HomeMy WebLinkAboutONE LIBRARY PARK (220 E. OLIVE ST.) - FDP - 34-07/A - CORRESPONDENCE -Department. Stormwater- Water- Wastewaterlssue Contact. Roger Buffington
Topic: Water/Wastewater
Number: 46 Created. 612412008
[6124108] The water mains adjacent to this project do NOT have cathodic
protection; therefore, Stda Details 18 and 26 are not needed.
Noted and revised
Number. 47 Created. 612412008
[6124108] Add Std Detail 11 - Typical Water Service.
Noted and revised
Number. 48 Created. 612412008
[6124108] Will fire line be DIP? PVC? If PVC, add Std Details for tracer wire and
locator station.
Noted revised to DIP
Number. 49 Created: 612412008
[6124108] See redlined plans for other comments.
Noted
Department. Zoning Issue Contact. Gary Lopez
Topic: zoning
Number. 44 Created. 611912008
[6119108] No comments.
Noted.
Please let us know if you have any other issues.
Sincerely:
Sandy McFeron
Project Manager
V.F. Ripley Associates, Inc.
Gary Odehnal
Project Manager
Northern Engineering
Shepard. Per an email from Doug Martine dated August 9, 2008 the location and
clearances are acceptable.
Number. 43 Created. 61312008
[613108] Light & Power Engineering will need an electrical 1-line diagram showing
both the main building service and the fire sprinkler pump service. Also, will
need a Commercial Service (C-1) form completed for each.
Noted.
Department., PFA Issue Contact., Carie Dann
Topic: Fire
Number. 45 Created. 612012008
[6120108] PFA has no further comments or concerns at this time.
Noted.
Department. Stormwater- Water- Wastewaterlssue Contact. Wes Lamarque
Topic: Stormwater
Number., 40 Created. 212912008
[6124108] There is no discussion in the drainage report whether or not the
proposed design is adequate in regard to the 100-year flows in the alley and
along Olive Street. Only cross -sections with their proposed water surface
elevations were included in the drainage report The text in the Drainage Report
needs to discuss this issue. The flows are very close to entering the
underground parking garage in the 100-year storm as well as overtopping the
stair landing and inundating the stair case along Olive Street. The text in the
report needs to evaluate the proposed conditions and make a conclusion whether
or not the design is providing a safe situation from flood waters.
Drainage report for site was revised, and additional sections were added to alley way
and Olive Street. Revisions and calculations are in Drainage report.
[2129108] Once the water surface elevation in the alley is determined due to the
flows running down Olive Street, a discussion needs to take place to determine if
the freeboard is adequate. In our criteria manual for conveyance elements, there
needs to be a foot of freeboard to any opening into a building or the conveyance
element needs to handle 1.33 times the flow and not enter any opening into the
building. With grades as proposed, the foot of free -board could not be met
unless a floodgate was installed at the underground parking entrance. Cortina is
an example of a project that installed a floodgate. An analysis of the flows in
Olive Street with the additional 33% may prove to not enter the underground
parking entrance, although a 1-foot tall floodgate would still be recommended.
Number. 50 Created., 612412008
[61241081 Please provide erosion control escrow calculations.
Erosion control escrow calculations included with re -submittal.
Legals and exhibits were forwarded to Marc on July, let us know if you did not receive
them.
[21261081 The revised design was viewed as being acceptable for City
Transportation Staff to grant an encroachment permit. A legal description and
exhibit should be prepared for the encroachments on Olive as well as Matthews.
A draft of the encroachment permit will then be prepared.
Olive Street encroachment exhibits were forwarded in July.
[11116107] There's been some general discussion and concern regarding the use
of the public space (right-of-way) for aspects the building. Fundamentally, the
steps and railings along Matthews along with the planter and low seat wall along
Olive are all obstructions of the right-of-way that would need to be approved via
an encroachment permit. We're potentially open to the encroachment shown on
the Matthews Street side, however we're concerned over the extent of the
encroachment onto the public space on the Olive Street side. We're not inclined
to introduce a meander in the sidewalk system along Olive Street and would
rather just see the sidewalk maintain the consistent 10 foot separation from the
curb and gutter. Why is the public space being encroached into? Interestingly,
we note page 7 of the traffic impact study which shows perhaps an earlier
iteration of the project and has the sidewalk along Olive Street maintain a
consistent separation from the street. We would prefer this design over the
present iteration and don't see a compelling reason to support the present
design.
Number.6 Created.1112112007
[6124108] The response letter indicates that the doors are not within right-of-way,
though sheet H1 seems to show the doors in right-of-way. Please add after the
label "proposed trash enclosure'; "enclosure doors located outside of right-of-
way".
Noted on Site Plan.
[2126108] Are the trash enclosure doors located within the right-of-way? If so,
why can't these be outside of the right-of-way?
[11121107] The proposed trash enclosure off of the alley cannot have doors which
swing out into the alley right-of-way. Either sliding doors or further insetting the
trash enclosure would need to be accomplished.
Department. Light & Power Issue Contact., Doug Martine
Topic: Light & Power
Number., 42 Created. 61312008
[6131081 The tentative location for the electric transformer shown at the S.E.
corner of the site may or may not work. With the electric loads of the building,
plus the load of the now planned fire sprinkler pump, a larger transformer MAY be
needed than the proposed site can accommodate.
The transformer has been revised. There will be two transformers. Dave Phillips has
been coordinating the location and clearance requirements with Doug Martine and Ted
B. The transformer pad is too small. Also, Light & Power needs 3 feet of
perimeter clearance around the transformer.
Noted
Department. Engineering Issue Contact. Marc Virata
A. The stairs to the parking garage along the alley need a wall or other substantial
barrier for the stairwell.
Curb head and landing pad elevated per detail
B.Remove the sliding gate as it encroaches into the right-of-way.
Gate has been removed from right of way.
Another "formal" round of review is not needed. Please submit 4 paper copies of
the plans for review by City staff.
Department. Engineering
Topic: Construction Plans
Number: 51 Created. 612412008
[6124108] On Sheet H1 please
details for the alley. This will
report.
Noted
Issue Contact: Marc Virata
remove references to the pavement subgrade
be specified at the time of a pavement design
Number: 52 Created. 612412008
[6124108] The stairwell leading to the parking garage off the alley should
incorporate a wall to provide separation and protection for vehicles/bikes/peds
traversing the alley as well as prevent water/snow entering the stairwell area due
to snow clearing/street cleaning operations. The wall should be located outside
of public right-of-way.
Wall / curb line added, see construction plans.
Number: 55 Created: 612712008
[6127108] I was recalling that it was suggested that the sidewalk along Olive Street
just west of the alley on the north side could appear to swing slightly towards the
south as it approached the alley to provide a visual cue to the encroachments
along the property. I was recalling that this may have been illustrated on a
redline set, which I'm not sure was returned with the submittal. Can a "redirect"
in the sidewalk be outlined?
Sidewalk at alleyway has been revised.
Topic: General
Number.2 Created.1111612007
[6124108] The response letter indicated legal descriptions and exhibits have been
added. In checking with Cameron, this did not appear to be submitted with the
submittal.
VIF-RipIGyASSOCIATES INC
Landscape ArchiteCtUro Urban Design Planning
September 08, 2008
Mr. Ted Shepard
Fort Collins Planning Department
281 North College Avenue
Fort Collins, CO 80524
ONE LIBRARY PARK - TYPE II
Response to staff Project Review comments
Dear Mr. Shepard,
We have reviewed the staff letter dated June 27, 2008 and have the following comment
responses:
ITEM: New Four -Story Potential Mixed-Use/Residential Building, 220 East Olive
Street
COMMENTS:
ISSUES:
Department: Current Planning Issue Contact: Steve Olt
Topic: General
Number: 54 Created: 612712008
[6127108] The following comments were expressed at Staff Review on June 23,
2008:
Stormwater/Glen Schlueter
A. One (1) foot of freeboard is needed for the parking access.
Three types of protection are proposed to protect parking garage access. 1) 33%
increase in 100yr storm capacity at alleyway, 2) trench drain at entrance and 3) sump
pump in garage. These items are detailed in revised drainage report dated July 14,
2008.
B. The drainage report needs to be modified and Stormwater needs 1 copy of
the revised report
Report modified.
Department: Light & Power
A. The transformer needs to be sized.
Transformers sized, shown on plans.
Phone 970.224.5828 Fax 970.224.1662
Issue Contact: Rob Irish
401 West Mountain Ave. Suite 201
Fort Collins, CO 80521-2604
vfripley.com
CoM n xwr
R- SPeNJ'F