standard of quality for future
projects. It transitions appropriately from the existing neighborhood to the south
in terms of height and massing. The elevations are broken down into roughly
twenty- to thirty-foot bays, a fine grain that blends well with the existing
residential behind and commercial across the street. The project sets an
enhanced standard for future redevelopment with its architectural detailing,
commercial display windows and metal detailing.
2) Privacy Considerations [Section 3.5.1 (D)]—The project is quite urban in nature,
however zones of semi -private and public have been established relatively
effectively in the outdoor seating and planting areas. The mixed -use nature of
the site provides some natural settings for interaction among neighbors in a
public space. There are also some outdoor private to semi -private spaces in
the form of balconies.
3) Building Materials [Section 3.5.1 (E)]—Both the materials and colors proposed
blend well with existing materials and colors and set an enhanced standard for
future redevelopment. Clear glass is used in all commercial storefront windows
and residential fenestration.
4) Outdoor Storage Areas/Mechanical Equipment [Section 3.5.1 (1)]—All trash and
recycling areas are at least 20 feet from public walks and are screened from
view according to Section 3.2.5 of the Land Use Code. Trash enclosure
elevations will be reviewed in Final Plan Review. All HVAC equipment will be
located on the roof. Loading and delivery will be accommodated in the
northeast of the parking lot.
5) Mixed -use, Institutional and Commercial Building Standards [Section 3.5.3]—
The building is a mixed -use building which fronts on both W. Elizabeth Street
and City Park Ave with connecting walkways along both streets. Both frontages
are extended to the build -to lines. A single, large dominant building mass has
been avoided in the proposed building. Numerous changes in mass break up
the volumes and are integrally related to entries, building structure and the
organization of space.
The proposed project contributes to the uniqueness of the Community
Commercial zone district and sets a higher bar for future residential and mixed-
Campus West Theatre Redevelopment, PDP (#23-04B)
Administrative Hearing
Findings, Conclusions, and Decision
August 10, 2006
Page 4 of 8
The result will not change the number of parking spaces and would satisfy the intent of this
standard.
2) Access, Circulation and Parking [Section 3.2.2]
a. Development Standards: [Section 3.2.2 (C)]—Safety Considerations:
Pedestrians, bicycles and vehicles are separated to a large extent in this
project. All retail and residential uses take their primary access from the
street fronts along Elizabeth and City Park. There are bike racks along
both street fronts in close proximity to existing bike lanes along W.
Elizabeth Street. There is an internal drive aisle for vehicular access
with a diagonal pedestrian linkage through the building.
b. Curb cuts and ramps are provided throughout the site. [Section 3.2.2
(C)(2)]
c. The design includes convenient parking facilities for bicyclists and ramps
and walkways for clear and direct access to all entrances. [Section 3.2.2
(C)(4)] The bike lanes on W. Elizabeth Street have been recently
improved by a capital improvement project.
d. A Transportation Impact Study was performed and submitted with this
proposal. Pertinent excerpts of the study are attached to this staff
report. [Section 3.2.2(c)(8)]
e. All off-street parking spaces have unobstructed access to and from
public streets. All off-street parking is contained onsite. All parking
surfaces are either asphalt or concrete. Light fixtures proposed for the
parking area meet the standard in Section 3.2.2 (D)(3)(d) in part due to
the house side shields which shield the source of light from sight and
prevent spillover onto residential uses.
f. The parking lot is designed with clear and logical circulation routes
primarily for vehicles, but also for bicycles and pedestrians. The vehicle
routes will be striped for clarity; the pedestrian routes will be striped at
drive aisle crossings. Striping details will be finalized during the Final
Plan Review process. The bike lanes on W. Elizabeth are striped. All
landscaped islands are defined with curbs [Section 3.2.2 (E)]
g. Required parking setbacks are met.
h. Based on the submitted plans, this project will need to provide a
minimum of 43 parking spaces for the residential units and a maximum
of 119 commercial spaces. 107 spaces are provided off-street in the
surface parking lot, which meets the requirement. There is no on -street
parking. [Section 3.2.2 (K)]
i. Four handicap parking spaces are provided. Five are required
according to Code standards. This will be rectified in Final Plan Review.
[Section 3.2.2 (K)(5)(d)]
j. The parking dimensions indicated on the plans meet the minimum
dimensions required. Many spaces are dimensioned for overhang into
the paved and landscaped areas as allowed by Code. [Section 3.2.2 (L)]
Where spaces overhang paved areas, the adjacent walk is at least 6 feet
wide.
Campus West Theatre Redevelopment, PDP (#23-04B)
Administrative Hearing
Findings, Conclusions, and Decision
August 10, 2006
Page 3 of 8
S: CC: Existing single family house and undeveloped land (John XXIII University
Center)
SW: MMN: Existing multi -family residences (Matador Apartments)
W: CC: Existing commercial and retail (Campus West Liquor Depot)
NW: CSU: Campus Housing
A portion of this property (the old Campus West Theatre) went through an entitlement process
through the City as two Project Development Plans called Brazil '99 and Brazil 2004. Recently,
the property was sold to TNC Holdings, LLC and they also acquired the corner lot (the old
Schrader's gas station and Corner Store).
Neighborhood meetings were not required for this project. No written comments from the public
have been received by the planner on this project. The project has had a sign posted and this
hearing was noticed properly. The planner received a phone call from neighboring business
owner John Musa on July 24, 2006 in support of the project as currently proposed.
2. Article 2 - Administration:
This Subdivision, PDP complies with the applicable requirements of the LUC, specifically the
procedural requirements located in Division 2.1 - General Procedural Requirements, Division
2.2 - Common Development Review Procedures for Development Applications, and Section 2.4
- Project Development Plan in Article 2 - Administration.
3. Article 3 — General Development Standards
A. Site Planning and Design Standards [Division 3.2]
1) Landscaping and Tree Protection: [Section 3.2.1]—The Project Development
Plan provides full tree stocking, street trees, landscaped and hardscaped areas
throughout the project. Street trees on Elizabeth are placed at 30-40 foot
intervals in tree grates that are greater than sixteen square feet. Trees on City
Park Avenue are placed behind the attached sidewalk at 40 foot intervals.
There is not sufficient room for species on the approved street tree list so
ornamentals have been used. Sight distance triangles are maintained at the
driveway intersections. Existing trees on Elizabeth Street will be protected.
Screening of parked cars from the residential neighbor to the south and the
commercial neighbor to the east will be achieved with a new six-foot high wood
privacy fence and mixed plantings of shrubs and ornamental trees. Standards
have been met for interior parking lot landscaping.
The Hearing Officer has concluded that the Article 3, General Development Standards have
been met, with the exception of trash enclosure screening from adjacent streets. While
sufficient block walls have been provided at each of the two enclosures to screen the actual
trash container inside, the location of these two enclosures is protruding into the parking bays
and as such is directly visible from West Elizabeth Street and City Park Avenue. In Section
3.2.1 (E) (6) a combination of additional landscaping on the street side of the enclosure facing
the adjacent street is needed to further screen the enclosures. A suggestion at the Hearing
would be to shift the nearby parking lot tree island to the side of the enclosure facing the street.
Campus West Theatre Redevelopment, PDP (#23-04B)
Administrative Hearing
Findings, Conclusions, and Decision
August 10, 2006
Page 2 of 8
NOTICE OF PUBLIC HEARING: Evidence presented to the Hearing Officer established no
controversy or facts to refute that the hearing was properly
posted, legal notices mailed and notice published.
PUBLIC HEARING
The Hearing Officer, presiding pursuant to the Fort Collins Land Use Code, opened the hearing
at approximately 4:15 p.m. on August 2, 2006 in Conference Room A at 281 N. College Avenue,
Fort Collins, Colorado.
HEARING TESTIMONY, WRITTEN COMMENTS AND OTHER EVIDENCE
The Hearing Officer accepted during the hearing the following evidence: (1) Planning
Department Staff Report; (2) application, plans, maps and other supporting documents
submitted by the applicant and the applicant's representatives to the City of Fort Collins; and (3)
a tape recording of testimony provided during the hearing; (4) a sign up sheet of persons
attending the hearing; and (5) verbal comments from a nearby property owner. The LUC, the
City's Comprehensive Plan (City Plan), and the formally promulgated policies of the City are all
considered part of the evidence considered by the Hearing Officer.
The following is a list of those who attended the meeting
From the City:
Anne Aspen, City Planner
From the Applicant:
Scott Addington, Project Manager
Walt Gantt, Kenney Associates, Architects
From the Public:
None
FACTS AND FINDINGS
1. Compatibility with Surrounding Uses:
The surrounding zoning and land uses are as follows:
N: CC: Existing restaurant and retail (McDonald's and the Patterson Building)
E: CC: Existing commercial (Campus West Self Serve Car Wash and John XXIII
University Center)
City of Fort Collins
Commun_ , Planning and Environmental S ices
Current Planning
CITY OF FORT COLLINS
ADMINISTRATIVE HEARING OFFICER
TYPE 1 ADMINISTRATIVE HEARING
FINDINGS, CONCLUSIONS AND DECISION
ADMINISTRATIVE HEARING DATE:
PROJECT NAME:
CASE NUMBER:
OWNER:
APPLICANT:
HEARING OFFICER:
PROJECT DESCRIPTION:
August 2, 2006
Campus West Theatre Redevelopment,
Project Development Plan
#23-04B
Scott Addington
Trade Wind Project Solutions, LLC
314 Red Hawk Drive
Fort Collins, CO 80525
Randy Meyers
TNC Holding, LLC
2620 E. Prospect Road, Suite 100
Fort Collins, CO 80524
Pete Wray
Senior City Planner
This is a request to redevelop a now vacant 2.06 acre (89,859sf) site into a one -building mixed -
use development with 27 residential units and approximately 21,863 square feet of commercial
space. This is a second hearing on this project —it was initially proposed to be a two -building
mixed -use development with 37 residential units and approximately 14,265 square feet of
commercial space. The project was approved on April 28, 2006 with one condition pertaining to
lighting. The applicant subsequently modified the design substantially, which necessitates a
second hearing. The property is located on the southeast comer of W. Elizabeth Street and
City Park Avenue, the former site of the Campus West Theatre and Schrader's Gas Station.
SUMMARY OF HEARING
OFFICER DECISION: Approval with condition
ZONING DISTRICT: CC - Community Commercial District.
STAFF RECOMMENDATION: Approval
281 North College Avenue • P.O. Box 580 • Fort Collins, CO 80522-0580 • (970) 221-6750 • FAX (970) 416-2020
ADMINISTRATIVE HEARIN
PROJECT eA-)
DATE Z4,,/,
NAME ADDRESS ZIP PHONE EMAIL
XOTT O ,j(,-r� j Z&-3/4 4eAl l oc QL 6652 ZL2- 5) 4 f