HomeMy WebLinkAbout2337 S. SHIELDS ST., HOME STATE BANK - PDP - 8-05 - CORRESPONDENCE - (5)[3/22/05] 1 am unable to locate the bicycle facilities on any of the plan sets
Number: 13 Created: 3/22/2005
[3/22/05] Need to remove the existing drive entrance from Shields Street on the Site Plan
and Landscape Plan.
Department: Technical Services Issue Contact: J.R. Wilson
Topic: Technical Services
Number: 20 Created: 3/23/2005
[3/23/05] Comments from Technical services:
1. Boundary and Legal close. Distance on plat does not match legal. 63.20 vs. 63.19
2. Please clarify the easements along the west side of the Sub - Different line types?
3. Please show how Raintree Drive was dedicated.
4. Is the 24' cross access existing or proposed? Add: "To be dedicated by" if it is
proposed.
Department: Water Wastewater Issue Contact: Roger Buffington
Topic: Utilities
Number: 8 Created: 3/20/2005
[3/20/05) Existing house is not billed for sewer and is believed to be on a septic system.
Sewer televising reports indicate no service connections in the run of sewer north of Shields
and Raintree. Installation of a new sewer service will be required.
Number: 9 Created: 3/20/2005
[3/20/05] If existing water service is to be abandoned, it must be abandoned at the main in
Shields.
Number: 26 Created: 3/23/2005
[3/23/05] Show location of septic tank on plans. Check with Larimer County Dept of Health
& Environment on proper abandonment procedures and add appropriate notes to plans.
Be sure and return all of your redlined plans when you re -submit.
If you have any questions regarding these issues or any other issues related to this project,
please feel free to call me at (970) 221-6750.
Sincerely,
Anne H. Aspen
City Planner
Page 4
[3/23/05) Please see redlines and utility plan checklist for any additional comments.
Topic: Landscaping
Number: 21 Created: 3/23/2005
[3/23/051 Please remember to show all utilities on the landscape plan and ensure that
required separations are met.
Department: Light & Power Issue Contact: Doug Martine
Topic: Utilities
Number: 2 Created: 3/7/2005
[3/7/05] The developer will need to coordinate locations for electric facilities (including a pad
type transformer), and electric development charges with Light & Power (221-6700). Light &
Power will also need the developer to provide a completed Commercial Electric Service
Information (C-1) form. The source of power to the site will be from the existing electric vault
at the N.E. comer of the lot (this corrects information given at Conceptual Review).
Department: Natural Resources
Topic: General
Number: 27
[3/23/05] No issues.
Issue Contact: Doug Moore
Created: 3/23/2005
Department: Police Issue Contact: Joseph Gerdom
Topic: General
Number: 28 Created: 3/23/2005
[3/23/05] Lighting: Area around building should be @ 1.Ofc. Also, parking and drive areas in
NE are below 1.Ofc requirement.
Department: Stormwater Utility Issue Contact: Wes Lamarque
Topic: Stormwater
Number: 10 Created: 3/22/2005
[3/22/05] The 2-year historic flow that releases from the pond into the existing storm sewer
has to be less than what drains into that storm sewer currently. If the flow is greater, an
analysis of the system will need to take place.
Number: 29 Created: 3/25/2005
[3/25/05] At final plan review, water quality outlet structure will need to be modified. See
redlined plans.
Department: Traffic Operations Issue Contact: Eric Bracke
Topic: traffic
Number: 1 Created: 3/3/2005
[3/3/05] No problems. A variance will be required regarding the sb right turn lane. I will
support the request.
Department: Transportation Planning Issue Contact: Kurt Ravenschlag
Topic: Transportation
Number: 11 Created: 3/22/2005
(3/22/05] Need to show access ramps at Raintree Drive and Shields Street intersection on
all plans.
Number: 12
Created: 3/22/2005
Page 3
Number: 7 Created: 3/18/2005
[3/18/05] Banks are required to have walk-up ATM facilities if they provide drive through
ATM facilities. I do not see any indication on your plans for where the walk-up ATM will be
located. It must be accessible 24 hours, so it can be in a building foyer or near the drive up
ATM for example. If it is located near the drive up ATM, a connecting walkway and safe
area for the pedestrian are required.
Department: Engineering Issue Contact: Katie Moore
Topic: General
Number: 15 Created: 3/23/2005
[3/23/05] As previously discussed with the engineering consultant for the project, the
variance request to not dedicate ROW for a right turn lane on Shields most likely is
unnecessary. Please show the dimension from the existing Shields Street centerline to the
proposed edge of ROW on Shields, and this can be resolved.
Number: 16 Created: 3/23/2005
[3/23/05] When the utilities were routed to determine whether a 5' utility easement on
Shields would be sufficient, two utilities had problems or concerns with that:
Comcast said that a 15' utility easement along Shields would be required.
XCEL's comment is as follows: We currently have a 4" PED stubbed into this 15' LIE for
approximately 50' from Raintree Drive. If you change this easement to 5' the customer
would be required to make sure this stub lays within this 5' LIE. Any relocation would be at
customer's expense. The new (proposed) gas meter would need to be placed at south end
of project. It would be very difficult to extend 4" PED in the proposed 5' UE. - Len
Hildebrand.
Number: 17 Created: 3/23/2005
[3/23/05] It appears that a number of offsite easements will be needed to construct this
project as shown. Because a number of those easements require City Council approval,
this project will be approved with conditions, and prior to hearing, a letter from Real Estate
Services will be needed stating that the City is amenable to granting the easements needed
for this project.
Number: 18 Created: 3/23/2005
[3/23/05] How is emergency access being addressed? I see no emergency access
easement for a fire lane.
Number: 19 Created: 3/23/2005
[3/23/05] Please include the new ADA ramp details in the plans.
Number: 23 Created: 3/23/2005
[3/23/05] Please show clearly how parking will work (dimensions, striping) in the Senior
Center with the proposed changes.
Number: 24 Created: 3/23/2005
[3/23/05] Please work on all drawings to ensure that scanability requirements are met prior
to submittal of mylars. Technical Services may reject drawings that do not meet the
standards.
LCUASS Appendix E-6.
Number: 25
Created: 3/23/2005
Page 2
i STAFF PROJECT REVIEW
Citvof Fort Collin.
BHA DESIGN INC. Date: 03/31/2005
SCOTT SINN
4803 INNOVATION DR.
FORT COLLINS, CO 80525
Staff has reviewed your submittal for 2337 S. SHIELDS ST. - HOME STATE BANK PDP,
TYPE I, and we offer the following comments:
ISSUES:
Department: Current Planning Issue Contact: Anne Aspen
Topic: General
Number: 30 Created: 3/30/2005
[3/30/05] Lighting is deficient in some areas. Please see redlines for details. Refer to LUC
3.2.4 for more detail also.
Number: 31 Created: 3/30/2005
[3/30/05] As we discussed on the phone, your site and landscape plans need to be cleaned
up. There is a fair amount of overlapping lines and generally more information than we
need on them. I've made some suggestions on the redlines and over the phone. Let me
know if you have further questions.
Number: 32 Created: 3/30/2005
[3/30/05] As discussed on the phone, we will get together on March 31 to explore the
possibility of a safe walkway between the Senior Center and the bank.
lbpok =•u"oes
Number: 3 Created: 3/18/2005
[3/18/05] 1 received a letter from the City's Recreation Administrator regarding the shared
parking. At this time it appears that the concept is well received by the Senior Center. They
will review the plans again at the final plan site and there will need to be an appropriate
signature block for the City on the final plans.
Number: 4 Created: 3/18/2005
[3/18/05] The following departments have indicated no problems or concerns with the plans:
Park Planning, Streets and Water Conservation.
Number: 5 Created: 3/18/2005
[3/18/05] Building Inspection has forwarded me a listing of the building codes which they
will enforce with this project. I will include this information with your redlines.
Number: 6 Created: 3/18/2005
[3/18/05] Xcel Energy comments:
+The owner or developer may need to have gas main relocated in proposed 5' Utility
Easement;
+Existing 4" PE Gas Main lays in existing along Shields St. Proposed gas meter for the bank
will need to be located along the south wall of the proposed building; and
+No trees may be planted within four feet of gas lines.