HomeMy WebLinkAboutFORT COLLINS COLORADOAN - PDP - 41-03 - CORRESPONDENCE -27. If the portions of Phase Two exceed 40 feet in height, then a shadow analysis will
be needed.
28. The demolition of any existing structure or portions of an existing structure will
require a Demolition Permit from the Building Inspection and Permits
Department.
29. The new office building will be subject to the architectural requirements of
Section 3.5.3(D) of the Land Use Code.
30. Since the new office building faces southwest, shade trees should be considered
between the parking lot and the building. For further information on energy
conservation, please contact Doug Swartz, Energy Service Engineer, City of Fort
.Collins Utilities, 221-6700
determine if this existing deficiency needs to be addressed by the proposed
expansion.
19. The Transportation Department is concerned about the number of driveways
intersecting with Riverside. Generally, the City desires as few driveway/arterial
intersections as possible. The Transportation Impact Study should address this
issue. The anticipated use and volume at these driveways should be estimated.
The T.I.S. should address Phase One and Phase Two improvements and note that
two driveways are scheduled for. closure with Phase Two. The site is unique in
that there are numerous circulation needs associated with the operation. For
example, the site must accommodate large truck circulation, small truck
deliveries, trash removal, carrier pick-up, employee parking and customer access
all of which contribute to the requirements of multi -faceted internal circulation
system. For further information, please contact Eric Bracke, 221-6630.
20. The driveways should be designed with a radial curb return.
21. Be sure to provide a bicycle rack near the office entrance.
22. Be sure to provide a sidewalk ramp system to accommodate the existing
pedestrian crosswalk across Riverside.
23. This site is in the Spring Creek drainage basin where the new development fee is
$2,175/acre which is applied to imperviousness greater than 350 square feet. The
standard drainage and erosion control report and construction plans are required
and they must be prepared by a professional engineer registered in Colorado.
24. This report needs to document the outfall system to the river which may need
some maintenance. The site presently does not drain onto Riverside which is
already carrying too much runoff, so no additional runoff will be allowed. Onsite
water quality extended detention is the recommended water quality treatment.
Parking lot islands could possibly be used to treat the runoff.
25. The site is on Stormwater inventory map #10I. A copy of the map can be
obtained from the Utilities office at 700 Wood Street. As long as there is no
increase in the volume of stormwater runoff, the Natural Resources Department
will not require an easement if the outfall system drains across their natural areas
and is changed in quantity, quality or character. For further information, please
contact Glen Schlueter, 221-6681.
26. Phase One will be assessed a Capital Expansion Fee of $0.53 cents per square
foot based on the "commercial" category. The Phase Two expansion would be
"industrial" and assessed a fee of $0.15 cents per square foot. The fee is collected
at the time of building permit issuance. Please note that the fee is adjusted
annually based on the Denver -Boulder consumer price index.
11. A Transportation Impact Study will be required. To determine the scope of this
study and which intersections to analyze, please contact Eric Bracke, 221-6630.
Keep in mind that all modes of travel must be analyzed, not just vehicles.
12. The Street Oversizing Fee will be based on square footage and anticipated trip
generation for the new office building and the new portions of the existing
building. The City also collects the Latimer County Road Impact Fee. Please
contact Matt Baker, 221-6605, for an estimate of these fees which are payable at
the time of building permit issuance. Please note that fees are adjusted annually
based on the Denver -Boulder consumer price index. (There is information on the
Street Oversizing Fee on the City's website at WWW.fCgOV.COM.
13. Any existing sidewalk, curb, or gutter that is damaged or in disrepair must be
repaired prior to issuance of Certificate of Occupancy. .
14. There is a concern about the closeness of the parking stalls to the travel lane in
Riverside. One of the Engineering standards is that parking stalls be set back
from the travel lane a specified distance based on the volume of traffic within the.
parking lot. Where this standard cannot be achieved, a variance procedure is
available. This is an internal variance that may be reviewed by the City Engineer.
This is not a Modification of Standard to be reviewed only by the Planning and
Zoning Board. The Transportation Impact Study should address this issue. A key
factor may the turnover of the parking spaces in question. If these are long-term
parking spaces for employees only, then this needs to be documented in support
of a variance. It appears that the setback will have to be in the 40 to 50-foot
range.
15. Driveways should intersect with Riverside as close to 90 degrees as possible for
25 feet.
16. Riverside Drive is classified as an "arterial" street and is eligible to be classified
as a "constrained" arterial. If considered constrained, there must be 51 feet of
right-of-way from property line to centerline of the roadway. Therefore,
additional right-of-way dedication may or may not be needed depending on how
much right-of-way exists now. It appears that one extra foot of right-of-way may
be needed, as well as a 15-foot wide utility easement both of which may be
dedicated by separate legal document as opposed to replatting.
17. A Development Agreement may be needed prior to recording of the plans
depending on the extent of public improvements that are constructed for this
expansion. For further information, please contact Susan Joy, Development
Review Engineer, 221-6605.
18. Riverside is a sub -standard arterial and lacks on -street bike lanes. The
Transportation Impact Study should address the bicycle Level of Service to
4. Please add street trees on 30 to 40-foot intervals along Riverside. The area along
Riverside in front of the new Phase Two improvements are more industrial in
character and this area may warrant more landscape material for screening
purposes. For example, foundation shrubs will be needed along the southwest
elevations of the Phase Two mail room, press support and press components.
5. For Phase One, the trash enclosure must be constructed to match the predominant
material of the building and be sufficiently sized for containers for recyclable
materials.
6. A sidewalk connecting the new office building's main entrance to the street
sidewalk should be provided including an enhanced crosswalk (including change
of texture) where this walk crosses a drive aisle.
7. The site will be served electricity by the City of Fort Collins Light and Power
Department. The existing electrical transformer is in place and any relocation
would be at the applicant's expense. Normal electrical charges will apply. Any
system modification to upgrade the power for an office will also be at the
developer's expense. For an estimate of these charges please contact Alan Rutz at
221-6700. Please contact Doug Martine if the internal workflow requires
electrical supply on both the east and west sides of the building. .
8. A Commercial One ("C-1") Form must be completed by an electrical contractor
to determine entrance capacity. The location of the electrical transformer must be
coordinated with Light and Power and Planning so that it is not located along the
roadway, but, rather, in a less visible location yet within ten feet of hard surface
for emergency change -out. The large switching cabinets in southeast comer of
the property must be preserved as these serve a large regional area.
9. The site is served by the City of Fort Collins Water and Wastewater Department.
There is a 12-inch diameter water main in Riverside. There are two sanitary
sewer lines in Riverside. There is an eight -inch diameter sewer line west of
McHugh and a 12-inch diameter sewer line east of McHugh. If there is a new or
increased water or sewer service, then Plant Investment Fees and Water Rights (or
cash -in -lieu) will be due for the net increase over that which is already in place.
Fees would be due at the time of building permit issuance. If there is a need to
abandon any water or sewer service, then such service must be abandon all the
way back to the main. For further information, please contact Roger Buffington,
221-6681.
10. A fire flow test can be set up with Poudre Fire Authority. Any open floor area
that exceeds 5,000 square feet must be treated with an automatic fire
extinguishing system. The building must be within 300 feet of a fire hydrant. All
portions of the building's exterior must be within 150 feet of the designated fire
access lane. For further information, please contact Ron Gonzales, 221-6570.
�j
CONCEPTUAL REVIEW STAFF COMMENTS
City of Fort Collins
ITEM: New Office for the Coloradoan (demolition of the old
Collins Cashway building) and Remodel and Expansion of
Existing Building at 1212 Riverside Drive
MEETING DATE: August 25, 2003
APPLICANT: The Coloradoan c/o Mr. Corky Bradley, RB+B Architects,
Inc., 315 East Mountain Avenue, Fort Collins, CO. 80524.
LAND USE DATA: Request to demolish the old Collins Cashway building and
construct a new two-story office building containing approximately 37,000 square feet as
Phase One. Phase Two would include expansion and remodel of the existing Coloradoan
Building at 1212 Riverside by adding a new press and mailroom between the existing
building and the old Collins Cashway building. Phase Two also includes partial
demolition of 1212 Riverside. The loading would be relocated to the rear and an existing
metal building on the east side of the site would be removed. There would be other
minor upgrades as well.
COMMENTS:
1. The parcel is zoned I, Industrial which allows both offices (Phase One) and print
shops (Phase Two), subject to Administrative Review.
2. The maximum number of parking 'spaces for general office is 3.0 spaces per 1,000
square feet of gross floor area. Additional parking spaces may be allowed based
on occupant load, square foot per employee, or other factors unique to the
applicant's request such as shift overlap. Please refer to Section 3.2.2(K)(4) for
further information on allowances for increased parking for offices. The print
shop is considered industrial and is allowed a maximum of .75 spaces per
employee.
3. Since the parking lot exceeds 100 spaces, 10% of the interior must be in
landscape islands.
COMMUNITY PLANNING AND ENVIRONMENTAL SERVICES 281 N. College Ave. P.O. Box 580 Fort Collins, CO80522-0580 (970) 221-6750
CURRENT PLANNING DEPARTMENT'
Comm, zy Planning and Environmental rvices
Current Planning
City of Fort Collins
August 25, 2003
Mr. Corky Bradley
RB+B Architects, Inc.
315 East Mountain Avenue
Fort Collins, CO 80524
Dear Corky:
For your information, attached is a copy of the Staff's comments for New Office
Building for the Coloradoan (demolition of the old Collins Cashway) and Remodel
and Expansion of Existing Building at 1212 Riverside Drive which was presented
before the Conceptual Review Team on August 25, 2003.
The comments are offered by staff to assist you in preparing the detailed components of
the project application. Modifications and additions to these comments may be made at
the time of formal review of this project.
If you should have any questions regarding these comments or the next steps in the
review process, please feel free to call me at 970-221-6750.
Sincerely,