HomeMy WebLinkAboutAGNEW CAR WASH - FDP - 32-06/A - CORRESPONDENCE - (5)[3/20/07] Please see other minor comments on the redlined plan set.
The redline comments have been addressed.
Comments from Current Planning:
1. Please make the minor revisions on the redlined plans. Revisions were made
to the lighting photometric plan, to indicate which lights would be left on, and which
would be turned off after hours. The outdoor light schedule was added to the
lighting photometric plan page.
Revisions may be made on the mylars and submitted to the City with proper
signatures. Mylars of the Final Development Plan was submitted to the City on April
11, 2007 along with 3 mylar plats. The construction set will be submitted at a later
date while issues with the Boxelder Sanitation District is resolved.
If you have any questions regarding these issues or any other issues related to this
project, please feel free to call me at (970) 221-6750.
Sincerely:
Ted Shepard
Chief Planner
Page 4
the floodway line shown on the plans. Product 6 corridor line has been removed
from the plans. The 0.5' FEMA floodway line has been added to and labeled on the
plans.
Topic: Stormwater
Number: 86 Created: 3/20/2007
[3/20/07] Please add text section discussing erosion control measures.
Text discussing the erosion control measures has been added to the drainage
report.
Number: 87 Created: 3/20/2007
[3/20/07] Please add erosion control effectiveness calculations and erosion control
escrow calculation.
Erosion control effectiveness calculations and escrow calculations have been added
to the drainage report.
Number: 88 Created: 3/20/2007
[3/20/07] Please add the City's standard erosion control notes to the utility plan set.
The City's standard erosion control notes have been added to the plan set.
Number: 89 Created: 3/20/2007
[3/20/07] Please add the construction schedule to the Erosion Control Plan.
The construction schedule has been added to the Erosion Control Plan.
Number: 90 Created: 3/20/2007
[3/20/07] Please add a basin and pond summary table to the drainage plan. See
redlines.
Basin and pond summary tables have been added to the Drainage Plan.
Number: 91 Created: 3/20/2007
[3/20/07] Please include the City's standard water quality outlet structure detail in the
utility plan set. Please email me at wlamarque@fcgov.com and I will replay with the
detail attached.
The City's standard water quality outlet structure detail has been added to Sheet C7.
Number: 92 Created: 3/20/2007
[3/20/07] The water quality pond needs a 2% slope at the bottom of the pond. If this
can not be obtained and still meet the required volume, a minimum of .5% slope can
be used with a drainage pan.
A concrete trickle channel has been added to the water quality pond.
Number: 93
Created: 3/20/2007
Page 3
expect an application from you soon. A CDoT access permit application was
forwarded to Gloria Hice-Idler on April 10, 2007.
Department: Light & Power Issue Contact: Doug Martine
Topic: Electric Utility
Number: 80 Created: 3/1 /2007
[3/1/07] The developer will need to coordinate a location for a pad type electric
transformer, and electric requirements and charges with Light & Power Engineering
(221-6700). So noted. A transformer location has been added to the plans.
Topic: Landscape Plan
Number: 78 Created: 3/1 /2007
[3/1/07] There are 2 existing streetlights along Lemay. The developer will need to
field verify the exact location of these lights, and show them on the landscape plan.
The location of street trees planned on Lemay will need to be adjusted to provide a
minimum of 40 feet clearance between the trees and the lights (15 feet if the tree is
an ornamental). Streetlights have been located and are shown on the Landscape
Plan. The landscape plan has been adjusted as requested.
Topic: Utility Plan
Number: 79 Created: 3/1 /2007
[3/1/07] No utility plan was included in the review packet. There is an existing
fiberglass electric vault at the N.W. corner of the lot. If this vault needs to be
relocated either vertically or horizontally, it will be at the developer's expense in
addition to normal electric development charges. So noted. The Overall Utility plan
is included with this plan set, in mylar form. The plan set includes an Overall Utility
Plan which shows the location of the electric vault noted.
Department: Stormwater-Water-Wastewaterlssue Contact: Wes Lamarque
Topic: Floodplain
Number: 96 Created: 3/22/2007
[3/22/07] The floodplain needs to be shown on the site plan — please see the
floodplain development review checklist - REPEAT COMMENT
We did not receive updated MSDS for the chemicals being used. Please resubmit to
address our previous comment: There is one chemical, The Option, that would
make this facility a critical facility because in concentrate form it is considered a
corrosive. Please try to find a different chemical and resubmit that MSDS for review.
— REPEAT COMMENT. An updated MSDS was sent via e-mail and accepted by
Marsha after the last staff review meeting.
Some of the floodplain regulations for the Poudre River changed in February: The
Product 6 corridor line is no longer regulated. Please remove this line from the plat
and plans. The floodway changed from a 0.1 ft. rise to a 0.5 ft rise. Please revise
Page 2
'a STAFF PROJECT REVIEW
Citv of Fort Collins
JOHN AGNEW & ANDREA AGNEW Date: 03/23/2007
P.O. BOX 827
FRISCO, CO 80443
Staff has reviewed your submittal for AGNEW CAR WASH PDP - TYPE I AND
FINAL PLANS (formerly Mulberry Crossing), and we offer the following comments:
Review Comments are indicated in BLUE ITALIC TEXT
ISSUES:
Department: Engineering Issue Contact: Randy Maizland
Topic: Engineering
Number: 81 Created: 3/19/2007
[3/19/07] Please revise line type and text weights for better copy and scanability.
See redlines for clarification. Complete. (Jones Engineering printed the mylars at
their office to assure appropriate line weights.)
Number: 82 Created: 3/19/2007
[3/19/07] Single point grade breaks cannot exceed 0.4 percent. Please provide
additional grade breaks or a vertical curve on the frontage road profile where
proposed meets existing to the east. See sheet C5 redlines for clarification.
Complete, an additional grade break has been provided so no grade break is greater
than 0.4 percent.
Number: 83 Created: 3/19/2007
[3/19/07] Please make minor revisions and plot mylars. Submit mylars with
Sanitation District signatures. Please include redlines with the mylars when
submitted. Mylars will be submitted with redlines and signatures from Boxelder
Sanitation District, when complete. A meeting is scheduled to discuss issues related
to this connection.
Number: 94 Created: 3/21 /2007
[3/21/07] Please add Dana Leavitt to the signature block with title. I think it is
Natural Resources or Current Planning. Please verify with Dana as he will be
signing these utility plans. The Current Planning was placed on the Signature block
as requested.
Number: 95 Created: 3/21/2007
[3/21/07] Reminder comment: As stated in the conceptual & preliminary design
review meetings, Mulberry and the frontage road are under CDOT jurisdiction. The
City cannot issue a permit for construction until you have an access permit from
CDOT. As stated in the staff review meeting, I will be meeting with Gloria from
CDOT on March 30 and I will let her know where we are in the process and to
Page I