Department: Zoning Issue Contact: Gary Lopez
Topic: zoning
Number: 129 Created: 6/23/2006
[6/23/06] provide bldg dimensions and foundation distance to nearest property line on site
plan.
Number: 130 Created: 6/23/2006
[6/23/06] Pole lights along south property line will require added light shields along s-edge
of fixture to prevent spillover to residential to south.
Be sure and return all of your redlined plans when you re -submit.
If you have any questions regarding these issues or any other issues related to this project,
please feel free to call me at (970) 221-6206.
Sincerely,
tAne H. eAsp&en��
City Planner
Page 10
Topic: Stormwater-Erosion Control
Number: 166 Created: 6/30/2006
[6/30/06] 1. The grading and erosion control notes on plan sheet #2 are incorrect. Please
delete.
2. Some of the BMP's in the report don't match the BMP's on the plan. Please make them
match.
3. 1 did not find a project schedule, PS/EFF calculations, and surety calculation. Please
provide.
Topic: WaterMastewater
Number: 7 Created: 1 /17/2006
[6/27/06] Please show the meter pit for this irrigation service.
[2/28/06] There is still one existing 4-inch water service in Elizabeth Street that needs to be
abandoned at the main or kept in service. Please clarify the intent for this water service.
[1/17/06] The existing water and sewer services in Elizabeth need to be abandoned at the
main if they have not already been abandoned there.
Number: 14 Created: 1 /17/2006
[6/27/06] Reminder comment for final compliance.
[2/28/06] Please provide calculations for the insulation thickness for the sewer line and for
vehicle loads on the shallow sewer line to ensure the sewer will not be negatively impacted.
[1/17/06] Due to shallow depth of sanitary sewer line, please provide design for insulation
thickness of sewer pipe.
Number: 102 Created: 2/28/2006
[6/27/06] Please show the easement on the plat.
[2/28/06] Please provide 10 feet of utility easement to the west of the north -south sanitary
sewer line. See redlined utility plan.
Number: 168 Created: 6/30/2006
[6/30/06] Project can go to a hearing.
Department: Stormwater-Water-Wastewater Issue Contact: Roger Buffington
Topic: Water/Wastewater
Number: 164 Created: 6/28/2006
[6/28/06] With the elimination of the south building, it may be possible to remove a portion
of the water main through the site. This will depend on PFA's fire hydrant requirements and
whether or not an acceptable layout for the fire line and domestic water services can be
developed. If the developer wishes to pursue this, a meeting with Water Utilities and PFA is
suggested.
Page 9
Number: 169 Created: 6/30/2006
[6/30/06] FIRE SPRINKLER: The building must be equipped with an approved, automatic
fire -sprinkler system.
Number: 170 Created: 6/30/2006
[6/30/06] WATER SUPPLY: Because the building will be fire sprinklered, the fire hydrant
located on the north side of Elizabeth Street meets our requirements for a second hydrant.
Number: 171 Created: 6/30/2006
[6/30/06] COMMERCIAL COOKING: With the production of grease -laden vapors, an
approved, automatic fire -extinguishing system shall be provided for the protection of
commercial -type cooking equipment.
Department: Transportation Planning Issue Contact: David Averill
Topic: Site Plan
Number: 21 Created: 1 /18/2006
[6/20/06] Still need to add a rack or two on the City Park frontage. Also, please show bike
rack locations on the utility plans. Thanks.
[3/1/06] Thanks for adding the racks on Elizabeth. I apologize that I didn't bring it up during
the first round, but we also need to add at least one rack on the west side of BLDG C,
somewhere in the vicinity of the patio. Thanks.
[1/18/06] Where will a customer of the proposed retail that arrives by bicycle park along W.
Elizabeth St.? There needs to be some bicycle parking located along the W. Elizabeth
frontage to serve the proposed retail uses.
Department: Stormwater-Water-Wastewater Issue Contact: Wes Lamarque
Topic: Stormwater
Number: 6 Created: 1 /17/2006
[6/27/06] Reminder comment for final compliance.
[2/28/06] The concept of the underground storm water quality system is approved. At final
design, the best design can be discussed and how maintenance will be achieved.
[1/17/06] Water quality mitigation is required per conceptual review comments. No water
quality treatment was proposed. The oil separator at the inlet is not mentioned as to what
the purpose is.
Number: 16
[6/27/06]
Created: 1 /17/2006
[2/28/06] Repeat Comment.
[1/17/06] Please revise the hydrology calculations per redlines.
Number: 167 Created: 6/30/2006
[6/30/06] Additional comments may follow at final compliance. Project can go to a hearing.
Page 8
Department: Light & Power Issue Contact: Doug Martine
Topic: electric service
Number: 1 Created: 12/30/2005
[6/15/06]
[12/30/05] All electric meters must be accessible without an access key or an escort. All
residential units must be individually metered.
Topic: Landscape Plan
Number: 127 Created: 6/15/2006
[6/15/06] Two street trees shown on Elizabeth St. need to be relocated to be a minimum of
40 ft. from the existing street light. These are approx. 90 ft. east of City Park Ave., and 20 ft.
west of the driveway entrance.
Topic: Utility Plans
Number: 128 Created: 6/15/2006
[6/15/06) Developer will need to coordinate power requirements and costs with Light &
Power Engineering (970)221-6700.
Department: PFA Issue Contact: Carle Dann
Topic: fire
Number: 56 Created: 1 /18/2006
[6/30/06]
[1/18/06] Fire hydrants are required, spaced not farther than 300 feet to any building, with
minimum flow requirement of 1,500 gallons per minute at 20 psi residual pressure.
Number: 93 Created: 2/28/2006
[6/30/06]
[2/28/06] Turning radii throughout the fire lane shall be a minimum of 25 feet for inside
radius, 50 feet outside turning radius.
Number: 117 Created: 3/1/2006
[6/30/06] This shall be mounted at the main entrance.
[3/1/06] Poudre Fire Authority requires a "Knox Box" to be mounted on the front of every
new building equipped with a required fire sprinkler system or fire alarm system.
Number: 118 Created: 3/1/2006
[6/30/06]
[3/1/06] Fire apparatus access roads shall be designed and maintained to support the
imposed loads of fire apparatus; the underground water -quality pond must be able to
support the weight of fire apparatus (40 tons).
Number: 119 Created: 3/1/2006
[6/30/06]
[3/1/06] The Fire Department Connections must be located on the perimeter of the
buildings, not the internal area between the buildings, to facilitate access to the FDCs.
Number: 165 Created: 6/30/2006
[6/30/06] FIRE LANE: The Emergency Access Easement must be reconfigured, to bring it
closer to the buildings (new structure configuration dictates the change). Minimum width
shall be 20 feet.
Page 7
Department: Engineering Issue Contact: Sheri Wamhoff
Topic: Utility Plans
Number: 27 Created: 1 /18/2006
[6/27/06] (Before Hearing) Repeat - stairs and some sort of wall are now shown in the row.
[2/28/06] (Before Hearing) Please provide the construction details asked for below. It
appears that there are footings in the row that will require an encroachment permit. See
below.
[1/18/06] Retaining walls/ seat walls may not encroach into the ROW without an
encroachment permit. This includes the footings. Please provide construction details of the
proposed walls, and add spot elevations of top and bottom of walls to the grading sheet.
Engineering will look at this and let the applicant know its thoughts regarding the issuance of
encroachment permits in this area.
Number: 31 Created: 1 /18/2006
[6/27/06) Need to be a little more specific in line 48 and list the required setback of 100' and
the granted variance of 50'.
[2/28/06] The variance request has been granted. Please state the variance on line 48 of
the General Notes, cover sheet.
[1/18/06] The parking setback distance from Elizabeth is not being met. Per the volumes in
the parking lot and volumes on Elizabeth the setback is 100 feet.
Number: 40 Created: 1 /18/2006
[6/27/06] Utilities are still shown outside a utility easement.
[2/28/06] [1/18/06] One sanitary and one stormwater manhole are located outside of the
utility easement. Not sure that this will be acceptable to the utilities.
Department: Engineering Issue Contact: Susan Joy
Topic: Utility Plans
Number: 114 Created: 2/28/2006
[6127/06] Final Compliance
[2/28/06] Sheet 12 - The Stormtech details need to be designed specifically to this site and
not refer to a design manual.
Number: 115 Created: 2/28/2006
[6/27/06] [2/28/06] Detailed comments to follow with Final Compliance. Please complete
Appendix E4 and submit with the first Final round. Any item not shown on the plans will
become a new comment that must be addressed before the plans can be approved.
Number: 143 Created: 6/27/2006
[6/27/06] Please remove all revisions from the title block. Revisions only occur after the
plans are approved, gone to mylar, and then are revised.
Number: 144 Created: 6/27/2006
[6/27/06) Sheet 5 - show all locations for the roof drains so that we can verify that water is
not being discharged over a public sidewalk.
Page 6
10 0
Topic: Plat
Number: 91 Created: 2/28/2006
[6/27/06] [2/28/06] Please see comments under other "topics" as they may affect the plat
as well.
Number: 100 Created: 2/28/2006 .
[6/27/06] (Before Hearing) Plat shows the easement but the rest of the plan sets do not.
[2/28/06] (Before Hearing) A drainage easement must be provided where the underground
water quality structure is located and where the storm sewer/manhole is located in the north
east corner of the property. Must be shown on all plan sets.
Number: 146 Created: 6/27/2006
[6/27/06] From Technical Services: Boundary and legal close, total area = 2.06 acre, legal
says 2.03.
Number: 147 Created: 6/27/2006
[6/27/06] From Technical Services: Note #1 on the plat says "Right of Way" is vacated with
this plat - that CANNOT be done by plat and can only be done by City Council.
From Engineering: If you wish to vacate row, please submit a TDRF application along with
$800 plus a legal description and exhibit. (Is this new?)
Number: 148 Created: 6/27/2006
[6/27/06] From Technical Services: How was City Park and West Elizabeth dedicated?
Number: 149 Created: 6/27/2006
[6/27/06] From Technical Services: The use of "more or less" as in this description is (I
believe) inappropriate. See attached handout.
Topic: Redlines
Number: 131 Created: 6/27/2006
[6/27/06] Please return all redlines with all future submittals.
Topic: Site Plan
Number: 160 Created: 6/28/2006
[6/28/06] The row is incorrectly shown. Stamped or colored concrete is not allowed in the
row. Structures (stairs, retaining walls, footings, etc) are not allowed in the row. See
original comment and history under General.
Number: 162
[6/28/06) Easements do not match the plat.
Number: 163
[6/28/06] Show all existing or proposed ramps.
Created: 6/28/2006
Created: 6/28/2006
Page 5
Department: Engineering Issue Contact: Susan Joy
Topic: General
Number: 94 Created: 2/28/2006
[6/27/06] [2/28/06] Need to show where the existing sidewalk along Elizabeth ends and
where the proposed construction starts.
Number: 95 Created: 2/28/2006
[6/27/06] Need to show existing or proposed ramps at the Elizabeth entrance (and correct
the symbols shown at the intersection). Need to discuss the ramp configuration at the City
Park entrance with Dave Averill and get back to you.
[2/28/061 Please show the existing directional ramps at the corner of Elizabeth and City
Park.
Number: 101 Created: 2/28/2006
[6/28/06] Colored concrete is still shown in the row (must be removed) and the row is now
incorrectly shown on all plan sets except the plat.
[2/28/06] Colored or patterned concrete is not allowed in the row. Please remove or this
may be addressed in the DA if the developer agrees to maintain the colored and/or
patterned sidewalk in perpetuity.
Number: 134 Created: 6/27/2006
[6/27/061 (Before Hearing) Curb returns must be designed in accordance with 8.2.9 of
LCUASS. 20' off Elizabeth and 15' of City Park. Please revise all plan sets. However, PFA
may still require 25' curb returns at this particular location. We can discuss this with PFA
and determine the final dimension for you.
Number: 135 Created: 6/27/2006
[6/27/06] (Before Hearing) Please update the TIS to reflect the current layout.
Number: 139 Created: 6/27/2006
[6/27/06] This project will be subject to the TDRF (effective January 1, 2006) for the Final
Compliance submittal. $1000 will be due at the final compliance submittal after hearing and
is good for 2 rounds of review. Please fill out and submit the attached TDRF application
with the final compliance submittal.
Number: 145 Created: 6/27/2006
[6/27/06] Will need to review the plans one more time before going to hearing to make sure
all of the items marked (Before Hearing) have been addressed. If I'm the ONLY department
that needs another round, I can do this with just a site plan with the understanding that the
rest of the plan sets have to be updated to match the site plan in Final Compliance. If there
are other departments needing another round, then a formal submittal will be required.
Topic: Landscape Plan
Number: 158 Created: 6/28/2006
[6/28/06] Show all utilities. Show and dimension all easements. Show all ramps (proposed
and existing). Remove sight distance triangles (none are required at 90 degree
intersections).
Number: 159 Created: 6/28/2006
[6/28/06] The row is incorrectly shown.
Page 4
Department: Engineering Issue Contact: Sheri Wamhoff
Topic: General
Number: 29 Created: 1 /18/2006
[6/27/06] (Before Hearing) Now that the building has gone from 3 stories to 2 stories, the
30' EA goes to a 26' EA and drive aisle. However, driveways that serve 12 or more units
need to be a minimum of 28' wide and then may taper back to 26'. Need to be 28' for at
least 25' and then taper from there. The purpose is to allow fora little more room fora car
wanting to turn right exiting the project while another is waiting to turn left. You may offset
the drive aisle to the right side versus tapering both sides if this helps your site layout. This
comment affects both the City Park entrance and the Elizabeth Street entrance. Please
update ALL plan sets accordingly.
[2/28/06] (Before Hearing) Per a meeting with PFA, the existing curb cut off Elizabeth will
have to be rebuilt to the 30' width. There may be some room for compromise on the curb
return radii requirement of 25' however. PFA may be able to defer to the LCUASS, table 8-
2, for curb return radii off a public street. I encourage you to speak with Carie Dann at PFA
as soon as possible.
[1/18/06] Need to show that the existing driveway off of Elizabeth Street aligns with the
proposed drive and is of adequate width. If not it will need to be reconstructed.
Number: 30 Created: 1 /18/2006
[6/27/06] The driveways still need to be built in accordance with drawing 707.
[1/18/06] The driveway onto City Park Ave is to be built to City driveway standards - with
directional ramps. Non directional are shown at this time.
Number: 34 Created: 1 /18/2006
[6/27/06] Please change the "pedestrian" easement to "access" on all plan sets where the
sidewalk is outside the row.
[2/28/06] The variance request for an attached sidewalk along City Park has been granted
PROVIDED THAT the sidewalk width is increased to V or the walk must be detached. The
portion of the sidewalk outside of public row must be dedicated either as row or as an
access easement. Please revise all plan sets (including the plat) accordingly.
[1/18/06] Sidewalk on City Park Ave doesn't meet minimum attached width requirement
Attached sidewalks are to be a minimum of 6 feet in width — The minimum width that can be
added to a sidewalk is 4 feet or the sidewalk will need to be rebuilt. With the elimination of
driveways, the new driveway and any curb, gutter and/or sidewalk that maybe damaged it
may make more sense to replace the walk rather than add to it.
Number: 38 Created: 1 /18/2006
[6/27/06] [2/28/06] [1/18/06) Refer to redlines for additional comments.
Number: 50 Created: 1 /18/2006
[6/27/06] (Before Hearing) Repeat comment. Easements do not match on all plan sets.
The row is now incorrectly shown along Elizabeth on the site/landscape and utility plans.
[2/28/06] (Before Hearing) Need to coordinate the easements on the plat with the other
plan sets so all plan sets provide the same information. The drainage and utility easement
shown along the east property line is not shown on the other plan sets.
[1/18/06]Per the improvements shown on the utility plans it appears that the area east of the
utility, access, and emergency access easement along the eastern property line needs to be
a utility and drainage easement.
Page 3
Number: 153 Created: 6/27/2006
[6/27/06] Why no lighting at the ped circle on the corner? This area must be lit per code as
a pedestrian walkway, and even though there is a street light not too far from the corner, it
seems like a good opportunity for some unobtrusive decorative lighting which would
enhance the corner at night and even highlight the architecture.
Number: 154 Created: 6/27/2006
[6/27/06) Lights specified must be mounted level not rotated. I think this is what is intended.
This note is just for the record.
Topic: Plat
Number: 155 Created: 6/27/2006
[6/27/06] (Pre -hearing) The plat will need to be adjusted to show revised emergency access
easement.
Topic: Site Plan
Number: 17 Created: 1 /17/2006
[6/28/06]
[1/17/06] Please remove all radius info and surveying information from the site plan. Also,
show the proposed finished improvements not the delineation between existing and
proposed.
Number: 138 Created: 6/27/2006
[6/27/06] Bike racks must be mounted on a hard surface like concrete.
Number: 140 Created: 6/27/2006
[6/27/06] There are still numerous stray lines on the site plan showing existing curb cuts
that will be removed, etc. These make the plans hard to read. Please remove these lines or
turn off that layer so that all that is shown is what's proposed.
Number: 141 Created: 6/27/2006
[6/27/06] The sidewalk should dip down to the handicap ramp on either side so that the
through walkway is not pinched. See redlines.
Number: 142 Created: 6/27/2006
[6/27/06] Other minor comments on redlines. Please return redlines with next submittal.
Number: 150 Created: 6/27/2006
[6/27/06] (Pre -hearing) PFA will want the emergency access to be closer to the building
now. This will require some thought about where deliveries will occur, as they are probably
going to want to stop in the fire access lane.
Number: 156 Created: 6/27/2006
[6/27/06] You will want to have some way to dedicate the residential parking—signage
perhaps.
Number: 157 Created: 6/27/2006
[6/27/06] Please be mindful of where HVAC equipment will be located, including air
conditioning compressors. They may require some tweaks to your site and landscape
plans.
Page 2
6aSTAFF PROJECT REVIEW
Citv of Fort Collins
SCOTT ADDINGTON Date: 07/03/2006
TRADE WIND PROJECT SOLUTIONS LLC
314 RED HAWK DR
FORT COLLINS, CO 80525
Staff has reviewed your submittal for CAMPUS WEST THEATRE REDEVELOPMENT PDP
- TYPE I, and we offer the following comments:
ISSUES:
Department: Current Planning Issue Contact: Anne Aspen
Topic: General
Number: 132 Created: 6/27/2006
[6/27/06] The following departments or agencies have indicated that they have no further
concerns with the proposed at this time: GIS, Poudre R-1, Park Planning, Building
Inspection, USPS.
Number: 133 Created: 6/27/2006
[6/27/06] For the record, this project was resubmitted 2 weeks after promised and did not
contain redlines or a planning response. We are doing our best to review. Update: redlines
were returned at 3pm on the day before review. In the future, please bring complete
submittal package, including all redlines and a response to previous comments.
Topic: Architecture Plans
Number: 82 Created: 1 /20/2006
[6/28/06] (Pre -hearing)
[1/20/06] Please add elevations of trash enclosure and storage buildings. Materials and
styling must blend with the main building design.
Topic: Landscape Plan
Number: 22 Created: 1 /18/2006
[6/28/06] (Pre -hearing) Street trees are required along City Park Avenue to standards.
Consider also placing a tree, perhaps an ornamental, in the seating circle at the corner.
[1/18/06] Street tree standards are not met along the west end of Elizabeth and all of the
City Park Ave. frontage. Please rectify.
Number: 137 Created: 6/27/2006
[6/27/06] There is not much turf onsite. Will the HOA or business assn. have someone on
contract to care for the landscaping? Seems like not much turf --would it be worth it? .You
might consider going to all perennials and shrubs.
Topic: Lighting Plan
Number: 85 Created: 1 /20/2006
[6/28/06]
[3/7/06]
[1/20/06] There is excessive light spillage beyond the southern boundary. Since the church
rectory is there and is residential in nature, measures will need to be taken to tone down the
lighting or provide additional shielding.