From: Susan Joy
To: Steve Olt; troy@architex.com
Date: 9/10/04 9:59AM
Subject: Adrian Hearing
Hello!
I just ran over all of the comments to you Steve and I just wanted to go over The Schedule so we get
where we need to go with this project.
Troy requested that they be allowed to go to hearing as soon as possible in order to make their financing
deadlines. We briefly discussed the timeline at Staff Review on Wednesday and it was as follows:
We (the city) need to get revised utility plans from the applicant by Monday or Tuesday early a.m.
Stormwater/W W/Eng will review by Tuesday afternoon. If the plans are acceptable, the project can go to
hearing. The letter needs to go out no later than the 16th in order to get a public hearing scheduled by the
30th. We will not schedule the hearing until the drainage issues have been sufficiently addressed.
Troy - please contact me so we can talk about what we need on the plan and profiles. I can also meet
with you and/or Jade today or Monday. You've got one shot to get it right if we are going to hit.your dates,
so let's meet and make sure its correct.
You might want to run the plans by Glen, Jeff and Wes before you submit too.
If I have the timeline wrong, please respond to all so that we have it straight over here.
Thanks!
Susan
CC: Glen Schlueter; Jeff Hill; Wes Lamarque