HomeMy WebLinkAboutSEVEN GENERATIONS (FORMERLY EASTBROOK) OFFICE PARK - PDP - 4-06 - CORRESPONDENCE - (3)M
Be sure and return all red -lined plans when you submit the required Final
Compliance documentation. Please see the attached Final Compliance
Routing Sheet for the number of required documents to submit.
If you have any questions regarding these issues or any other issues related
to this project, please feel free to call me at 221-6341.
Yours Truly,
Steve Olt
City Planner
cc: Susan Joy
North Star Design, Inc.
Current Planning file #4-06
Page 6
r
Department: Stormwater-Water-Wastewater Issue
Contact: Basil Hamdan
Topic: Stormwater -Grading
Number: 25 Created: 3 / 7 / 2006
[4/25/06] The pan located on the property to the north needs to be
approved by that property owner.
[3/7/06]
Any grading on the property to the north should be done in a manner that
would minimize disturbance. Add a note stating that all disturbed areas are
to be reseeded.
Call out existing elevations on the grading plan. Make sure all grades are
tied in (proposed and existing). Please add a note stating that no grading
shall be done off -site except as indicated on these plans. Can the dry stack
wall on the south property line be built without getting on Lot 1 ?
Topic: Stormwater- easement
Number: 20 Created: 3 / 6 / 2006
[4/25/061
[3/6/06] The proposed water quality pond should be located within a
drainage easement. Also need drainage easement for access to the rear of
the property.
This item can be handled at final.
Need to provide access easement for maintenance of drainage facilities to
the west.
Topic: Water/Wastewater
Number: 61 Created: 4 / 28 / 2006
[4/28/06] In order to avoid a street cut the existing water service line to be
abandoned off of Eastbrook Drive could be used as a fire line.
Department: Zoning Issue Contact: Peter Barnes
Topic: Zoning
Number: 3 Created: 2 / 17/ 2006
[5/ 15/06] Just to reiterate. The Final Landscape Plan must be very specific
about plant materials.
[4/ 18/06] I guess I'll look for it on a later submittal as per their response
letter.
[2/ 17/06] The "proposed shrub planting" shown on the landscape plan
should be illustrated as to species and quantity. The Plant List includes a
large selection of recommended evergreen and deciduous shrubs. Without
some clarification on the plan, they could put in nothing but evergreen
shrubs.
Page 5
Number: 58 Created: 4/ 18/2006
[4/ 18/06] Final Compliance - Please provide spot elevations for the lot
corners.
Topic: Site Plan
Number: 55 Created: 4/ 18/2006
[4/ 18/06] Final Compliance - Please dimension and label all easements to
match the utility plans.
Topic: Utility Plans
Number: 54 Created: 4/ 18/2006
[4/ 18/06] Final Compliance - Station the driveway curb cuts.
Department: Light & Power Issue Contact: Janet McTague
Topic: Site Plan
Number: 18 Created: 3 / 6/ 2006
[4/ 18/06] Second round comments same as 1st round
[3/6/06] Need to coordinate transformer location. Will need C-1 form and
approved site plan
Department: PFA Issue Contact: Carie Dann
Topic: fire
Number: 40 Created: 3 / 8 / 2006
[4/27/06] The fire lane over the drive aisle on the north side of the lot
needs to run all the way west to Eastbrook Drive. The site plan doesn't show
the F.L. next to Building A. Also, the fire lane must be platted as an
Emergency Access Easement.
[3/8/06] ACCESS: An Emergency Access Easement is required. It shall be
a minimum width of 20 feet and maintained unobstructed, and visible by
painting and signage. It must consist of an all-weather driving surface
(asphalt or concrete); compacted road base is acceptable only temporarily,
during construction.
Number: 42 Created: 3/8/2006
[4/27/061
[3/8/06] KNOX BOX: Poudre Fire Authority requires a "Knox Box" to be
mounted on the front of every new building equipped with a required fire
sprinkler system.
Department: Transportation Planning Issue Contact: David Averill
Topic: General
Number: 60 Created: 4 / 25/ 2006
[4/25/061 No further comments. Ready for hearing.
Page 4
Department: Engineering Issue Contact: Susan Joy
Topic: Detail Sheet
Number: 57 Created: 4/ 18/2006
[4/ 18/06] Final Compliance - Please add details 701, 702, 1602, 2501, and
the new ramp detail (I can send that to you email if you don't have it
because I don't think it's online yet).
Topic: General
Number: 33 Created: 3 / 7 / 2006
[4/ 18/06] Final Compliance comment -just carrying this through until
then.
[3/7/06] Please provide legals and exhibits for all easements being
dedicated by separate document for our review.
Number: 34 Created: 3 / 7 / 2006
[4/ 18/06] Final Compliance comment -just carrying this through until
then.
[3/7/06] All easements to be dedicated by separate document have a $250
processing fee each plus the appropriate Larimer County filing fee.
Number: 35 Created: 3 / 7 / 2006
[4/ 18/06] I'm checking with Stormwater to see if we can get by with just a
letter of permission from Lot 4 versus an actual easement since Lot 4 is
owned by this development as well.
[3/7/06] Please show, label and dimension all easements on all plan sets.
All plan sets need to match. The landscape plans are showing offsite
grading along the. north side of the property line that the utility plans do
not.
Number: 53 Created: 4/ 18/2006
[4/ 18/06] The utility easement vacation request was routed and approved
provided that this project does not require any portion of the easement to
remain. It appears from the plans that this is not going to be a problem. In
addition, a $400 fee for vacating the easement is required. Please forward a
check made out to "City of Fort Collins" prior to going to hearing if possible
or we can put the payment off until Final Compliance if you need to. The
legals and exhibit as well as the actual vacation can take place during Final
Compliance.
Number: 59 Created: 4/ 18/2006
[4/ 18/06] Engineering is ready for this project to go to Hearing.
Topic: Grading Sheet
Number: 56 Created: 4/ 18/2006
[4/ 18/06] Final Compliance - Label all slope ratios.
Page 3
Number: 63 Created: 5/ 15/2006
[5/ 15/06] Tim Buchanan, City Forester, indicated that the current
Landscape Plan shows the use of Swamp White Oak (Quercus bicolor), but
not as a street tree. This species is very sensitive to high pH soils that
frequently occur in Fort Collins. It is very unlikely that this species will
survive or thrive in this project. An alternative species such as Bur Oak
should be considered.
Number: 64 Created: 5/ 15/2006
[5/ 15/06] Regarding the proposed trees on the Landscape Plan, Section
3.2.1(D) (3) - Minimum Species Diversity of the Land Use Code, sets for the
maximum percentage of any one species of tree that can occur in a
development plan. In this case, there are 62 trees proposed and there can
be no more than 15% of any one species, equaling 9 trees. Therefore, the
proposed amount of Colorado Blue Spruce (10) and Black Hills Spruce (11)
exceed the allowable by a couple of trees each. Please revise the Final
Compliance Landscape Plan to address this issue.
Topic: Site Plan
Number: 13 Created: 3 / 1 / 2006
[5/ 15/06] Just to reiterate. Assuming the dashed lines around the
buildings are the intended "Building Envelopes". They must be labeled as
such on the Site Plan. The label "Proposed Easement" (in Building A) would
not be correct.
[3/ l/06] On the Site Plan, are the buildings as shown the building
footprints or the building envelopes? Building envelopes should be shown,
with scaled dimensions for the sides and distances from property lines.
Topic: Utility Plans
Number: 45 Created: 3 / 9 / 2006
[5/ 15/06] Just to reiterate. Also, no trees can be planted within 4' of gas
mains or gas services to each building.
[3/9/06] Len Hilderbrand of Xcel Energy indicated that the proposed 10'
wide utility easement must extend across the entire length of the east
frontage of the office park.
Number: 46 Created: 3/9/2006
[5/ 15/06] Will Comcast Cable's concern be addressed with Final
Compliance and easement dedications through separate documents? If the
entire site outside of the building envelopes is going to be a utility easement
then they have no problem as long as this is stated on the plat.
[3/9/06] Dennis Greenwalt of Comcast Cable TV indicated that they did
not receive a plat map for this project. They would like to see utility
easements that would allow them to build from the street up to the
buildings.
Page 2
STAFF PROJECT REVIEW
City of Fort Collins
VF Ripley Associates, Inc. Date: 05/ 15/2006
c/o Joanna Frye
401 West Mountain Avenue, #201
Fort Collins, CO. 80521
Staff has reviewed your submittal for EASTBROOK OFFICE PARK, PDP -
TYPE I, and we offer the following comments:'
ISSUES:
Department: Current Planning Issue Contact: Steve Olt
Topic: fire
Number: 62 Created: 5/ 15/2006
[5/ 15/06] Please see the attached copy of Poudre Fire Authority's "fire
lane" requirements. The current Site Plan (dated 4/ 12/06) does not show
the fire lane, which must be dedicated through separate document.
Topic: Landscape Plan
Number: 17 Created: 3/ 1 /2006
[5/ 15/06] Just to reiterate. Also, please consider adding'some evergreen
trees (native species) along the west - northwest side of the site for
additional screening between residential neighbors to the northwest and
this development.
[3/ l/06] Will the proposed native shrub plantings along the parking lots on
the north and south sides of the development provide sufficient year -around
screening from adjacent properties to satisfy the requirements set forth in
Section 3.2. 1 (E) (4) (b) of the Land Use Code?
*In the case of the north parking lot, screening from all residential uses
shall consist of a fence or wall 6' in height in combination with plant
material of sufficient opacity to block at least 75% of light from vehicle
headlights.
*In the case of the south parking lot, screening from all non-residential uses
shall consist of a wall, fence, planter, earthen berm, plant material or a
combination of such elements, each of which shall have a minimum height
of 30". Such screening shall extend a minimum of 70% of the length of any
boundary of the parking lot that abuts any non-residential use.
Page 1