HomeMy WebLinkAboutFIRST MAINSTREET BANK - PDP - 37-03 - CORRESPONDENCE -If you have any questions regarding these issues or any other issues
related to this project, please feel free to call me at 221-6341..
Youurrs� j�TruullQy, ,
Steve Olt
City Planner
cc: Marc Virata, City Engineering
First Mainstreet Bank
North Star Design
King Surveyors
Current Planning File #37-03
Page I
N
2. This development must dedicate additional street right-of-way..
for Boardwalk Drive to provide the ultimate width of 56' from
the centerline.
Stormwater:
1. The plans do not show improvements to the existing ditch along
the north side of the property. It is currently carrying 24
cubic feet per second of stormwater flows. Continue the drainage
easement to the east property line. Erosion protection is
needed.
2. Spillway and water quality details for the detention pond are
needed. Please clarify the swale location.
Light & Power:
1. Street trees must satisfy the separation requirement from street
lights ... 40' for shade trees and 15' for ornamental trees.
Water/Wastewater:
1. Connect the domestic water service to the main, not the fire
line.
2. Abandon, to the street, or use existing water and sanitary sewer
service stubs.
Transportation Planning:
1. Is the proposed right turn lane on Boardwalk Drive too long?
2. The sidewalks should stay to the City's standards at the
intersection.
3. Relocate the bicycle rack by the handicapped ramp.
Traffic Operations:
1. Another TIS must be submitted for review by the City.
This completes staff (and outside reviewing agencies) review and
comments at this time. Additional comments and red -lined plans may
be forthcoming. Another round of staff review is determined to be
necessary. This proposal is subject to the 90-day revision re -
submittal requirement (from the date of this comment letter, being
December 3, 2003) as set forth in Section 2.2.11(A) of the Land Use
Code. Be sure and return all of your red -lined plans when you re-
submit. The number of copies of each document to re -submit is shown
on the attached Revisions Routing Sheet.
Page 10
Department: Zoning Issue Contact: Peter Barnes
Topic: zoning
Number: 3 Created: 11/12/2003
[11/12/031 Need to label the building envelope. If it's what I
think it is, then the northernmost projection of the building
appears to be outside the envelope.
Number: 4 Created: 11/12/2003
(11/12/03) In order for the building to be more than 15' from the
Boardwalk ROW as shown, the development must comply with the outdoor
plaza exception in 3.5.3(B)(2)(d). Planning Dept. should determine
if compliance is obtained.
Number: 5 Created: 11/12/2003
(11/12/031 Per Section 3.2.1(E)(5)(b), each landscape island needs
to have 1 tree per 150 sf of landscape island area. It appears that
2 or 3 more trees need to be planted in numerous islands.
Number: 6 Created: 11/12/2003
[11/12/03] This property is in the residential neighborhood sign
district, wherein only 1 sign per exterior wall is allowed. They
must indicate on the elevation drawings where the probable wall sign
locations will be. For their information, individual letter wall
signs are limited to a maximum height of 1211, logos and cabinet wall
signs are limited to a maximum height of 18". Monument signs are
limited to 32 sf per side, 5' maximum height.
Number: 7 Created: 11/12/2003
[11/12/03) How tall are the light poles?
Number: 8 Created: 11/12/2003
[11/12/03) The trash enclosure seems to be quite a distance from
the building - about 1701. Can it be located closer?
Number: 9 Created: 11/12/2003
[11/12/031 The plat name should indicate somewhere that it's a
replat of the Plat of Rafferty's PUD, instead of "Part of the
southeast quarter of section 36, etc...". There is a recorded and
valid Rafferty's PUD subdivision plat.
The following comments were expressed at staff review on November
26`h:
Engineering:
1. The striping plan as submitted is not acceptable. A new
Transportation Impact Study (TIS) must be submitted and
reevaluated.
Page 9
Number: 34 Created: 11/26/2003
(11/26/03) City standards require that an 8' bike lane be striped
on a 2-Lane Arterial when adjacent,to the curb. The proposed 5' bike
lane with the new left turn lane into Whalers Way will require
additional internal transportation discussions.
Number: 35 Created: 11./26/2003
(11/26/031 The Boardwalk bike lane along the development's proposed
right turn lane into the site needs to be located adjacent to the
curb rather than being exposed to traffic for over 500 feet.
However, to transition between the right turn lane at Whalers Way
and align to the existing bike lane north of the site, the bike lane
will need to transition between the right turn lane and the through
lane approximately 60 feet from Whalers Way with roughly a 50'
transition period (see red lines). This will also require that the
bike lane width be constructed to 8' as per City standards.
Number: 36 Created: 11/26/2003
(11/26/03) Is the entire length of the development's proposed right
turn lane necessary?
Department: Water Wastewater Issue Contact: Jeff Hill
Topic: General
Number: 23 Created: 11/25/2003
[11/25/031 Provide utility easements for all curb stops.
Number: 24 Created: 11/25/2003
[11/25/031 Water services may not be connected to proposed fire
lines.
Number: 26 Created: 11/25/2003
[11/25/031 All existing stubs must be used or abandoned at the
main. Show and, label all existing stubs and clearly define the
abandonment procedures.
Number: 27 Created: 11/25/2003
[11/25/031 Maintain a 5 foot separation between all water
mains/sewer mains and the flow line of the curb and gutter. Loop
the proposed water main between Boardwalk Dr. and Whalers Way to
promote water quality, system reliability and facilitate service
connection for the future building on lot 2.
Number: 28 Created: 11/25/2003
(11/25/03] See site, landscape and utility plans for other
comments.
Topic: Landscape plan
Number: 22 Created: 11/25/2003
(11/25/031 Maintain required landscape/utility separation distances
on the landscape plans.
Page 8
Topic:- Utility Plans
Number: 29 Created: 11/25/2003
[11/25/031 Please call out all proposed storm lines on the utility
plans.
Please provide riprap protection at all culvert outlet locations.
Please provide a detail design for the proposed spillway outlet from
the pond. Spillway should be riprapped.
The water quality outlet details are lacking. Please provide an
actual detail for the proposed outlet box, not the generic UDFCD
detail.
Please note that the level of detail for the submitted plans is OK
for a PDP hearing, additional comments may arise as more details are
submitted at Final Compliance.
Department: Transfort
Topic: General
Number: 12
[11/24/031 No comments
Issue Contact: Garold Smith
Created: 11/24/2003
Department: Transportation Planning Issue Contact: Tom Reiff
Topic: Transportation
Number: 30 Created: 11/26/2003
(11/26/031 Construct the entire length of the sidewalk along
Boardwalk as a detached walk to Harmony Road. At Harmony Road
directional access ramps, similar to the ones on the SW corner of
the intersection need to be constructed.
Number: 31 Created: 11/26/2003
(11/26/03] Consider relocating the bike rack near the entrance and
the HC parking stalls so that cyclists can utilize the HC ramp as
well.
Number: 32 Created: 11/26/2003
[11/26/031 Due to ditch constraints along Whalers Way, if the
standard 5' detached sidewalk with a narrowed parkway width is not
possible than an 6' attached walk would be sufficient. Also
directional access ramps are required at the Boardwalk / Whalers Way
intersection as well as the driveway at Whalers Way.
Number: 33 Created: 11/26/2003
[11/26/03] The intersection striping for southbound traffic on
Boardwalk will remain the same. Therefore, the 6' bike lane needs to
be placed between the right turn lane and the through travel lane
per City standards.
Page 7
0
Department: Police Issue Contact: Joseph Gerdom
Topic: Landscape plan
Number: 19 Created: 11/25/2003
[11/25/031 Landscape & Lighting:
West elevation has potential security/safety issues - the apparent
lack of soffit lighting and sight obscuring Serviceberry create
opportunities for unobservable access to building and unlawful
congregation. would recommend lower plant materials (under 41) and
soffit lighting.
Distance from building, location of access, and large plant
materials (dogwood) create safety/security issue at Trash enclosure.
Would recommend moving closer to building, improve lighting, and
reduce height of plant materials and/or use of hostile plants.
Department: Stormwater Utility Issue Contact: Basil Hamdan
Topic: Drainage Plan
Number: 21 Created: 11/25/2003
(11/25/031 Basin 03 needs to be drained into the proposed detention
pond, please make sure that the swale is significant enough to drain
that area into the proposed pond.
It is suggested that a storm sewer be stubbed out of basin 1 into
the pond for the pad site.that is being designed with this plan.
Topic: Erosion Control
Number: 20 Created: 11/25/2003
(11/25/03)
November 24, 2003
1. Submittal is incomplete, please provide a complete
sediment/erosion control submittal for review.
NOTE: The standard erosion control notes have been updated. Please
replace the notes on the current plan with the new notes (available
from stormwater development review). we can email you an electronic
version of the updated notes upon request.
Topic: North drainage swale
Number: 25 Created: 11/25/2003
(11/25/031 The drainage swale on the north end of the site should
be checked to see if it has enough capacity for off -site flows
coming from west of this site and going through the site. The swale
should be improved to provide adequate capacity if needed and the
easement should be enlarged to accommodate these flows. According
to the master plan that swale carries 23.8 cfs of off -site flows.
Page 6
Number: 16 Created: 11/24/2003
(11/24/031 The new sidewalk along Whalers Way is required to be
detached 8' from the existing curb with a 5' sidewalk, not attached
as shown. Right-of-way should then be dedicated to the back of
walk.
Topic: Utility Plans
Number: 17 Created: 11/24/2003
(11/24/031 Indicate the curb return sizes proposed for all
intersections on both public and private areas and ensure these curb
returns meet LCUASS access requirements in Chapter 8.
Number: 44 Created: 12/2/2003
[12/2/03] While not required at this time, as a head -up, at time of
final submittal after a theoretical hearing, the utility plans will
need to show flowline profiles and cross sections along Boardwalk
Drive to demonstrate the widening of the roadway for the right turn
lane will meet all LCUASS requirements.
Number: 48 Created: 12/2/2003
[12/2/03) The driveway out to Whalers Way appears to be exceeding
the amount of area sheetflowing drainage across the public walk.
750 square feet of influence area is the maximum area allowed to be
designed to drain out the driveway. For the driveway out to
Boardwalk Drive, the flow arrows indicate no drainage across the
sidewalk, although there appears to be a discrepancy or issue with
not enough grade with a spot elevation of 03.99 behind the sidewalk
combined with the 04 contour being 40 feet east.
Department: Light & Power Issue Contact: Doug Martine
Topic: Landscape plan
Number: 2 Created: 11/10/2003
[11/10/031 The landscape plan needs to be adjusted to provide 40
ft. clearance between shade trees and streetlights (15 ft. if the
tree is an ornamental). A streetlight layout plan has been sent to
Steve Olt via inter -office mail 11-10-03.
Topic: Light & Power
Number: 1 Created: 11/10/2003
(11/10/03) Developer needs to coordinate the power requirements and
a location for a pad type transformer with Light & Power Engineering
(221-6700).
Department: Natural Resources
Topic: General
Number: 37
[11/28/031 No Issues.
Issue Contact: Doug Moore
Created:.11/28/2003
Page 5
M
Number: 18 Created: 11/24,/2003
[11/24/03] The plat should dedicate an emergency access easement to
satisfy PFA requirements. This is for the main drive aisle from
Whalers Way to Boardwalk Drive as well as the internal parking lot
loop which connects to the main drive aisle. Will the building be
sprinklered?
Number: 50 Created: 12/2/2003
[12/2/03] Technical Services offered the following comments:
1. Legal and plat close, see typo in curve table (redlined).
2. The "sub title" of the plat needs to say: "Being a replat of
Rafferty's P.U.D.", located in the southeast 1/4 . . . . .
3. A "Block 1" designation isn't needed, lot 1 and lot 2 is
sufficient and less confusing.
Topic: Transportation
Number: 10 Created: 11/24/2003
[11/24/03] In discussion with City Transportation, the striping
plan proposed by the development (which would eliminate separate
through and right -turn movements on both legs for Boardwalk Drive)
is not acceptable. Separate through and right turn movements must
be maintained due to the high number of right -turn turning
movements. As a result, the TIS will need to be amended based upon
single left turning movements instead of the double lefts assumed in
the study.
Number: 13 Created: 11/24/2003
(11/24/031 The sidewalk along Boardwalk shall be placed at the edge
of the new right-of-way as noted in issue 11.
Number: 14 Created: 11/24/2003
[11/24/031 The access ramps at the intersection of Harmony.and
Boardwalk shall be "directional" as recently constructed on the Bank
One site across the street.
Number: 15 Created: 11/24/2003
[11/24/03] The access drive out to Boardwalk Drive is a variance to
the LCUASS, Chapter 7 with regards to its separation from Whalers as
well as offset from the driveway into the apartments across the
street. A variance request is required from the consultants design
or traffic engineer. Of particular concern in my opinion is the .
center turn lane being shared between the Bank's entrance off of
Boardwalk and the apartments across the street. With about only 40'
of separation between the drives and Boardwalk an arterial street,
isn't there a possibility that the proposed striping design will
result in movements for northbound into the apartments and
southbound into the bank wanting to both utilize this center turn
lane at the same time? I'd like for the TIS or the design engineer
to address this concern as I feel it's unsafe.
Page 4
Topic: Utility Plans
Number: 49 Created: 12/2/2003
[12/2/03] Len Hilderbrand of Xcel Energy, or Public Service (PSCO),
offered the following comments:
a. No trees may be planted within 4' of gas lines.
b. PSCO has a 4" MW gas main along the west edge of the proposed
bank. The main lays 4' west of the east right-of-way line of
Boardwalk Drive.
C. PSCO also has a 2" MW gas main located 5' south of the north
right-of-way line of East Harmony Road.
d. To schedule proposed service please call Jim DeWilde at 970-
225-7844.
Number: 52 Created: 12/2/2003
[12/2/03] Dennis Greenwalt of Comcast Cable (TV) indicated that
they would like to make the developer aware of their fiber optic
cable that will need to be located so that any conflicts can be
identified and resolved before work begins.
Number: 54 Created: 12/3/2003
[12/3/03.1 Please see the Landscape Plan marked up by Doug Martine
of Light & Power with the street light and street tree locations.
Department: Engineering Issue Contact: Marc Virata
Topic: General
Number: 51 Created: 12/2/2003
[12/2/03] Engineering Pavement offered the following comment:
Whalers Way was.paved in 2001, triple impact fees will be assessed
if the street is cut. A mill and inlay may be needed.
Topic: Plat
Number: 11 Created: 11/24/2003
[11/24/031 The TIS indicates that all the curbs at the Harmony and
Boardwalk intersection are at "finished" locations. The current
street width would need to change in order to allow for future
double lefts; the Bank One project across the street dedicated
additional right-of-way to allow for this future widening. Please
ensure 56' of right-of-way is provided from the existing street
centerline of Boardwalk Drive; this width is exclusive of the
developer's right turn lane which is additional right-of-way
required.
Page 3
M
Topic: Landscape plan
Number: 46 Created: 12/2/2003
[12/2/03] A low, 3' high berm directly south of the building (see
red -lined Landscape Plan) would be good to help screen East Harmony
Road from the offices in the bank building.
Number: 47 Created: 12/2/2003
[12/2/03] There are 12 Colorado Spruce trees shown in the 80'
Harmony Road setback area. -These evergreen trees are not in the
plant palette for the setback area in the Harmony Corridor Standards
and Guidelines.
Topic: Site Plan
Number: 40 Created: 12/2/2003
[12/2/03] Staff recommends relocating the proposed trash enclosure
to the south of the 5 parking spaces on the east side of the drive,
in the island (see red -lined Site Plan).
Number: 41 Created: 12/2/2003
[12/2/03] The west side of the building does not meet the "build -
to" line standard set forth in Section 3.5.3(3)(2)(b) of the LUC.
Assuming the inclusion of the patio spaces to satisfy Section
3.5.3(B)(2)(d)1- Exceptions to the standard in the LUC, is there not
room and the ability to move the building or enlarge the patios to
put the landscaped beds at the base of the patio walls within 10, to
15, from back of sidewalk? This would better address the statement
in Section 3.5.3(B)(2)(d)1 that says "..... Such a larger front yard
shall have landscaping, low walls, fencing or railings, a tree
canopy and/or other similar site improvements along the sidewalk
designed for pedestrian interest, comfort and visual continuity".
Number: 42 Created: 12/2/2003
[12/2/03] The 80' Bicycle and Pedestrian Access Easement shown on
the Site Plan places the building and vehicle area 80' back from the
East Harmony Road right-of-way. Per the Harmony Corridor Standards
and Guidelines, this 80' setback has to be only from the future edge
of pavement, not the ROW. This excessive setback is acceptable if
that is the applicant's choice.
Number: 43 Created: 12/2/2003
[12/2/03] There are some "Do Not Enter", "Wrong Way", "End Median",
and "Steel Structure" notes on the Site Plan that do not make sense.
Number: 45 Created: 12/2/2003
[12/2/03] The proposed low seat walls around the patios on the Site
Plan are not shown (and must be) on Exterior Building Elevation Plan
4 of 4, West Elevation.
Page 2
I/
STAFF PROJECT REVIEW
Citvof Fort Collins
VF Ripley Associates Date: 12/3/2003
c/o Cathy Mathis
401 West Mountain Avenue, Suite 201
Fort Collins, CO. 80521
Staff has reviewed your submittal for FIRST MAINSTREET BANK, PDP -
TYPE I (LUC), and we offer the following comments:
ISSUES:
Department: Current Planning Issue Contact: Steve Olt
Topic: Building Plans
Number: 53 Created: 12/3/2003
[12/3/03) Please contact Rick Lee of the Building Department (221-
6.760) for information on the current codes and standards that they
will be enforcing relative to this building.
Number: 57 Created: 12/3/2003
[12/3/03] The Exterior Building Elevations Plans must indicate a
PDP Submittal, not PUD. There are no PUD's in Fort Collins anymore.
Topic: General
Number: 38 "Created: 12/2/2003
[12/2/03] Per the Planning Objectives, the existing bank facility
is at the southwest, not southeast, corner of Harmony Road and Lemay
Avenue.
Number: 39 Created: 12/2/2003
[12/2/03) Per the Planning Objectives, the proposed number of on -
site parking spaces is 52, which is more than the allowed 46 spaces
per LUC. Section 3.2.2(K)(3) of the Land Use Code (LUC) does allow
an applicant to request Alternative Compliance to the parking ratio
for non-residential uses; however, the applicant must support and
justify the additional spaces per this section of the LUC. This has
not been done in the Planning Objectives or on any other document.
Number: 55 Created: 12/3/2003
[12/3/03] Please check the sheet numbering. The Site & Landscape
Plans are numbered Sheets 1 & 2 of 3, but there is no Sheet 3. The
Exterior Building Elevations Plans are numbered Sheets 3 & 4 of 4.
Probably this is a 4-3heet set that needs to be numbered
accordingly.
Number: 56 Created: 12/3/2003
[12/3/03] The building footprint on the Lighting Plan is
inconsistent with the footprint on the Site & Landscape Plans.
Page I