HomeMy WebLinkAboutOLD TOWN FLATS - PDP - PDP130022 - CORRESPONDENCE -Comment Number: 1
Comment Originated: 08/09/2013
08/09/2013: On the Landscape plan a substantial amount of area is designated "Landscape
Planting" what does this mean? Additional details needed.
This was defined in the legend. An example planted bed has been added. (RMS)
Comment Number: 2
Comment Originated: 08/09/2013
08/09/2013: Four parking spaces along the North do not have wheel stops these spaces also
need to include wheel stops.
The wheel stops have been added. (RMS)
Comment Number: 3 Comment Originated: 08/09/2013
08/09/2013: Where is the walk-in access on the trash and recycling enclosure?
OZ Response: We have developed the design of the trash enclosure and now indicate doors and
a walk-in opening for tenants. (OZ)
Please label the dimensions of the trash and recycling enclosure on the site plan.
We have added dimensions. (OZ)
Comment Number: 4
Comment Originated: 08/09/2013
08/09/2013: The application states that bicycle spaces are located in each unit, is there a
designated area in the unit for this that can be seen in a example floor plan?
We have added a typical unit plan showing where the bike rack will be located. (OZ)
Can bicycle spaces be placed on the West side of the accessibility spaces?
Bicycle spaces have been added to the area near the access from the parking. (RMS)
Comment Number: 5 Comment Originated: 08/09/2013
08/09/2013: The drive direction of an aisle should be designated at the entrances of the aisle.
Plans should be revised to make the drive direction clearer at the entrances of aisles.
Amended (RMS)
Comment Number: 6 Comment Originated: 08/09/2013
08/09/2013: A modification request for increase in compact stalls was submitted by the
applicant. Due to recent LUC changes this modification is not necessary.
this, we focused peaestrian enhancements to the Mason and Maple Street frontages which serve
as a main pedestrian connection between the Max north terminus and the museum.
Topic: Traffic Impact Study
Comment Number: 1
Comment Originated: 08/23/2013
- Disagree with the Bike LOS findings in the Traffic Impact Study, considering the railroad
crossing on Mason. This needs to be reflected and addressed.
This has been addressed. (ELB)
- Disagree with the Ped LOS findings considering there is no sidewalk on Cherry (the north side
of the block), needs to be addressed in the study with potential mitigation
Done. Added narrative. (ELB)
- Ped LOS needs to discuss the pedestrian crossing of Cherry at Mason
Done. (ELBi
- The TIS did not include the chosen ped and bike destinations, would like to see what the
assumptions were.
Added narrative on destinations analyzed. (ELB)
Department: Water -Wastewater Engineering
Contact: Roger Buffington, 970-221-6854,
Topic: Construction Drawings
Comment Number: 1
rbuffington@fcqov.com
Comment Originated: 08/20/2013
08/20/2013: Are there other utilities not shown on the utility plans (telephone, cable, etc.)? With
the intensity of these infill projects which seem to fill up the entire site, it's important to have ALL
underground utilities shown and shown accurately to avoid conflicts and delays during
construction.
SiteWise has provided utility locates for the project site, and to the best of our knowledge, all utilities are
shown on the plans. (NE)
Comment Number: 2
Comment Originated: 08/20/2013
08/20/2013: There does not appear to be adequate space for the fire hydrant located adjacent
to the alley. A minimum of 2 feet (3 feet would be better) clear distance is required between
the fire hydrant and the curb/curb return.
The requested separation has been provided. (NE)
Comment Number: 3 Comment Originated: 08/20/2013
08/20/2013: Was the 12" main on the east side of Mason potholed to get an accurate location?
Potholing was scheduled for 9/16, but had to be delayed due to the flooding. The potholing has
been rescheduled for 9/25, and the plans will be updated to reflect that location. (NE)
Comment Number: 4 Comment Originated: 08/20/2013
08/20/2013: The Standard Detail for the Meter vault will be modified to move the MH access
out of the sidewalk. This revision will also include the requirement to extend conduits to the
face of the building to mount the radio units for the automated meter reading system.
Acknowledged. (NE)
Department: Zoning
Contact: Noah Beals, 970-416-2313, nbeals@fcqov.com
Topic: General
Department: Traffic Opa.ation
Contact: Ward Stanford, 970-221-6820, wstanford@fcqov.com
Topic: Traffic Impact Study
Comment Number: 1 Comment Originated: 08/23/2013
08/23/2013: The intersection of Maple and Mason no longer allows N/S left turns onto Maple.
Please revise TIS evaluation at the intersection.
The turning movements were analyzed in the existing condition since that is what is occurring at
the intersection. Future years were modified in the Revised TIS. (ELB)
Comment Number: 2 Comment Originated: 08/23/2013
08/23/2013: Please include in the TIS the review of the possible west bound left and east
bound right turn auxiliary lanes on Cherry into the alley.
This has been included. (ELB)
Comment Number: 3 Comment Originated: 08/23/2013
08/23/2013: Please provide the approach LOS's for each of the four directions in the various
LOS tables.
This has been included. (ELB)
Comment Number: 4 Comment Originated: 08/23/2013
08/23/2013: Please make sure the analysis is based upon the 2000 HCM (Synchro 6 or 7
HCM). We've found problems in the shared lane analysis of 2010 HCM.
The analyses utilized Synchro 6. (ELB)
Comment Number: 5 Comment Originated: 08/23/2013
08/23/2013: Please revise the east bound arrows on Maple at the Alley, Fig 7.
These have been revised. (ELB)
Comment Number: 6 Comment Originated: 08/23/2013
08/23/2013: Modeling the alley access on Cherry provides real possibility of west bound traffic
queuing back into the College intersection or impeding Sb College right turning traffic onto
Cherry. The Cherry St. alley access may need to be restricted to RVRo only. Internal staff
needs to discuss the issue.
Additional narrative added to TIS. (ELB)
Department: Transportation Planning
Contact: Aaron Iverson, 970-416-2643, aiverson@fcqov.com
Topic: Site Plan
Comment Number: 2 Comment Originated: 08/23/2013
- Is there an access easement across the parking lot to and from curb cut on College? This
movement is not addressed in the traffic study but should be discussed.
Did not address in TIS. (ELB)
- The north alley access to Cherry may be closed or moved in the future to implement a
railroad crossing quiet zone, this may impact circulation in the future.
Added narrative but did not model potential changes. (ELB)
- Suggestion: Consider alley improvements to create an enhanced alley experience similar to
other downtown alleys.
Alley improvements were considered and discussed with the DDA. The alley is part of the
Downtown Alley Improvement Master Plan, but it is not seen as a priority at this point. In light of
This has been conected. (NE)
Topic: Landscape Plans
Comment Number: 3 Comment Originated: 08/21/2013
08/21/2013: The index on sheet LP001 does not match the sheet LP101 title. See redlines.
Corrected (RMS)
Comment Number: 4 Comment Originated: 08/21/2013
08/21/2013: Please correct the LP101 sheet number in the index on sheet LP001. See
redlines.
Corrected (RMS)
Topic: Lighting Plan
Comment Number: 5
08/21/2013: No comments.
Comment Originated: 08/21/2013
Topic: Plat
Comment Number: 6 Comment Originated: 08/21/2013
08/21/2013: Please add the "Name/Title" in the Owners & Lienholders signature blocks. See
redlines.
We are currently using a standard placeholder for the Owner & Lienholder signature blocks. Once
they are confirmed, final entities will be added as requested. (NE)
Comment Number: 7 Comment Originated: 08/21/2013
08/21/2013: Please label the remaining portions of Block 23 that surround this Plat. See
redlines.
This info has been added as requested. (NE)
Comment Number: 8
Comment Originated: 08/21/2013
08/21/2013: Please show ties to the boundary from the monumentation found along the east
side of the alley. See redlines.
This info has been added. (NE)
Comment Number: 9 Comment Originated: 08/21/2013
08/21/2013: Please add bearings & distances for all easement lines shown. See redlines.
This info has been added. (NE)
Comment Number: 10 Comment Originated: 08/21/2013
08/21/2013: Please label alley dedication information. See redlines.
This info has been added. (NE)
Topic: Site Plan
Comment Number: 11 Comment Originated: 08/21/2013
08/21/2013: Please add a legal description for the property to sheet LS001. See redlines.
Corrected (RMS)
Comment Number: 12 Comment Originated: 08/21/2013
08/21/2013: The index on sheet LS001 does not match the sheet LS101 title. See redlines.
Corrected (RMS)
Comment Number: 13 Comment Originated: 08/21/2013
08/21/2013: There are line over text issues on sheet LS102. See redlines.
Corrected (RMS)
The required taming radii of afire apparatus access road shaj, oe a minimum of 25 feet inside
and 50 feet outside.
International Fire Code 503.2.4 and Local Amendments
Adequate turning radii at the alley entryway onto Maple Street shall be achieved along with any
future needs internal to the site.
Site plan has been revised to allow for trucks to access the alley from Maple, and turn into the
center drive aisle of the parking lot. (NE)
Department: Stormwater Engineering
Contact: Jesse Schlam, 970-218-2932, ischlam@fcgov.com
Topic: Erosion Control
Comment Number: 3 Comment Originated: 08/21/2013
08/21/2013: The site disturbs more than 10,000 sq-ft and in a sensitive area, therefore Erosion
and Sediment Control Materials need to be submitted for FDP. The erosion control
requirements are in the Stormwater Design Criteria under the Amendments of Volume 3 Chapter
7 Section 1.3.3. Current Erosion Control Materials Submitted does not meet requirements.
Please submit; Erosion Control Plan, Erosion Control Report, and an Escrow / Security
Calculation. If you need clarification concerning this section, or if there are any questions
please contact Jesse Schlam 970-218-2932 or email @ ischlam@fcgov.com.
An Erosion Control Report will be provided with the FDP, along with an Erosion Control Plan and
Details. (NE)
Contact: Wes Lamarque, 970-416-2418, wlamargue@fcqov.com
Topic: General
Comment Number: 1 Comment Originated: 08/19/2013
08/19/2013: Stormwater is ready for a hearing. Please see minor comments redlined on the
plans.
Redline comments have been addressed. (NE)
Comment Number: 2 Comment Originated: 08/19/2013
08/19/2013: The area of porous pavers and underground detention which lies underneath the
building may not be allowed or will require special consideration. The City will let the applicant
know of any determination.
The paver extents have been modified. (NE)
Department: Technical Services
Contact: Jeff County, 970-221-6588, icounty@fcqov.com
Topic: Building Elevations
Comment Number: 1 Comment Originated: 08/21/2013
08/21/2013: There are line over text issues on sheet PDP 2. See redlines.
This has been corrected. (OZ).
Topic: Construction Drawings
Comment Number: 2 Comment Originated: 08/21/2013
08/21/2013: There are line over text issues on sheet C200. See redlines.
Comment Number: 2 Comment Originated: 08/05/2013
08/05/2013: There is an existing streetlight on Mason, approximately 120 feet north of Maple
and one at the N.E. corner of Mason & Maple. The exact locations of these lights needs to be
shown on the landscape plan. Street tree locations need to be adjusted as necessary to
provide 40 feet of clearance between the tree and the lights (15 feet if the tree is an ornamental
type).
The existing streetlight on Mason, approximately 120 feet north of Maple, is proposed to be
removed and replaced with four (4) new pedestrian -scale pole -mounted light fixtures (by
Developer). Additional building -mounted light fixtures will further illuminate the adjacent
streetscape to safe levels. The existing streetlight at the N.E. corner of Mason & Maple is
proposed to be relocated to the parkway strip approximately 8 feet N.W. of its current
location. The proposed street trees have been adjusted to maintain separation requirements.
Comment Number: 3 Comment Originated: 08/05/2013
08/05/2013: Electric development and system modification charges will apply.
Acknowledged (BD)
Comment Number: 4 Comment Originated: 08/05/2013
08/05/2013: After the plans are final, an AutoCad drawing (V.2008) of the utility plan will need to
be sent to Terry Cox at TCOX @ FCGOV.COM.
Acknowledged (BD)
Department: PFA
Contact: Jim Lynxwiler, 970-416-2869, Iynxwiler@poudre-fire.orq
Topic: General
Comment Number: 1 Comment Originated: 08/20/2013
08/20/2013: FIRE LANES
Fire Lanes shall be provided to within 150' of all portions of the building, as measured by an
approved route around the exterior of the building. When fire lanes cannot be provided, the fire
code official is authorized to increase the dimension of 150 feet if the building is equipped
throughout with an approved, automatic fire -sprinkler system.
2006 International Fire Code 503.1.1
Comment No. 3 from the original PDR remains active and requires clarification. A meeting with
the project team and PFA staff determined that Maple St. could be used for aerial fire apparatus
access which eliminates the need for a 30' wide fire lane internal to the site. However, it must
be understood the more general, blanket requirement for 150' fire access to the building
remains. Providing for fire access through the alley is thereby necessary and as it will become
critical with further development within this site, it seems reasonable that this problem be
mitigated in the first phase rather than be put off until later construction phases. The alley shall
then maintain a 20' width, drive aisle throughout for fire access. Please contact me to discuss
this further.
Subsequent meetings with PFA have occurred since these comments were made, and
modifications to the site plan have been made. In particular, the layout of the parking area has
been modified to allow a fire truck to access the center drive aisle. An emergency access
easement has been provided in this location as well. (NE)
Comment Number: 2 Comment Originated: 08/21/2013
08/21/2013: TURNING RADII
infrastructure.
The truncated domes are now shown along with all improvements proposed at this corner. (NE)
Comment Number: 8 Comment Originated: 08/21/2013
08/21/2013: The transformer and trash enclosure shown off the alley do not indicate the use of
doors/fences to protect and screen. If a door and/or fence is to be constructed in either
location, they may not swing out into public right-of-way.
We have developed the design of the trash enclosure and now indicate doors and a walk-in
opening for tenants. (OZ)
Comment Number: 9 Comment Originated: 08/21/2013
08/21/2013: A truncated dome detection panel would need to be installed on the Maple Street
sidewalk just west of the alley in accordance with Drawing 803 of LCUASS.
Truncated domes will be installed per LCUASS and are now shown on the plans. (NE)
Comment Number: 13 Comment Originated: 08/23/2013
08/23/2013: There are two bike racks that are shown within Mason Street right-of-way. These
can't be counted towards any required bike parking for the development. The placement of
bike racks in right-of-way would need to be coordinated with FC Moves through a separate
process. Acknowledged.
Bike racks shown on Mason Street frontage are now within the property line. (RMS)
Topic: Traffic Impact Study
Comment Number: 11 Comment Originated: 08/21/2013
08/21/2013: I'll ultimately defer to Transportation Planning on the findings in the TIS regarding
Bicycle LOS. It was discussed however with Transportation Planning that the analysis and
findings of the bicycle system in this section of the TIS might be viewed differently in light of
comments #2 and #3.
Acknowledged. (ELB)
Department: Environmental Planning
Contact: Lindsay Ex, 970-224-6143,
Topic: General
Comment Number: 1
08/13/2013: No comments.
Department: Light And Power
Contact: Doug Martine, 970-224-6152,
Topic: General
lex@fcqov.com
dmartine@fcgov.com
Comment Originated: 08/13/2013
Comment Number: 1 Comment Originated: 08/05/2013
08/05/2013: The site shown for the utility electric transformer appears to be too small.
Depending on the electric service size, the transformer will require a minimum depth of 10 feet,
and width of 15 feet. Also, the transformer cannot be located under a building overhang or
within 20 feet of an emergency exit. Contact Light & Power Engineering at (970)221-6700 with
any questions.
Currently, a transformer pad measuring 4'-8" x 6 7', which is the dimension specified for a 75-500 KVA 3
phase transformer. The pad is surrounded by appropriate landscaping, and does not have any enclosure
surrounding it. (NE)
Clarified transformer location (Given)
Comment Number: 3
Comment Originated: 08/21/2013
O8/21/2013: The applicant should be aware that the City is actively looking at installing
temporary measures at this time to create a more perpendicular crossing for bicyclists heading
north along Mason Street due to heightened awareness on bicycle crashes occurring. Any
work that occurs should be considered temporary and would need to be removed and
improved with the project per the previous comment.
Addressed in revised TIS. (ELB)
Acknowledged. Thank you for the information. At this time, there are no plans to preserve the
temporary improvements as they do not relate very well to our proposed right-of-way
improvements and enhancements. (NE)
Comment Number: 4
Comment Originated: 08/21/2013
08/21/2013: The placement of the various structures in right-of-way have varying degrees of
concern. The elongated seatwall/retaining wall shown on the northwest corner of the property in
close proximity to the railroad would need to be placed outside of right-of-way. The smaller
concrete seatwalls indicated on the site plan may be approvable through an excavation permit,
subject to review of their specific design and review of placement with the finalized streetscape
design along Mason Street, looking to ensure sufficient through clearance for the general
public occurs. The stairs located along Maple Street right-of-way should ideally be removed at
this time and designed without the stairs, if the applicant still wants to pursue the placement of
the stairs in right-of-way, additional review and discussion is needed.
Additional discussions with city staff have indicated that the site layout as shown will be
acceptable. It is understood that revocable encroachment permits will be required for most, if not
all, of the structures listed. (NE)
Seatwall outside property and adjacent land parcel will be removed. Permits will be sought for
seat areas along Mason and stairways along Maple. (RMS)
Comment Number: 6 Comment Originated: 08/21/2013
08/21/2013: The parkways shown between the sidewalks and Mason/Maple street are 5 feet in
width and would not meet the minimum the parkway strip width for either street (8 feet for Mason
Street, 6.5 feet for Maple Street). It was commented on the PDR that 15 foot wide attached
sidewalks were envisioned by Current and Transportation Planning along the public streets and
may still be preferred over the detached sidewalks. Note that comments from Tom Knostman
with the City Streets Department would ideally want to see 8 foot wide parkway strips, if a
parkway strip is to ultimately be installed, or the use of tree grates and an attached sidewalk
system.
The water line complicates spacing of trees along Mason Street. Original goal was to have an
allee of trees on either side of 10' wide sidewalk, which limited the tree lawn to 5' for this to occur.
Bikeway location limits the parkway to a single row of street trees in the tree lawn behind the curb.
As there is not any parking along Mason Street, we feel an 8' tree lawn is the correct response to
this area and the extra wide condition R.O.W. The sidewalk is 10' wide to help accommodated
pedestrian movement to along the street towards Lee Martinez Park, Museum of Discovery and the
Poudre River and Trail system. Maple Street tree lawn is now shown at 6.5'. (RMS)
The required parkway widths are now provided. (NE)
Comment Number: 7
Comment Originated: 08/21/2013
08/21/2013: The plans don't show the existing truncated dome detection /access ramp installed
at the southwest corner of the site (northeast corner of Mason Street and Maple Street). The
plans need to reflect how the truncated dome/access ramp is to be situated with the new
Department: Engineering Development Review
Contact: Marc Virata, 970-221-6567, mvirata@fcgov.com
Topic: Building Elevations
Comment Number: 5 Comment Originated: 08/21/2013
08/21/2013: Please indicate the property line on elevations in order to demonstrate whether
balconies and other appurtenances above the first floor are possibly encroaching onto public
right-of-way.
We have added sections that indicate the relationship of the building to the property line. All
building elements are within the property line. (OZ)
Topic: Construction Drawings
Comment Number: 10
Comment Originated: 08/21/2013
08/21/2013: Any initial indication as to what the proposed cover of the storm drain outfall under
the alley, as well as how much patching would be envisioned in the alley right-of-way?
As currently designed, the 15" storm drain running at 0.5% will have 2.65' of cover from the outside of pipe
to the existing grade at the northern manhole (STMH 1). Cover increases over the length of the pipe run,
and reaches 2.88' of cover at the most upstream storm manhole. Opportunities exist to increase this
cover, including the use of a smaller pipe size, different material, flatter slopes, or some combination of
these options. A final determination on the solution will be provided with our final design. (NE)
Comment Number: 12 Comment Originated: 08/23/2013
08/23/2013: The storm line along the alley would need to be a public storm line in order to
travel within the alley right-of-way. If ultimately allowed, street patching for the storm line in the
alley would need to be for the entire alley width.
At this time. the storm drain is proposed to be public since it will provide an outfall to adjacent
properties in addition to our project. (NE)
Topic: General
Comment Number: 1 Comment Originated: 08/21/2013
08/21/2013: A repay for alley improvements abutting the property won't be required as
commented on the PDR. The age of the alley improvement is such that it's beyond the period
in which a repay can be collected.
Acknowledged. (NE)
Comment Number: 2 Comment Originated: 08/21/2013
08/21/2013: The creation of a separate bike lane for Mason Street is needed. The proposed
design does not create a separate bike lane north of Maple Street as bike are still either
combined with vehicles on -street, or combined with pedestrians off-street. A distinct bike lane
needs to be built with the project, with the goal of aligning with the bikelane along Mason Street
on the south side of Maple Street. Transportation Planning has created a sketch of how the
bikelane can be accommodated.
This has been addressed in the revised TIS. (ELB)
Bike lane has been included that allows for a continuous at street grade bike lane that crosses the
railroad tracks safely. The existing curb will need to be reinstalled approximately 2' east of
current location. This ensures all existing railroad infrastructure does not need to be relocated.
This concept was vetted with City Staff. (RMS)
A separate bike lane is now included with the design that attempts to balance the need to align with
the improvements to the south while preserving the existing railroad infrastructure on the northeast
corner of the intersection. (NE)
08/24/2013: The top parapet at the corner of Mason and Maple should be repeated at the top
of the southeast and northwest corners of the building as well.
We agree that a strong corner element is necessary to emphasize the intersection of Maple &
Mason, but don't feel that that the ends of the building merit similar emphasis. At some point in
Q • �I- '
the future, the ends of the building are likely to be obscured by future development, which will
drastically reduce the prominence of the southwest and northwest corners. (OZ)
Comment Number: 9 Comment Originated: 08/24/2013
08/24/2013: Along the west elevation, there is a strong horizontal band shown between the
fourth and fifth floors but this band is only depicted along a short segment of the south
tL
elevation. This band should be continued along the entire south elevation.
This band on the west elevation is used to provide a horizontal break in a flat section of wall. The
��+a
south elevations broken by projecting elements creating a more vertical rhythm. These vertical
�� G p J c ��''
elements are already broken at level 3 with a material change. We don't believe that it makes
d tJ
sense to further break this element. (OZ)
Comment Number: 10 Comment Originated: 08/24/2013
08/24/2013: The drawings indicate that the building is arranged in a series of modules allowing
for projections and recesses and shadow lines. This arrangement appears, at this time, to be
sufficient. In order for this concept to be more defined, the plan sheets should indicate the
depth of modules so we can see how the modules are differentiated from each other. Be sure
to indicate the depth of the step back between the second and third floors.
We have added sections that more clearly show horizontal relationships. (OZ)
Comment Number: 11 Comment Originated: 08/24/2013
08/24/2013: Please indicate exactly how and where the enclosed bicycle spaces will be
provided. How much square footage will be allocated within the unit for bicycle parking?
't
Perhaps a typical floor plan could be provided that indicates the location and size allocated for
bike parking.
We have added a typical unit plan showing where the bike rack will be located. (OZ)
Comment Number: 12 Comment Originated: 08/24/2013
08/24/2013: Please add a note that all rooftop mechanical equipment will be screened from
4 �� view from public streets and sidewalks.
We have added the note. For your information, rooftop equipment is fairly small and will be located
toward the center of the roof, allowing the parapet to provide the necessary screening. This is
evidenced by the views generated for the View Analyses, showing that no mechanical units are
visible. (OZ)
Comment Number: 13 Comment Originated: 08/24/2013
08/24/2013: The north and east elevations are depicted such that there are no windows on the
two ends of the building. Is this really the case?
Clerestory windows are indicated,which apparently did not show up well in your copy. The gray
color has been changed, which helps the window read visually stronger. Note that these windows
are in bathrooms and the bed wall of bedrooms, so making the windows larger is problematic.
(OZ)
Comment Number: 14 Comment Originated: 08/24/2013
08/24/2013: Please add to the Data Table the number of bedrooms and provide a ratio of the
number of parking spaces to the number of bedrooms.
We have added that information to the table. (OZ)
Comment Number: 2
Comment Originated: 08/24/2013
0, V
6.
0•�
08/24/2013: The arrangement of the seat walls along Mason Street looks very good but could
be improved by introducing more curves or semi -circular forms. As shown, the seat walls and
their relationship to the building and sidewalk is very rectilinear and could be softened with
more quarter -round or half -round shapes.
We believe the mounded garden beds and native planting will create the form that will create a successful
streetscape and outdoor rooms, or seating nodes for this area. The human scale pavement treatment will
also enhance these areas. We believe the rectangular treatments are a design response needed for an
urban street. (RMS)
Comment Number: 3
Comment Originated: 08/24/2013
08/24/2013: The area of the seat walls needs to be upgraded with additional ornamental
lighting. The Lighting Plan indicates only one fixture (662) along Mason Street. Please add
several more of these fixtures to complement the seat walls and to create a more inviting
space. We have added additional fixtures. (OZ)
Comment Number: 4 Comment Originated: 08/24/2013
08/24/2013: Please provide more detail as to the material that has been selected to screen the
parking lot along Mason Street. It is not entirely clear what this is and what color.
The parking lot will be screened with landscape. Mounded earth will reach 2' in height adjacent
to the parking lot. Grasses, perennials and small shrubs planted on the elevated soil will provide
a vegetative screen for the parking lot. (RMS)
Comment Number: 5 Comment Originated: 08/24/2013
08/24/2013: The Material Legend on the architectural elevation is difficult to de -code due to the
ability of the black and white drawing to convey the distinctions among the materials and colors.
Please indicate on the elevations the materials and colors so it is not necessary to refer to the
Legend.
We have clarified colors and materials to make them more readable. See elevations. (OZ)
Comment Number: 6 Comment Originated: 08/24/2013
08/24/2013: There appears to be a heavy use of gray color among the various materials.
Perhaps this amount of gray is excessive. Staff recommends less reliance on gray. The
building should take color ques from the Old Power Plant on North College, now the C.S.U.
Engines and Energy Conversion Lab and the historic Trolley Barn. Brick should be carried up
higher to the upper floors instead of being limited to the lower floors. The use of gray colors
looks repetitive and causes the building to appear more commercial than residential. Staff
recommends greater use of brick in the red and orange tones so as to better reflect the older
buildings in the Downtown area and to create a softer more residential character.
Colors have been revised. The brick is a medium orange, which is the predominant brick color in
the surrounding area. Much of the gray has replaced by warmer colors. See elevations. (OZ)
Comment Number: 7 Comment Originated: 08/24/2013
08/24/2013: Instead of topping the building with a metal coping, why not a real cornice? As
depicted, the top of the building is not distinctive, it just stops in space. Please replace the flat
metal coping with a projecting cornice that has real and effective depth. A detail should be
provided indicating the specifications to ensure that there is three -dimensionality and
shadowing.
An "eyebrow", functioning as a cornice, has been added to the projected, raised portions of the
fagades. These will be very visible when approaching from Mason or Maple Streets. See
elevations and perspective. (OZ)
Comment Number: 8 Comment Originated: 08/24/2013
F6rt Collins
Community Development and
Neighborhood Services
281 North College Avenue
PO Box 580
Fort Collins, CO 80522
970,221.6750
970.224.6134 - fax
fcgov. comIde velopmentreview
August 24, 2013
Dave Derbes
Brinkman Development, LLC
3003 E Harmony Rd
Fort Collins, CO 80528
RE: Old Town Flats, PDP130022, Round Number 1
Please see the following summary of comments from City staff and outside reviewing agencies for your
submittal of the above referenced project. If you have questions about any comments, you may contact the
individual commenter or direct your questions through the Project Planner, Ted Shepard, at 970-221-6343 or
tshepard@fcgov.com.
Comment Summary:
Department: Current Planning
Contact: Ted Shepard, 970-221-6343, tshepard@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 08/24/2013
08/24/2013: The relationship of the building to Maple Street must be enhanced by making the
unit entries more prominent. The entrances to these five units need to be highlighted with more
detail by use of more typical front doors, stoops, railings, overhangs, ornamental iron, planters
and the like. Please re -design these units so that Maple Street is the active and functional front
of the unit, not the back, secondary patio. Addresses or unit numbers/letters should be added
to create individuality. Space should be provided for planters. These units, and their
entrances, play an important role in activating the street and creating a pedestrian scale that
mitigates the height and mass of the building.
We have made several changes to the unit entries to make them more prominent, more functional,
and to make them feel more like a front door. The balconies over the unit entries have been
made more substantial, helping to emphasize these as entries. The sliding glass doors have
been replaced with a single door making them feel more like a formal entry than a back door
patio. Metal rails will provide a balance of enclosure/privacy and openness. The walks have been
shifted off -center to align with the door, providing a stronger focus on the entry as well as
making the porch more functional by providing a usable alcove out of the traffic flow. The
landscaping also serves to reinforce the sense of entry. (OZ)