HomeMy WebLinkAbout605 WEST LAKE STREET BOARDING HOUSE - PDP - 48-05 - CORRESPONDENCE - (12)If you have any questions regarding these issues or any other issues related to this project,
please feel free to call me at 221-6341.
Yours Truly,
*SW -
Steve Olt
City Planner
Ll 1A D2 �s
Page 2
STAFF PROJECT REVIEW
City of Fort Collins
James Swanstrom
P.O. Box 271516
Fort Collins, CO. 80527
-Date: 10/ 17/2006
Staff has reviewed your submittal for 605 WEST LAKE STREET BOARDING HOUSE PDP,
and we offer the following comments:
ISSUES:
Department: Current Planning Issue Contact: Steve Olt
Topic: General
Number: 28 Created: 10/17/2006
(10/17/06] This item is ready to be scheduled for an administrative public hearing. There are
several changes to the Site Plan that must be made before approval and recording of the
plan.
Department: Engineering Issue Contact: Susan Joy
Topic: General
Number: 27 Created: 10/10/2006
[10/10/06] Please dimension ALL existing sidewalks on the property.
Department: Engineering Issue Contact: Dan DeLaughter
Topic: General
Number: 1 Created: 11 /23/2005
[10/10/06] Please remove the OLD incorrect labeling (it conflicts with the NEW correct
labeling).
[6/8/06] The sidewalk is only 32" here. With curb and gutter, it may be 4.5', but please label
as 32" sidewalk, not 4.5 'concrete.
[11/23/05] Sidewalk along frontage must be dimensioned.
Number: 9 Created: 12/1/2005
[10/10/06] Per Sheri Langenberger, the notation stating that the shed will be moved at such
time the utility companies need access is acceptable to engineering. However, are there
any minimum setback requirements from either Building and Zoning or Planning?
[6/9/06] The shed is within the easement.
[12/1/05] Show the existing 5' easement (per Blevins Subdivision plat) on south of the site.
It appears your shed is located within this easement. The shed would have to be moved or
utilities must give approval for it to remain.
Number: 24 Created: 6/23/2006
[10/10/06] The Final Compliance Fee has been reduced to $200 per the City Engineer.
[6/23/06] At the time of Final Compliance, a $1000 Transportation Development Review fee
will be owed to engineering.
Be sure and return all red -lined plans when you re -submit.