> >>> "Joanna Frye" 9/19/2007 2:20:04 PM >>>
> Anne,
> Yesterday the clients of 3425 S. Shields, Linda Ripley and myself
> visited the site to take a look at the sidewalk condition along Shields St.
> With some measuring, we confirmed that the sidewalk is 7.5' wide instead of
> 6' like called ! out o n the plans. It was apparent to us that with the trees
> being as close as they are to the sidewalk, it would be very difficult to
> widen it, not to mention, probably a waste of resources if you are thinking
> about it in an environmental sense. Also, as you can see in the picture, a
> bike lane is provided next to the walk which provide more feet of protection
> from the traffic on the street.
> We concluded that it would make the most sense to keep the sidewalk
> in the condition it is in. Please review the photograph and let me know if
> you'd still like to get out there to assess the situation with others,
> although I think it may be unnecessary. If you have any questions or would
> like to discuss this in further detail, please let me know.
> Thank you,
> Joanna Frye
> VF Ripley Associates
> 401 W. Mountain, Suite 201
> Ft. Collins, CO 805! 21 > (970) 224-5828
> (970) 224-1662 fax
> joanna@vfavfr.com
file://C:\Documents and Settings\AAspen\Local Settings\Temp\GW}00001.HTM 10/1/2007
Page 1 of 2
Anne Aspen - Re: 3425 Shields Street -sidewalk
From: <c.matkins@comcast.net>
To: "Anne Aspen" <AAspen@fcgov.com>
Date: 9/25/2007 3:15 PM
Subject: Re: 3425 Shields Street -sidewalk
Hello Anne,
The City has commented on the need for additional South Shields Street Right of Way and adjacent
utility easement to be dedicated as part of this project. BCS is proceeding with this requirement and will
be providing these dedications on the Plat filed with this project as part of final review. Since this is
only one of several comments that our surveyor needs to address on the Plat, I would prefer to handle
these corrections in or next full submittal during the final review stage (this minimizes his desgin
iterations and potential for confusion). I would propose instead that BCS acknowledge this final Plat
requirement in our response letter to City comments prior to going to hearing. Is this an acceptable
aproach? feel free to call me if you'd rather talk than type .... 231.9632.
Thanks,
Chris
-------------- Original message --------------
From: c.matkins@comcast.net
Thank you for coordinating the internal discussion/decision on this issue so quickly, Anne.
From an Engineering perspective, we have only to route a traffic impact study memo to Ward to
address one of Mark's comments. I will email that today, and copy you and Joanna. Assuming
Ward's concerns are satisfied, I believe we are ready for hearing and would request the earliest
schedule available.
I'll invite Joanna to coordinate with you for any other information needed,
Chris
-------------- Original message --------------
From: "Anne Aspen" <AAspen@fcgov.com>
> Hi Joanna and Chris,
> We reivewed your email internally and agree that the sidewalk is OK as is. Will
> one of you call me? I think we're close if not ready to schedule this one for
> hearing.
> Anne
> Anne Aspen
> City Planner
> Current Planning Department
> City of Fort Collins, CO
> aaspen@fcgov.com
> (970)221-6206
>
file://CADocuments and Settings\AAspen\Local Settings\Temp\GW)00001.HTM 10/1/2007
Anne Aspen - Fwd: Re: 3425 Shields Street -sidewalk Page 1
From: Cameron Gloss
To: Anne Aspen
Date: 9/28/2007 4:41:10 PM
Subject: Fwd: Re: 3425 Shields Street -sidewalk
Yep that's fine. Let's add the ROW/Easement dedication as a condition of approval
Cameron
>>> Anne Aspen 09/28/2007 2:50 PM >>>
Hi Cameron,
Please see attached. I'm thinking it would be fine as long as we make it a condition of approval so we
CYA. Does that work for you?
Anne