Pre -Submittal meetings are offered to assist the designer/builder by assuring, early on in the
design, that the new commercial or multi -family projects are on track to complying with all of the
adopted City codes and Standards listed below. The proposed project should be in the early to
mid -design stage for this meeting to be effective and is typically scheduled after the Current
Planning conceptual review meeting.
Applicants of new commercial or multi -family projects are advised to call 416-2341 to schedule a
pre -submittal meeting. Applicants should be prepared to present site plans, floor plans, and
elevations and be able to discuss code issues of occupancy, square footage and type of
construction being proposed.
Construction shall comply with the following adopted codes as amended:
2009 International Building Code (IBC)
2009 International Residential Code (IRC)
2009 International Energy Conservation Code (IECC)
2009 International Mechanical Code (1MC)
2009 International Fuel Gas Code (IFGC)
2009 International Plumbing Code (IPC) as amended by the State of Colorado
2011 National Electrical Code (NEC) as amended by the State of Colorado
Accessibility: State Law CRS 9-5 & ICC/ANSI A117.1-2003.
Snow Load Live Load: 30 PSF / Ground Snow Load 30 PSF.
Frost Depth: 30 inches.
Wind Load: 100- MPH 3 Second Gust Exposure B.
Seismic Design: Category B.
Climate Zone: Zone 5
Energy Code Use
1. Single Family; Duplex; Townhomes: 2009 IRC Chapter 11 or 2009 IECC Chapter 4
2. Multi -family and Condominiums 3 stories max: 2009 IECC Chapter 4.
3. Commercial and Multi -family 4 stories and taller: 2009 IECC Chapter 5.
Fort Collins Green Code Amendments effective starting 1-1-2012. A copy of these requirements
can be obtained at the Building Office or contact the above phone number.
City of Fort Collins
Building Services
Plan Review
416-2341
3. Section 3.2.2(H) comains standards that address drive-in facilities. lease note that under (H)(4), the
building must provide a walk-up service as well as the drive-in service. This standard could also be
achieved by providing an interior sit-down function. At this time, there does not appear to be either a
walk-up or an interior sit-down options.
4. Please note that under Section 3.5.3(D), in the case of multiple building development, each individual
building shall include predominant characteristics shared by all buildings in the development. Further, a
standardized prototype design shall be modified as necessary to comply with these requirements.
5. Since a Convenience Shopping Center is permitted subject to consideration by the Planning and Zoning
Board, a neighborhood information meeting is required.
6. Section 3.5.3(D) also requires that a each building be designed such that there is a distinctive base and
top treatment. In the case of flat -roofed buildings, this requires a cornice, sloping false mansard, parapet
or other architectural element that creates a distinctive top.
7. As a Convenience Shopping Center, the development is also subject to the requirements of Section 3.5.5.
Please note that there are specific setbacks required that may differ from the Build -To Line requirements in
Section 3.5.3. Staff is willing to work with the applicant on site design that best accomplishes the overall
objectives of creating an attractive development that serves all modes of travel.
8. The proposed development project is subject to a Type 2 (Planning and Zoning Board) review and public
hearing. The applicant for this development request is required to hold a neighborhood information
meeting prior to formal submittal of the proposal. Neighborhood meetings offer an informal way to get
feedback from your surrounding neighbors and discover any potential hiccups prior to the formal hearing.
Please contact me, at 221-6750, to assist you in setting a date, time, and location. I and possibly other
City staff, would be present to facilitate the meeting.
9. Please see the Development Review Guide at www.fcgov.com/drg. This online guide features a color
coded flowchart with comprehensive, easy to read information on each step in the process. This guide
includes links to just about every resource you need during development review.
10. This development proposal will be subject to all applicable standards of the Fort Collins Land Use Code
(LUC), including Article 3 General Development Standards. The entire LUC is available for your review on
the web at http://www.colocode.com/ftcollins/landuse/begin.htm.
11. If this proposal is unable to satisfy any of the requirements set forth in the LUC, a Modification of Standard
Request will need to be submitted with your formal development proposal. Please see Section 2.8.2 of
the LUC for more information on criteria to apply for a Modification of Standard.
12. Please see the Submittal Requirements and Checklist at:
hftp://www.fcgov.com/developmentreview/applications.php.
13. The request will be subject to the Development Review Fee Schedule that is available in the Community
Development and Neighborhood Services office. The fees are due at the time of submittal of the required
documents for the appropriate development review process by City staff and affected outside reviewing
agencies. Also, the required Transportation Development Review Fee must be paid at time of submittal.
14. When you are ready to submit your formal plans, please make an appointment with Community
Development and Neighborhood Services at (970)221-6750.
4. Please contact the City's Traffic Engineer, Joe Olson (224-6062) to schedule a scoping meeting and
determine if a traffic study is needed for this project. In addition, please contact Transportation Planning
for their requirements as well.
5. Any public improvements must be designed and built in accordance with the Larimer County Urban Area
Street Standards (LCUASS). They are available online at:
http://www.larimer.org/engineering/GMARdStds/UrbanSt.htm
6. The plat for the previous project at this location was never signed and filed so this project is responsible
for dedicating any right-of-way and easements that are necessary. Easements and right-of-way can be
dedicated by a replat of the property or the process by separate document.
7. A new set of utility plans and a new Development Agreement will be required and recorded once the
project is finalized.
8. A Development Construction Permit (DCP) will need to be obtained prior to starting any work on the site.
Department: Electric Engineering
Contact: Rob Irish, 970-224-6167, rirish@fcgov.com
1. Light & Power has existing 3-phase electric facilities running adjacent to this site along Boardwalk Dr.
There is also a 3-phase vault at the SW corner of the post office entrance that could serve as the source
for this site. Any relocation or modification to existing electric facilities will beat the owner's expense.
2. A transformer location will need to be determined within 10' of a paved surface. Per the landscape
standards of the Land Use Code, the transformer must be screened from public view but must be within
ten feet of hard surface for emergency change -out.
3. A C-1 form and a One -line diagram will need to be submitted to Light & Power Engineering showing your
power needs.
4. Owner will be responsible for Electric Capacity Fee, Building Site charges and any system modification
charges that apply.
Coordinate with Light & Power Engineering @ 970-221-6700.
Current Planning
Contact: Ted Shepard, 970.221-6343, tshepard@fcgov.com
1. Drive -through restaurants are only allowed as a component of a Convenience Shopping Center. A
Convenience Shopping Center is specifically defined in Section 5.1.2 and must contain four or more
business establishments with separate entrances. At this time, there is no evidence that there is
compliance with this definition.
2. In the Employment zone, Convenience Shopping Centers are defined as a Secondary Use and, therefore,
must be integrated both in function and appearance into the larger employment district development plan
that emphasizes primary uses. Further, a secondary use shall occupy no more than 25% of the total gross
area of the development plan. At this time, no evidence has been presented that defines the larger
development plan and how the proposed project does not exceed 25% of this larger plan.
2. FIRE CONTAINMENT
Buildings exceeding 5000 square feet shall be sprinklered or fire contained. If containment is used, the
containment construction shall be reviewed and approved by the Poudre Fire Authority prior to
installation.
3. WATER SUPPLY
COMMERCIAL REQUIREMENTS: Hydrants to provide 1,500 gpm at 20 psi residual pressure, spaced not
further than 300 feet to the building, on 600-foot centers thereafter.
2006 International Fire Code 508.1 and Appendix B
4. PREMISE IDENTIFICATION
New and existing buildings shall be plainly identified. Address numbers shall be visible from the street
fronting the property, plainly visible, and posted with a minimum of six-inch numerals on a contrasting
background.
2006 International Fire Code 505.1
5. FDC (for sprinkler system)
Fire Department Connections shall be installed in accordance with NFPA standards. Fire department
connections shall be located on the street side of buildings, fully visible and recognizable from the street
or nearest point of fire department vehicle access. The location of the FDC shall be approved by the fire
department.
2006 International Fire Code 912.2
6. KEY BOXES REQUIRED
Poudre Fire Authority requires at least one key box ("Knox Box") to be mounted in approved location(s)
on every new building equipped with a required fire sprinkler or fire alarm system. The top shall not be
higher than 6 feet above finished floor.
2006 International Fire Code 506.1 and Poudre Fire Authority Bureau Policy 88-20
Department: Environmental Planning
Contact: Lindsay Ex, 970-224-6143, lex@fcgov.com
1. With respect to landscaping and design, the City of Fort Collins Land Use Code, in Article 3.2.1 (E)(2)(3),
requires that you use native plants and grasses in your landscaping or re landscaping and reduce
bluegrass lawns as much as possible.
Department: Engineering Development Review
Contact: Tyler Siegmund, 970-221-6501, tiegmund@fcgov.com
1. Larimer County Road Impact Fees and Street Oversizing Fees are due at the time of building permit.
Please contact Matt Baker at 224-6108 if you have any questions.
2. The City's Transportation Development Review Fee (TDRF) is due at the time of submittal. For additional
information on these fees, please see: http://www.fcgov.com/engineering/dev-review.php
3. Any damaged curb, gutter and sidewalk existing prior to construction, as well as streets, sidewalks,
curbs and gutters, destroyed, damaged or removed due to construction of this project, shall be replaced
or restored to City of Fort Collins standards at the Developer's expense prior to the acceptance of
completed improvements and/or prior to the issuance of the first Certificate of Occupancy.
facilities need to be prep.,,ed by the drainage engineer and there is a... tal site inspection required when
the project is complete. The erosion control report requirements are in the Fort Collins Stormwater
Manual, Section 1.3.3, Volume 3, Chapter 7 of the Fort Collins Amendments. If you need clarification
concerning this section, please contact the Erosion Control Inspector, Jesse Schlam at 224-6015 or
jschlam@fcgov.com.
2. Onsite detention is required for the runoff volume difference between the 100 year developed inflow rate
and the 2 year historic release rate.
3. Fifty percent of the site runoff is required to be treated using standard water quality treatment methods as
described in the Fort Collins Stormwater Manual, Volume 3 - Best Management Practices (BMPs).
(hftp://www.fcgov.com/utilities/business/builders-and-developers/development-forms-guidelines-regulati
ons/stormwater-criteria) Extended detention is the usual method selected for water quality treatment;
however the use of any of the BMPs is encouraged.
4. Low Impact Development (LID) requirements went into effect March 11, 2013. These require a higher
degree of water quality treatment for 50% of the new impervious area and 25% of new paved areas must
be pervious. Please contact Basil Hamdan at 224-6035 or bhamdan@fcgov.com for more information.
There is also more information on the EPA web site at: hftpl/water.epa.gov/polwaste/green/bbfs.cfm?
goback=.gde_4605732_membe r_219392996.
5. The drainage outfall for the site is through the existing Post Office drainage system. The design engineer
can use the Fox Pointe Plaza drainage system design as a guide line but the LID requirements and
"Landscape Design Standards and Guidelines for Stormwater and Detention Facilities" are new since the
project was approved in 2006.
6. The city wide Stormwater development fee (PIF) is $6,390.00/acre ($0.1467/sq.-ft.) for new impervious
area over 350 sq.-ft., and there is a $1,045.00/acre ($0.024/sq.-ft.) review fee. No fee is charged for
existing impervious area. These fees are to be paid at the time each building permit is issued.
Information on fees can be found on the City's web site at
hftp://www.fcgov.com/utilities/business/builders-and-developers/plant-investment-development-fees or
contact Jean Pakech at 221- 6375 for questions on fees. There is also an erosion control escrow
required before the Development Construction permit is issued. The amount of the escrow is
determined by the design engineer, and is based on the site disturbance area, cost of the measures, or
a minimum amount in accordance with the Fort Collins Stormwater Manual.
7. The design of this site must conform to the drainage basin design of the Mail Creek Master Plan Update
as well the Fort Collins Stormwater Manual.
Department: Fire Authority
Contact: Jim Lynxwiler, 970-416-2869, *Iynxwiler@poudre-fire.org
1. FIRE LANES
Fire Lanes shall be provided to within 150' of all portions of a building, as measured by an approved
route around the exterior of the building or facility.
2006 International Fire Code 503.1.1
As the office building is bordered by two busy roads, the access drive aisle on the south side of the
office building will need to also serve as a fire lane and an EAE will be required.
2. LUC 4.27(D)(4)(a) Maximum height shall be four (4) stories.
3. LUC 3.5.3 Build -to lines based on a consistent relationship of buildings to the street sidewalk shall be
established by development projects for new buildings and, to the extent reasonably feasible, by
development projects for additions or modifications of existing buildings, in order to form visually
continuous, pedestrian -oriented streetfronts with no vehicle use area between building faces and the
street.
4. LUC 3.2.1 A Landscape plan is required (see section for details).
LUC 3.2.4 A lighting plan is required this includes a photometric site plan with catalog cut sheets.
LUC 3.2.5 An enclosure adequate for both trash and recycling is required. Such enclosure shall be
designed with walk-in access without having to open the main service gate and located on a concrete at
least 20ft from a public sidewalk.
5. LUC 3.2.2(K)(5) At least one of the accessibility off street parking spaces shall be van accessible (8ft
wide stall adjoined to 8ft wide loading area). All accessibility spaces shall be designated by the
standard vertical sign.
6. LUC 3.2.2(C)(4) Bicycle parking is required based on the total square footage of the buildings and certain
percentage on the bicycle spaces will be required to be enclosed.
7. LUC 3.2.2(L) Standard Stall dimensions are 9'xl9' and two-way drive aisles are required minimum of 24ft
in width.
8. LUC 3.5.1(1) Mechanical/Utility equipment (vents, flues, meters, boxes, conduit, outside condensing units,
roof top mechanical equipment, electrical transformer etc., locations shall be identified on plans with notes on
how such equipment is screened/painted.
Department: Water -Wastewater Engineering
Contact: Roger Buffington, 970-221-6854, rbuffington@fcgov.com
1. Existing water mains and sanitary sewers in this area include 8-inch water and 8-inch sewer mains in both
Boardwalk and JFK.
2. In 2007, two domestic water services (3/4-inch and 1-inch) and a 6-inch fire line were extended into the
site. If these services are not used, then they must be abandoned at the main.
3. The water conservation standards for landscape and irrigation will apply. Information on these
requirements can be found at: hftp://www.fcgov.com/standards
4. Development fees and water rights will be due at building permit.
Department: Stormwater Engineering
Contact: Glen Schlueter, 970-224-6065, gschlueter@fcgov.com
1. A drainage report, erosion control report, and construction plans are required and they must be prepared
by a Professional Engineer registered in Colorado. The drainage report must address the four -step
process for selecting structural BMPs. Standard operating procedures (SOPs) for all onsite drainage
City of
F6rt Collins
May 28, 2013
Daniel Bernth
Doberstein Lemburg Commercial, Inc
1401 Riverside Avenue
Fort Collins, CO 80524
Community Development and
Neighborhood Services
281 North College Avenue
PO Box 580
Fort Collins, CO 80522
970.221.6750
970.224.6134 - fax
fcgov.com
60emw4. i Vox ti'o;,VG 006m -- 4 LIP - U (o
Re: JFK & Boardwalk - Comm erciaVRestaurant
Description of project: This is a request to construct an office building (approximately 6,800 square feet)
and restaurant with drive-thru (approximately 1,500 square feet) located at the southeast corner of John F
Kennedy Parkway and East Boardwalk Drive (Parcel# 97362-05-018). The office building would be similar to
the footprint as shown on the site plan (originally submitted as Fox Pointe Plaza, 2006), but 1 story instead of
2. A restaurant with drive-thru would be located to the east of the office building. The site is located in the
Employment (E) Zone District. In the Employment zone district offices are subject to Administrative (Type 1)
review. Drive-in (drive-thru) restaurants are subject to Planning & Zoning Board (Type 2) review, but only if
located in a convenience shopping center.
Please see the following summary of comments regarding the project request referrenced above. The
comments offered informally by staff during the Conceptual Review will assist you in preparing the detailed
components of the project application. Modifications and additions to these comments may be made at the
time of formal review of this project. If you have any questions regarding these comments or the next steps in
the review process, you may contact the individual commenter or direct your questions through the Project
Planner, Ted Shepard, at 970-221-6343 or tshepard@fcgov.com.
Comment Summary:
Department: Zoning
Contact: Noah Beals, 970-416-2313, nbeals@fcgov.com
1. Land Use Code (LUC) section 4.27(13)(2)(c)1. In the Employment (E) District Offices are permitted use
through a TYPE 1 Review.
LUC 4.27(C) Standard Restaurants and fast food restaurants with drive-in or drive -through services are
permitted use in the E zone only in a convenience shopping center, which is a Type 2 review.
If a portion of the development project is a higher level of review than other portions all portions are
brought to the higher level of review.