HomeMy WebLinkAboutRAVEN VIEW - PDP - 12-05 - CORRESPONDENCE - (5)[9/30/05] Please show more precisely the flow path for these off -site flows to verify that they will miss the site. [4/1/05] Investigation needs to take place for off -site flows to the west that may travel through the site. Basin 21 from the Canal Importation Master Plan appears to flow near or through the site. Department: Transportation Planning Issue Contact: David Averill Topic: General Number: 32 Created: 3/29/2005 [9/27/05] Repeat comment. [3/29/05] A minor point, on the "Cover Sheet", please remove the wording "Bike Path Each side of Road" as it references Taft Hill Rd. and Mulberry St. While bike lanes do exist (at a sub -standard configuration) there are no bike paths along these facilities in this location. Of course if you want you can leave the wording'on the sheet but change "path" to "lane". Department: Water Wastewater Issue Contact: Roger Buffington Topic: General Number: 101 Created: 9/29/2005 [9/29/05] Provide offsite easements for the water and sewer lines. Topic: Landscape Plan Number: 107 Created: 9/29/2005 [9/29/05] Separation distance between water/sewer MAINS and trees is 10 feet. (Land Use Code is incorrect.) Topic: Plat Number: 103 Created: 9/29/2005 [9/29/05] On the plat, clarify that tracts are utility easements. Topic: Utility plans Number: 102 Created: 9/29/2005 [9/29/05] Provide 2 foot minimum separation between water services and driveways. Number: 104 Created: 9/29/2005 [9/29/05] Pothole the water main in Mulberry during final compliance to provide a complete design for the water/sewer crossing. Number: 105 Created: 9/29/2005 [9/29/05] If street is stubbed to the south, we may want to have water/sewer mains stubbed also. We will await determination from planning and engineering on the street stub. Number: 106 Created: 9/29/2005 [9/29/05] Schedule a meeting with me to discuss connection to water main in Taft and to look at possibility of reversing the water/sewer locations in the streets. Be sure and return all of your redlined plans when you re -submit. If you have any questions regarding these issues or any other issues related to this project, please feel free to call me at (970) 221-6750. Sincerely, Anne H. Aspen, City Planner Page 10 [3/29/05] This project does not meet the city's street naming criteria. Each of the legs will need its own name and remove the "Court" from the street name. Please see JR/Tech Services if you have any questions. Topic: Traffic Study Number: 90 Created: 4/1/2005 [10/4/05] Please provide another copy of the updated TIS. [4/1/05] Needs to be updated to reflect the current layout and include the pedestrian LOS requirements. Topic: Utility Number: 37 Created: 3/29/2005 [10/4/05] [3/29/05] Need to dimension all drive aisles and parking stalls in accordance with LCUASS. Number: 112 Created: 10/4/2005 [10/4/05] Final Compliance. Please remove the street patch detail. Number: 139 Created: 10/5/2005 [10/5/05] See redlines for comments on sheet U1. Add street cut note. Department: PFA Issue Contact: Michael Chavez Topic: General Number: 96 Created: 9/23/2005 [9/23/05] In addition to previous comments submitted by Poudre Fire Authority a sign shall be placed at the point where the "Emergency Access Road" meets Mulberry Street indicating "Emergency Access Only -Raven View". Contact Michael A. Chavez with Poudre Fire Authority at 970-416-2869 for sign details. Department: Stormwater Utility Issue Contact: Wes Lamarque Topic: Stormwater Number: 72 Created: 3/30/2005 [9/30/05] Before hearing, need to make sure that the letter of intent includes a drainage easement in addition to a utility easement for the detention pond spillway. Once that is determined, project is OK for hearing. [3/301051 All off -site drainage easements or letter of intents need to be in place before a hearing. Number: 83 Created: 3/31 /2005 [9/30/05] Stormwater is confident this can be worked out after the hearing. Comments may follow at final compliance on the details of this to satisfy Stormwater and Poudre Fire Authority's requirements. [3/31/05] There is a conflict with the emergency access road and inlet along Mulberry which needs to be resolved. Number: 87 Created: 4/1 /2005 [9/30/05] Repeat [4/1/05] SWMM Comments - Please provide a connectivity schematic and show revised basin boundaries on SWMM exhibit. Number: 88 Created: 4/1 /2005 Page 9 Topic: Public Hearing Number: 31 Created: 3/29/2005 [10/4/05] [3/29/05] The applicant must provide a letter of intent for all offsite easements from all effected property owners before being allowed to schedule a public hearing. The actual easements themselves must be provided during Final Compliance and the reception number must be shown on all plan sets. Please submit an exhibit and legal description for our review and approval prior to recording so that we can verify that they are correct. Easements dedicated to the City (drainage, utility and public access) must be done using our dedication statement and then accepted through our own internal process. Easements between private parties can be recorded at the County Clerk's office once we have reviewed them for accuracy. Number: 41 Created: 3/29/2005 [10/4/05] [3/29/05] There is a proposed retaining wall outside of the 30' drainage and utility easement. This development will need a temp construction easement for any work done outside of the easement as well as a permanent easement for the wall itself. It might be easier to widen out the 30' easement to include the wall. Please provide a letter of intent from the property owner in order to go to hearing. Topic: Scanning Requirements Number: 10 Created: 3/28/2005 [9/30/05] This is more a Final Compliance issue but I'll just keep the comment open until resolved. [3/28/05] Please see Appendix E6 for our scanning requirements. Shaded areas and anal photos will not scan. Please correct all overlapped labeling. Please see Jr/Tech Services if you have any questions. Topic: Site Plan Number: 46 Created: 3/29/2005 [10/5/05] [3/29/05] The site plan needs to match the utility plan. Number: 47 Created: 3/29/2005 [10/4/05] [3/29/05) Please coordinate the comments under other sections so that all plan sets match. Number: 51 Created: 3/29/2005 [10/5/05] [3/29/05] Dimension all sidewalks. Number: 128 Created: 10/5/2005 [10/5/05] Please provide a north arrow, scale, etc. Number: 129 Created: 10/5/2005 [10/5/05] Please expand the Site Plan to include all offsites, must match the utility plans. Number: 130 Created: 10/5/2005 [10/5/05] Expand the Site Plan to include Taft and Mulberry and show all existing features within 150' of the project boundaries. Topic: Street Names Number: 24 Created: 3/29/2005 [9/30/05] Please see JR in Tech Services. Page 8 existing and proposed driveway area on sheet U1. In addition, you can not discharge more than 500sf of drainage across a public sidewalk - a sidewalk chase will be required. Number: 42 Created: 3/29/2005 [10/4/05] Repeat. [3/29/05] The east driveway off Mulberry is shown draining towards the street. No more than 500sf of drainage is allowed to discharge over a public sidewalk. Number: 43 Created: 3/29/2005 [10/4/051 Final Compliance. This driveway exceeds the maximum 500sf of drainage over a public sidewalk. You will need to provide a culvert to the street or and inlet to the stormdrain. [3/29/05] Please provide a typical section and a plan and profile for the western emergency access drive and include all information necessary build it. This drive must meet PFA's minimum requirements. Show how you are tying into Mulberry with it. The maximum 500sf of drainage over a public sidewalk applies here as well. Number: 61 Created: 3/29/2005 [10/3/05] Final Compliance. [3/29/05] Need to station every driveway along a vertical curb. Number: 64 Created: 3/29/2005 [10/4/05] Final Compliance. [3/29/05] Identify all grade breaks. Number: 65 Created: 3/29/2005 [10/3/05] [3/29/05] Final Compliance. Continue the centerline profile through the intersection at Taft and where the road loops back on itself. Number: 70 Created: 3/29/2005 [10/3/05] [3/29/05] Please provide a cut section through the PC and widest point of the bulbouts so that I can verify you are meeting our cross slope requirements (Final Compliance). Number: 125 Created: 10/5/2005 [10/5/05] Final Compliance. The cross slopes shown of 4% exceed the maximum cross slope requirement of 3%. Number: 126 Created: 10/5/2005 [10/5/05] Final Compliance. Minimum VC lengths are not being met on Pica. Please refer to figures 7-17 and 7-18. Topic: Plat Number: 30 Created: 3/29/2005 [10/4/05] [3/29/05] Final Compliance. Please provide signature/address lines and another for the City Clerk. Number: 113 Created: 10/4/2005 [10/4/05] See Technical Services comment sheet for their comments. Page 7 [10/5/05] Final compliance. Add Street Cut Note: Limits of street cut are approximate. Final limits are to be determined in the field by the City Engineering Inspector. All repairs to be in accordance with City street repair standards." Number: 140 Created: 10/5/2005 [10/5/05] Sheet U3 -see redlines. Number: 141 Created: 10/5/2005 [10/5/05] Remove the word Preliminary from the title block, all sheets. Number: 142 Created: 10/5/2005 [10/5/05] The typical street sections shown on sheet R1, R2, R3, & R4 do not meet city standard and require several corrections. Number: 143 Created: 10/5/2005 [10/5/05] Sheet D2 - See redlines for comments. Detail 10: Please label the slopes. The 18" separation requirement is not being met. Detail 11: See comments under Offsite Easements in this letter. Number: 144 Created: 10/5/2005 [10/5/05] Sheet D3 - Needs to be to scale and must in engineering scale. Not scannable - doesn't look like the minimum font size requirement is being met. Please see Appendix E6 for all scanning requirements. Number: 145 Created: 10/5/2005 [10/5/05] Sheet D5 -See redlines. Number: 146 Created: 10/5/2005 [10/5/05] Sheet D6 - Please provide more details on the modified inlet structure and drive cut. Topic: Plan and Profiles Number: 12 Created: 3/28/2005 [10/4/05] Will need this detail before hearing to make sure the horizontal layout is to standard OR you can go to hearing with the understanding that the row may still move if the bulbouts are not designed in accordance with 7-24. [3/28/05] Please provide a street widening detail for each of the three bulbouts. The street widening must be designed in accordance with detail 7-24. Call out each of the dimensions asked for in the detail (R1 can equal 20-36' per Mike Herzig). Where the street has been widened on the east leg and out at Taft, show another typical street section for those areas and label with "from station xxxx to station xxxx. Number: 38 Created: 3/29/2005 [10/4/05] Final Compliance. [3/29/05] All structures must be a minimum of 2.5' below the scarified subgrade of a public street. Number: 40 Created: 3/29/2005 [10/4/05] Final Compliance. The details shown are incomplete and are not buildable. [3/29/05] Sheet D5: Put the offsite driveway details along with the other driveway details on the Plan and Profile sheets. Put the appropriate cut sections on sheet U1 for both the Page 6 [10/4/05] [3/29/05] Please coordinate the comments under other sections so that all plan sets match. Number: 131 Created: 10/5/2005 [10/5/05] Please provide a north arrow, scale, etc. Number: 132 Created: 10/5/2005 [10/5/05] Please expand the Landscape Plan to include all offsites, must match the utility plans. Number: 133 Created: 10/5/2005 [10/5/05] Expand the Landscape Plan to include Taft and Mulberry and show all existing features within 150' of the project boundaries. Topic: Offsite Easements Number: 134 Created: 10/5/2005 [10/5/05] The plat and the offsite easement documents do not match. The emergency access drive on the plat says it is a 24' emergency access, maintenance and construction easement while the contract calls it an emergency access and utility placement only. The construction easement needs to be called out separately on all documents and say whether its temporary or permenent. Is a drainage easement necessary as well? A letter of intent from the property owner is required prior to hearing if the original document is not correct. The drive on the east side of the property is called out as a 30' drainage and utility easement on the plat. The contract document calls it an Access and Utility Easement. We will also require a drainage and maintenance easement. Also, the 30' easement is not wide enough to include and construct the retaining wall. A letter of intent revising the contract is fine before going to hearing, the actual documents will need to be filed during Final Compliance. Emergency Access and Drainage easements need to be dedicated to the city and accepted through the city process. All other private easements can be recorded between the individual parties at the County. We will need a copy of the recorded documents before final plan approval. Topic: Overall Utility Number: 59 Created: 3/29/2005 [10/4/05] [3/29/05] Need to show/dimension existing and proposed row and utility easements along Taft and Mulberry. Number: 60 Created: 3/29/2005 [10/4/05] Final Compliance. [3/29/05] Need to dimension the crosspan at Taft and provide the detail in the detail sheets. Number: 62 Created: 3/29/2005 [10/3/05] Repeat. [3/29/05] Need to show existing features within 150' of the projects boundaries in a ghosted or alternate line weight. Need to show how your proposed items tie into the existing. Number: 123 Created: 10/5/2005 Page 5 [10/5/05] Please label all Tracts and Easements, all sheets, all plan sets. Number: 118 Created: 10/5/2005 [10/5/05] Final Compliance. Midblock crosspans must be 12' wide minimum. Number: 119 Created: 10/5/2005 [10/5/05] Final Compliance. Change all dimensions to engineering scale (can't be architectural in feet and inches). Number: 120 Created: 10/5/2005 [10/5/05] Final Compliance. Please provide more information and details on the proposed inlet modification on Mulberry. Topic: Grading Number: 57 Created: 3/29/2005 [10/4/05] Hard to see if this was done on the offsite drives to Mulberry. It is not clear if you will need offsite grading easements at this time. Please remove the landscaping off of all sheets (except the demo sheet). [3/29/05] Proposed contours need to tie into existing contours. Number: 58 Created: 3/29/2005 [10/4/05] [3/29/05] Final Compliance. Show drainage arrows on the drives out to Mulberry. Number: 121 Created: 10/5/2005 [10/5/05] Final Compliance. Label slopes in all detention areas. Number: 122 Created: 10/5/2005 [10/5/05] Final Compliance. You may have to break this sheet into two sheets so that the information is clear and scannible. Topic: Intersections Number: 68 Created: 3/29/2005 [10/3/05] [3/29/05] Please provide intersection details in accordance with details 7-27 and 7-28 (Final Compliance). Number: 69 Created: 3/29/2005 [10/4/05] [3/29/05] Profile grades within the intersection can not exceed 3%. Topic: Landscape and Site Plan Number: 52 Created: 3/29/2005 [10/5/05] [3/29/05] Please label and dimension all easements, row. Number: 148 Created: 10/5/2005 [10/5/05] Remove "Project Development Plan" from the plan sets. Number: 149 Created: 10/5/2005 [10/5/05] Must be in engineering scale. Topic: Landscape Plan Number: 48 Created: 3/29/2005 Page 4 Topic: Emergency Access Number: 124 Created: 10/5/2005 [10/5105] Please see PFA as soon as possible for their comments on the emergency access drive. Number: 127 Created: 10/5/2005 [10/5/05] Final Compliance. Minimum VCs are not being met along the emergency access road. Ensure that PFAs requirement of 25' inside and 50' outside turning radius is being met. Please provide a drive cut on Mulberry so that the fire trucks don't have to jump the vertical curb. Topic: General Number: 18 Created: 3/28/2005 [9/30/05] The row dedication shown does not equal 57.5 from the centerline. The 15' UE needs to be dimensioned and labeled. [3/28/05] This project is responsible for dedicating their half of a total of 115' of row along Taft plus a 15' utility easement. Number: 33 Created: 3/29/2005 [10/4/05] Repeat -Final Compliance. [3/29/05] The cutb returns must be designed in accordance with LCUASS, Table 8-2. Those shown on the plans do not. Number: 49 Created: 3/29/2005 [10/4/05] Repeat. Also, please dimension all parking stalls in accordance with LCUASS. [3/29/051 There are no handicapped parking spaces shown. Number: 54 Created: 3/29/2005 [10/3/05] [3/29/05] More detailed and specific comments to follow in Final Compliance. Number: 114 Created: 10/5/2005 [10/5/05] Final Compliance. The street stub to the south needs to be designed and constructed to the property line and a type III barricade is required (please show on all plan sets). This development has the option of building the stub and the curb return to the PCs and ramps and then cash in lieu of the rest. If this option is chosen, the plans would need to show interim and ultimate and an estimate for the remaining portion of the street has to be submitted for our review and approval. The estimate must include the removal of any landscaping in the row of the future street. Only grass will be allowed in the row, however, no shrubs or trees of any kind. We need it to be very clear to the future and existing residents that the street is absolutely going through. Number: 115 Created: 10/5/2005 [10/5/05] Final Compliance. Directional ramps are required at all intersections. Those shown at Taft Hill do not meet standard. Number: 116 Created: 10/5/2005 [10/5/05] Final compliance. Please provide PFA approved bollards where the street stubs to the north and add the appropriate detail in the detail sheets. Number: 117 Created: 10/5/2005 Page 3 Susan Joy that she finds the project ready to go to hearing, I will verify with the rest of staff and then schedule the hearing. Number: 152 Created: 10/5/2005 [10/5/05] The USPS comments as follows: "Mail Service: Centralized delivery using of a minimum of 4 centralized box units (3 industry type III and 1 type 1) is required. Revise plan to show the required CBU locations as approved by the US Postal Service. In all cases the CBU's must be located in the public right-of-way or a designated easement. ,Be advised the responsibility of purchase and maintaining the CBU's with the concrete pads is that of the owner/developer/builder/HOA. Prior to occupancy within the development approved mail receptacles will be in place. Delivery Agreement will be in place prior to any delivery of mail. Contact Carl Jenkins Growth Coordinator, US Postal Service 301 E. Boardwalk, Fort Collins, CO, phone # 970- 225-4130, cell # 970-214-3668, fax # 970-225-4139. Topic: Ped LOS Number: 108 Created: 10/4/2005 [10/4/05] The proposed project is not meeting the pedestrian level of service standards. While City staff is well aware that at this infill site it is perhaps not possible to meet these standards, they are standards nonetheless. In order to go to hearing, the applicant will need to submit a written request for modification of standards. City staff is in agreement that this modification of standards request will receive staff support. Since the request is more of a formality than anything else, it can be submitted concurrently with the PDP and be addressed at the same hearing as the PDP. Please let me know if you have any questions about the process or requirements for a modification submittal. Topic: Public Hearing Number: 151 Created: 10/5/2005 [10/5/05] Please remember to relabel the Lot that is Tract F for your plans to be submitted to the Hearing Officer. Department: Engineering Issue Contact: Susan Joy Topic: Demo Sheet Number: 135 Created: 10/5/2005 [10/5/05] Final Compliance. Label the existing Gravel Drive on the north side of Raven View that it is to be removed. Number: 136 Created: 10/5/2005 [10/5/05] Final Compliance. Scanning issues here. Don't shade the existing offsite structures, just outline. Add the street row for Crestmore Place and Court. Number: 137 Created: 10/5/2005 [10/5/05] Final Compliance. Label which trees are to be removed. Number: 138 Created: 10/5/2005 [10/5/05] Add Street Cut Note (provided elsewhere in the comment letter). Topic: Driveways Number: 67 Created: 3/29/2005 [10/4/05] [3/29/05] Sidewalks must be continuous through the driveways. Final Compliance. Page 2 STAFF PROJECT REVIEW City of Fort Collins TOM PETERSON Date: 10/05/2005 3555 STANFORD RD. #204 FORT COLLINS, CO 80525 Staff has reviewed your submittal for RAVEN VIEW PDP, TYPE I, and we offer the following comments: ISSUES: Department: Current Planning Issue Contact: Anne Aspen Topic: General Number: 97 Created: 9/27/2005 [9/27/05] Change Director of Planning to Director of Current Planning on the signature block (2 times). Number: 99 Created: 9/27/2005 [9/27/05] Need to add a street tree at the NEC of Pica and Corvid Way Number: 100 Created: 9/27/2005 [9/27/05] The lighting fixture you have chosen does not meet the standards of the Land Use Code. It is not down directional nor is it fully shielded. Number: 109 Created: 10/4/2005 [10/4/05] You will need to meet with Ron Gonzales at Poudre Fire Authority right away to make sure that they have no concerns with this proposal. Number: 110 Created: 10/4/2005 [10/4/05] In the staff review meeting, you indicated that you do not intend to construct the stub road to the south. Your site plans seem to show, with equal line weights, that you plan to build and not build the stub. You said that City staff had Owed not building the stub at this time. I told you that wasn't what I recalled but that I would look back through the record and get back to you. I looked through the entire record on this project and found nothing to indicate that staff OK'ed your not building the street stub. What I did find were three references to the contrary. First, in your conceptual review letter dated May 10, 2004, it is clear that street stubs must be designed and constructed. Second, at a transportation coordination meeting on March 31, 2005, Susan Joy and I explained to you, Russ Wells, Matt Delich and Wayne Hochstetler that you would be required to construct the street stubs to standard, which in this case would be 51-53'. Susan mentioned the possibility of a contribution in aid as a possibility and suggested that you be in touch with her about that. There was no further communication about that. Finally, in an email dated April 1, 2005, Susan Joy wrote to Nick Hawes and stated that the street stub would need to be designed and constructed. So as it stands now, you will be responsible for the design and construction of the street stubs. Staff has determined that it would be possible to modify the requirements given the nature of the circumstance. See Susan's comment # 114. Number: 111 Created: 10/4/2005 [10/4/05] Since the remaining issues are primarily Engineering's comments, you will not be required to submit for another formal round of review. Please submit a complete set to Susan Joy and address any other issues to the commenter directly. Once I have heard from Page I