I do have a Current Planning file (#42-03C) for the Adrian Subdivision, First Filing - Final Compliance
submittal, including a completed application dated 11/10/2004 and signed by you. City staff reviewed this
application, discussed it at staff review on December 8, 2004. A comment letter dated December 14, 2004
was sent to you, DMW Engineers, and King Surveyors. In the next to last paragraph of this letter it states,
in part, that:
This proposal is subject to the 90-day revision re -submittal requirement (from the date of this
comment letter, being December 14, 2004) as set forth in Section 2.2.11(A) of the Land Use Code.
Therefore, it is my opinion that a re -submittal must be made or an extension request must be addressed
and submitted to Cameron, either as soon as possible.
Thank you for the modification of standard request document for Lemay Avenue Estates.
Steve
>>> Troy Jones <troyzerjess@yahoo.com> 04/19 11:26 AM >>>
Steve,
Here's the file for the Lemay Av. modification
request.
Also, after talking to Cameron, it sounds like I don't
need an extension letter because we haven't submitted
for final compliance yet, so 2.2.11(A) doesn't apply,
because there's nothing technically under review. He
clarified that at this point, until we submit our
final compliance application, the section 2.2.11(C)
applies. He did clarify that once we do submit our
final compliance application, the section 2.2.11(A)
will apply.
Troy
Do you Yahoo!?
Yahoo! Mail - Helps protect you from nasty viruses.
http://promotions.yahoo.com/new—mail
CC: Cameron Gloss
Steve Olt - Adrian Subdivision, First F
Page 1
From:
Steve Olt
To:
Troy Jones
Date:
05/02/2005 3:46:12 PM
Subject:
Adrian Subdivision, First Filing
Troy,
Please see the attachment regarding the Adrian Subdivision, First Filing - Final Compliance review. It
verifies the fact that you did submit Final Compliance documentation for this development request on
November 10, 2004. After completing the first round of development review a letter, dated December 14,
2004, with staff's concerns and comments was sent to you. At the end of this letter it stated that this Final
Compliance review was subject to the 90-day revision re -submittal requirement set forth in Section
2.2.11(A) of the Land Use Code. At this time we are past the 90-day requirement.
To date we have not received a re -submittal of the Adrian Subdivision, First Filing - Final Compliance
documentation. Also, I am not aware of a request for an extension, as allowed per Section 2.2.11(A) of the
Land Use Code, having been submitted. To ensure that the review and approval of this development plan
is being diligently pursued and processed you must re -submit plans or submit a request for an extension
no later than Friday, May 6, 2005.
Steve