1. The normal electric development charges will apply to this
request.
2. There may be system modification charges associated with
development on this property and these charges will be at the
property owner's expense.
This completes staff (and outside reviewing agencies) review and
comments at this time. Additional comments and red -lined plans may
be forthcoming. Another round of staff review is determined to be
necessary to enable City staff to receive and review utility plans.
This proposal is subject to the 90-day revision re -submittal
requirement (from the date of this comment letter, being December 3,
2003) as set forth in Section 2.2.11(A) of the Land Use Code. Be
sure and return all of your red -lined plans when you re -submit The
number of copies of each document to re -submit is shown on the
attached Revisions Routing Sheet.
If you have any questions regarding these issues or any other issues
related to this project, please feel free to call me at 221-6341.
Yours Truly,
,�
4U�b
Steve Olt
City Planner
cc: Katie Moore, City Engineering
John Shaw
Current Planning File #36-03
Page 4
Department: Police
Topic: General
Number: 7
[11/10/031 No comments.
Issue Contact: Joseph Gerdom
Created: 11/10/2003
Department: Stormwater Utility Issue Contact: Wes Lamarque
Topic: Stormwater
Number: 13 Created: 11/26/2003
Please provide a grading and erosion control plan showing proposed
buildings with F.F. elevations as well as existing and proposed
contours. Erosion control notes and proposed mitigation should be
included on this plan.
Department: Water Wastewater Issue Contact: Jeff Hill
Topic: General
Number: 11 Created: 11/26/2003
[11/26/031 Please provide a utility plan that shows the existing
water, sewer, electric and gas as well as any proposed services.
Number: 12 Created: 11/26/2003
(11/26/03] Provide a 5 foot utility easement along the west side of
the proposed Lot 1 for the existing sanitary sewer line.
Department: Zoning Issue Contact: Jenny Nuckols
Topic: General
Number: 2 Created: 11/4/2003
[11/4/03] No comment
The following comments were expressed at staff review on November
26`':
Engineering:
1. The legal description does not close or match the subdivision
plat.
2. A set of utility plans must be submitted to the City for review.
Water/Wastewater:
1. A set of utility plans must be submitted showing, as a minimum,
the existing utilities around and to this property.
Stormwater:
1. A grading & erosion control plan must be submitted to the City
for review.
Page 3
Number: 5 Created: 11/5/2003
[11/5/03] Please clarify that the driveway easements are separate
private easements not being dedicated to the City, and,clarify who
they are being dedicated to.
Number: 6 Created: 11/5/2003
[11/5/03] Please define UE and DE. (Provide a legend)
Number: 8 1 Created: 11/21/2003
[11/21/031 How was the ROW for West Street, Elm Street, and the
alley originally dedicated?
Number: 9 Created: 11/21/2003
[11/21/031 A Development Agreement will be needed for this
subdivision to address concerns about the alley and sidewalk
improvements. The alley will have to be designed and constructed if
more than one dwelling unit takes access off of it. The current
sidewalk along Elm Street does not meet standards, so each lot would
be responsible for constructing a sidewalk to standards as it
develops.
Number: 14 Created: 12/3/2003
[12/3/03] Please submit a utility plan set per LCUASS.
Number: 15 Created: 12/3/2003
[12/3/03] Prior to formal submittal of this replat, the developer
asked about the possibility of vacating ROW on West Street. As
noted on the plat, some vacation of ROW on West Street has already
occurred, and the question of vacating more ROW was raised. if
further ROW vacation proposed by this development, then a formal
request for that vacation will need to be submitted to the City and
routed to all affected parties. The only ROW the City sees as a
possibility for further vacation is the triangular portion adjacent
to this replat, but this is a preliminary assessment and would,
again, need to be routed to and approved by all affected parties
(utilities, City departments, neighbors) and would also need to be
approved by City Council. The instructions for requesting ROW
vacation are attached.
Department: Light & Power Issue Contact: Doug Martine
Topic: Light & Power
Number: 1 Created: 11/4/2003
[11/4/03] Normal Electric Development Charges plus costs to modify
the electric system due to the requested replat will apply. Contact
Light & Power Engineering at 221-6700 to coordinate power
requirements and costs.
Department: Natural
Topic: General
Number: 10
(11/25/031 No Issues
Resources
with the replat.
Issue Contact: Doug Moore
Created: 11/25/2003
Page 2
I/
Citvof Port Collins
STAFF PROJECT REVIEW
Stewart & Associates Date: 12/3/2003
c/o Jack Blake
103 South Meldrum Street
Fort Collins, CO. 80521
Staff has reviewed your submittal for SHAW REP.LAT (PDP) - TYPE I
(LUC), and we offer the following comments:
ISSUES:
Department: Current Planning
Topic: Gas Service
Issue Contact: Steve Olt
Number: 19 Created: 12/4/2003
[12/4/03) Len Hilderbrand of Xcel Energy offered the following
comments: I
a. Existing gas mains are located on the east side of West
Street, south side of Elm Street; and, on the east side of the
north - south alley between North Shields Street and West
Street.
b. Gas service to 1112 Elm Street attaches to the gas main
located in the alley to the west.
Topic: General
Number: 16 Created: 12/4/2003
[12/4/03] Spelling of the Arthur Ditch is incorrect (Aurther) on
the Vicinity Map on the subdivision plat.
Number: 17 Created: 12/4/2003
[12/4/03] The title of the subdivision plat should be "Shaw Replat"
instead of "A Plat of Shaw PDP".
Number: 18 Created: 12/4/2003
[12/4/03] City staff is requesting that utility plans be submitted
for review. An administrative public hearing will not be scheduled
for this development request until utility plans are provided and
reviewed.
Department: Engineering
Topic: General
Issue Contact: Katie Moore
Number: 3 Created: 11/5/2003
[11/5/03] Please provide an 8' utility easement along the Alley
ROW.
Number: 4 Created: 11/5/2003
[11/5/03] Please provide the standard 9' utility easement along
West Street.
Page 1