HomeMy WebLinkAboutADVANCE AUTO PARTS - PDP - 26-07 - REPORTS - TRAFFIC STUDY (3)ALDRIDGE TRANSPORTATION CONSULTANTS, LLC
Page 6 of 6
The graphic above shows the proposed location of the shared driveway which is 15 feet offset
north of the property line. There are no required improvements including building reconfiguration
from the adjacent property owner. A joint access easement will allow the property owner to the
south full use of the driveway and ensure its future use by both properties should the south side
redevelop.
The graphic above shows the problem with a shared driveway constructed to CDOT and City
specifications. A 25 foot drive aisle would require the removal of the front 15 feet of the existing
building. Also it is assumed that the right-of-way dedication, landscaping, and sidewalk
requirements would be waived for the remainder of the property on the south side to preserve the
small building that directly fronts on North College.
+` ALDRIDGE TRANSPORTATION CONSULTANTS. LLC
Page 4 of 6
Should you have any questions or need additional information please call me at 303-703-
9112. Thank you for the opportunity to be of service.
Kind
Aldri,
John:
Principal
Jmwa/melatt.
Consultants, LLC
'OE, AICP
ALDRIDGE TRANSPORTATION CONSULTANTS. LLC
Page 3 of 6
This facility is a low volume traffic generator. For comparison a typical fast food
restaurant with a drive through window will generate over 100 trips in the PM peak hour
vs. the 42 vph projected here. A drive in bank will generate over 200 trips in the PM peak
hour.
TRAFFIC DISTRIBUTION & ASSIGNMENT
The distribution assumed, to be conservative, all of the traffic using the North College
shared access. The entering left turn was programmed at 13 vph, the entering right turn at
8 vph. The exiting left turn was programmed at 8 vph and the exiting right turn at 13 vph.
The existing condition with the site generated traffic is shown on the attached operations
analysis. To project future 20 year future conditions, ATC factored the existing volumes
by 1.27 per the CDOT website. This is considered conservative in developed areas. The
2027 PM peak hour is shown in the operations analysis worksheets that are attached.
Please note the 2027 analysis is to meet code requirements. We are fully aware that the
proposed long-term plans for North College in the ACP would not allow the access.
TRAFFIC IMPACT
ATC uses Synchro v.6 for operations analyses. The Synchro reports are attached for
reference. For the PM peak hour analysis we are assuming a standard eight percent of
daily volume and a 55/45 directional split, with the heavier movement in the northbound
direction during the PM peak hour. The operations analysis shows that the critical
movement at the access (northbound left turn out) will operate at LOS B during the PM
peak hour for the existing plus site generated condition and in the future (2027)
condition. The left turn in from North College will operate at LOS B in existing
conditions with a 95th percentile queue length of 2 feet (25 feet is one vehicle). In 2027 it
will continue to operate at LOS B with a 95th percentile queue length of, again, 2 feet.
CONCLUSION & RECOMMENDATIONS
Based on the site plan and operations analysis, the proposed full movement shared access
will provide the site with efficient on and off site movement without compromising
safety or traffic operations on North College. No improvements to the adjacent streets
and intersections are occasioned by the project.
In our opinion the shared access is in conformance with the ACP but its exact location on
the property line is precluded by the existing buildings on the adjacent property. Our
investigation finds that a 15 foot offset to the north, a joint access easement, and support
of the long-term plans are consistent with the purpose and intent of the ACP and State
Highway Access Code.
Please let us know the best way to proceed on getting an access permit for this property.
ALDRIDGE TRANSPORTATION CONSULTANTS, LLC
Page 2 of 6
driveway on the property line and how the front 15 feet or more of building would have
to be removed to allow a 25 drive aisle from the driveway. The second graphic shows
how we propose to locate the driveway which is 15 feet offset from the property line.
This would permit both properties to use the driveway. A joint access easement would be
provided to ensure future use and in the event the south side property owner redevelops
he/she would have that access available. It would also be possible to reconstruct the
driveway to be on the property line if that makes sense in the future.
We understand you're are concerned about this proposal and are recommending a design
waiver for the 15 foot offset. This is obviously a hardship situation created by physical
limitations. It is our opinion that the 15 foot offset will have no impact on the operations
and safety of the roadway and that the proposed reconstruction of the frontage, dedication
of right of way for the widening of North College, and landscaping features will, in fact,
be a sizeable benefit to CDOT and the City.
Furthermore, the developer and property owner are fully aware of the long-term plans in
the ACP and supportive of them. This includes a possible raised median in the near -term
that would restrict the access to a right in/right out and the ultimate condition where all
access would be eliminated on this section of North College.
The following is a traffic impact analysis for your consideration.
EXISTING CONDITIONS
In this area, North College is a four -lane roadway with a painted center left turn lane. It
currently carries approximately 23,800 ADT (average daily traffic) according to 2004
CDOT counts. Hemlock is a two-lane collector type roadway. The intersection is full -
movement and stop -sign controlled.
PROPOSED LAND USE and TRIP GENERATION
The proposed land use is auto parts sales. The estimated trip generation is from the
Institute of Transportation Engineers Trip Generation Manual, 7th Edition. The
following chart shows the trip generation for the weekday and the AM/PM peak hour.
843 Automobile Parts Sales KSF 7 61.91 1.10 1.11 2.93 3.05
433 8 8 21 21
Transportation T&nning andTraffic Engineering
John M.W. Aldridge, PE, PTOE, AICP
Colorado Registered Professional Engineer
Professional Traffic Operations Engineer
American Institute of Certified Planners
May 10, 2007
Ms. Gloria Hiee-Idler
Access Manager
CDOT R-4
1420 2nd Street
Greeley Colorado 80631
RE: Traffic Study
Advance Auto — Ft. Collins, Colorado
Dear Gloria:
1840 W. Uttleton Blvd., Suits B
Uttleton, Co 80120
Tele: 303-703-9112
Fax:303-703-9152
Mobile:303-594-4132
Email: johnaldridge(rilgwest net
This technical letter provides a study of the potential traffic impact occasioned by the
development of an Advance Auto Store in Fort Collins, Colorado. The project site is
located on the southwest corner of North College and Hemlock. The primary access to
the site will be from a full -movement shared access on North College approximately 150
feet south of Hemlock. Secondary access will be available from an alley on the west side
of the site.
The site plan has been prepared in accordance with the City of Fort Collins Planning
Department's guidelines that require the building to be located on the north side of the
site and as close as possible to the eastern property line. The access to the site has been
located per the US-287/SH-14 Access Control Plan (ACP) for the short-term condition.
The allowed short term access to properties on North College is described in Figure 3-13
on Page 33 of the US-287/SH-14 Access Management Report. The ACP shows a
shared driveway for this property and the adjacent property to the south and alley access
to Hemlock. Direct access to Hemlock is precluded by the ACP and the building location.
As we discussed at our recent meeting, the shared access to.North College cannot be
located on the property line at this time due to the proximity of the existing buildings.
Two graphics are attached for your reference. The first shows the location of the shared