our site borders a future City park so there are shared benefits
with combing parkland open space with our athletic fields. As
mentioned, we think the Mountain Vista site has strong
advantages for a future high school.
70. By excavating a detention pond, you will likely hit gravel. This gravel
will have to be totally removed in order for the disturbed ground to be
amended with soil to grow turf.
A. We intend to abide by the City's requirements for surface
treatment for stormwater detention ponds and water quality
treatment.
71. The pavement on Prospect Road has deteriorated due to construction
traffic associated with all the residential developments located to the
east of C.R. 5.
73. The project is not compatible with the area.
I
A. Response from the City: We understand your frustration. The
City's Traffic Operations Department will evaluate the District's
Transportation Impact Study. From our preliminary analysis, the
study appears valid but we consider it a draft at this point. As
we have mentioned, the "growth shall pay its own way' policy is
fair to tax payers, but it does require developers to create an
impact before improvements are constructed. This causes a lag
time between the impact and the necessary road widening.
63. The City is pushing up against the County and allowing growth to occur
along unimproved County Roads. The City needs to bear the
responsibility to build the street improvements that are needed in a
timely manner.
64. The underlying assumption of the T.I.S. is that the impact of future
phases will be mitigated by road improvements for which there is no
funding. This is a flawed analysis. As residents, we will be asked to
accept the inconvenience.
65. How will the traffic be distributed?
A. According to the T.I.S., 60% will go east and west on Prospect;
20% will go north on C.R. to Mulberry; 15% will go south on
C.R. 5 to Harmony; and 5% will go east of C.R. 5 on Prospect.
66. 1 can tell you that the Mulberry/C.R. 5 intersection is dangerous..The
Vista Bonita subdivision contributes to the traffic in this area.
67. What about the 50 acres that the District owns on the east side of C.R.
5 south of C.R. 40?
A. This land is being reserved for a future school. No decision has
been made as to the final use of this parcel.
68. In terms of street improvements, is the District being allowed to do
anything less than if the land were being developed by a private sector
entity?
A. No, we are being treated as if on equal par with a private
developer. Street improvements are based on trip generation
as calculated by a T.I.S. that meets the requirements of the City
of Fort Collins.
69. The District's facility should be placed into the Mountain Vista area.
The 1-25 interchange there is in better shape and there would less
impact on surrounding neighbors.
10
57. The relationship of the fueling station and the junior high school is
flawed. The prevailing wind pattern will blow the diesel fumes toward
the school.
A. Keep in mind that our buses are plugged in at night so there is no need
for engines to be kept idling to warm up. While the majority of the
buses would be diesel, we are investigating the use of alternative fuels.
58. I'm concerned about both the District's buses and the County's heavy
equipment all engaging at once. The County's operation will go all
hours during a snow storm. This will involve diesel engines, back-up
beepers, lighting, and staff coming and going. The two entities will
create a "double -whammy" for the nearby residences.
A. This is why we are proposing the berm along our north property
line.
59. How high would the highest building be?
A. The warehouse is expected to be approximately 28 to 30 feet in height.
60. Would the warehouse be a metal building?
A. We are exploring a combination of materials that includes metal but
this would not be a "Butler" building. By way of example, we are
looking at a design that is roughly similar to the new Northern Colorado
Water Conservancy District building in Berthoud. Other examples
include buildings at the Larimer County Fairgrounds, Group Publishing
and New Belgium Brewery. These buildings use a combination of
metal, pre -cast concrete panels, brick and other accent features.
61. Would our property values go down?
A. Don't know. You could ask an appraiser to evaluate the homes in
Brittany Knolls, a subdivision in southeast Fort Collins that overlooks
our southern bus facility off Trilby Road to see if there is a relationship
between property values and our facility.
62. I'm glad you brought up the Trilby Road facility. I used to live off Trilby
Road. The City's Transfort facility has been there for over 16 years
and Trilby Road is still not fully improved between College Avenue and
Lemay Avenue. If this is an example of the rate of public
improvements along an arterial street, then we as neighbors can
expect to experience all the increase in traffic and no corresponding
improvement in the roadway.
9
49. Why is the project needed now?
A. The project is needed to support the growth that has occurred with the
new schools in the eastern portion of the District.
50. Why is there a proposed access at the Meadowaire alignment?
A. It is better to align access points than to create offset intersections.
51. The ground presently includes eight wells. There is a fine source of
ground water that can support agriculture. Paving over this ground is a
waste of a valuable resource.
A. We would use the available ground water to irrigate our turf areas.
52. Would you treat the stormwater runoff?
A. Yes, we are required by the City's Stormwater Department to detain for
the volume of the 100-year storm and to provide water quality
treatment before the detained storm flows exit the site. The proposed
stormwater detention pond is at the southeast corner of the site.
53. What about a fuel spill at the fueling station?
A. We will be required by the Poudre Fire Authority to have a spill
containment area.
54. How "green" or sustainable would the project be?
A. The District has a commendable record in this area. Vegetation would
be drought -tolerant. Buildings would be energy efficient. We are
exploring the use of alternative energy sources such as photo -voltaic
solar panels.
55. Would the buildings be L.E.E.D. certified?
A. We don't know yet.
56. What about lighting? Our rural character would be impacted by an
excessive amount of outdoor lighting?
A. We are willing to work with you on lighting levels. For example, the
new light fixtures are now considered to be "dark sky compliant" and
we can explore the use of timers and photo cells to control the timing.
s
A. We agree that street improvements are not a minor expense.
40. It is very frustrating to travel westbound on Prospect Road and have to
stop and wait for a truck making a right turn exiting the truck stop.
There is not enough lane width for a truck to make this right turn
without encroaching into the westbound travel lane. This is an existing
problem that should be fixed.
A. We will pass this along to the City of Fort Collins.
41. What are the interim improvements that could be made to the
interchange without spending the $25 million on total reconstruction?
A. The interchange needs separate east and westbound left turn lanes on
Prospect for cars heading north and south on 1-25.
42. What is the worst case scenario for the interchange?
A. The worst case scenario is that no improvements are made by 2015.
In this scenario, there are Levels of Service failures up and down the
system.
43. How long would it take to fully improve the interchange?
A. With right-of-way acquisition, design and construction, it could take as
long as six years.
44. Does the 2015 scenario assume full build -out of the White property?
A. Yes.
45. It appears evident to me that due to the lack of funding by CDOT for
interchange improvements, it is irresponsible for the PSD to develop
this property as proposed.
46. 1 submit that the two key issues are land use and traffic. These two
issues are critical and stand on their own.
47. The project does not fit into the context of the area.
48. Is the PSD willing to plant a double row of street trees as per the
Prospect Road Streetscape Program?
A. Yes.
rl
31. Do the studied intersections currently meet the minimum Level of
Service standards for the City of Fort Collins?
A. Yes.
32. What are the peak timeframes?
A. The morning peak is 7:30 - 9:30 and the afternoon peak is 4:30 - 6:30.
33. 1 don't think the T.I.S. methodology is accurate for 1-25 and the ramps
due to the commuting nature of how the highway is used. There is an
extraordinary amount of inbound (into Fort Collins) traffic in the
morning from out-of-town commuters and reverse in the afternoon.
A. The T.I.S. captures the highest one -hour peak.
34. Will PSD and Larimer County build out Phase Two if the 1-25
interchange is not improved?
A. We do not know at this point.
35. Would you agree that the bridges over the Lake Canal on Prospect
and C.R. 5 and the 1-25 interchange are functionally obsolete?
A. Yes.
36. By my analysis, the PSD has only 2 of 50 facilities east of 1-25 and 48
of 50 are west of 1-25. Based on the distribution of facilities, the
warehouse should be located west of 1-25, not east.
A. We see the proposed location having strategic proximity to Mulberry,
Prospect and 1-25.
37. What do you estimate is the percentage of trips that would go north on
C.R. 5 and then west on Mulberry?
A. We estimate that this would be about 40% of the total.
38. Would Larimer County be required to improve their frontage along
Prospect Road to the arterial standard at the time they develop?
A. Yes.
39. The two bridges over the Lake Canal need to be replaced. I estimate
that this would cost between $750,000 and $one million. The present
lack of sidewalks is particularly disturbing, especially for children.
6
22. Like the project proposed for 1-25 and State Highway 392 in Windsor?
A. Yes.
23. Are all the interchanges along 1-25 outdated?
A. All but Harmony Road.
24. So, bottom line, when does the interchange need to be upgraded?
A. According to the assumptions made in the phasing plan, by 2015.
25. I'm concerned that the T.I.S. does not capture the true character of the
traffic impact associated with the interchange. Does the T.I.S. count
trucks the same as cars?
A. Yes.
26. So the T.I.S. indicates that Phase One Warehouse has a low impact?
A. Yes, the T.I.S. indicates that during the morning peak timeframe, there
would be 13 trips and during afternoon peak, there would be 15 trips.
27. But for Phase Two, these trips increase significantly?
A. Yes, for Phase Two, the morning peak would generate 500 trips and
the afternoon peak would generate 230 trips.
28. How many employees are expected at the Phase One Warehouse?
A. Approximately 25. And, the hours are typically 7:00 a.m. to 3:30 p.m.
which does not coincide with the peak times on the roadway.
29. How do you estimate the number of trips?
A. Good question. We use the trip generation data from Institute of
Traffic Engineers which is derived from real examples across the
country and updated on a regular basis.
30. How many trips are associated with the 1-25 Visitor Center?
A. We do not know but we think we captured these trips in the
background analysis and the 1.5% annual growth rate in background
traffic for the mid and long term analyses.
5
15. Does the T.I.S include full build -out of the entire site, including the
future school and development of the White property?
A. Yes, the T.I.S. includes three timeframes, 2010 (short term), 2015
(mid-term), and 2027 (long term). The short term includes the
warehouse. The mid-term includes both PSD and County
transportation maintenance and bus facilities. The long term includes
the school with an enrollment of approximately 750 students.
16. What is the assumption in the growth of background traffic?
A. The T.I.S. assumes that there would be 1.5% annual growth in
background traffic.
17. What is the immediate impact of the Phase One Warehouse?
A. This would be the short term condition and we estimate that the
warehouse will generate 100 trips per day which can be
accommodated on the roadway with the addition of an eastbound left
turn lane on Prospect at McLaughlin Lane.
18. What about the mid-term condition?
A. By the year 2015, an eastbound left turn lane would be needed at
Meadowaire. And the 1-25 interchange would need to be reconstructed
to include a four lane overpass, including right and left turn lanes. A
traffic signal would be needed on Prospect at the eastern frontage
road. And arterial street improvements would be needed along the
site's Prospect Road frontage.
19. What about the long term condition?
A. In the long term, arterial street improvements would be needed along
the C.R. 5 frontage. And a traffic signal would be needed at the
intersections of Prospect Road and C.R. 5 and at Mulberry Street and
C. R. 5.
20. Who is responsible for the improvements to the interchange and what
is the latest cost estimate? And, does any entity have the funding?
A. CDOT is responsible and the rough cost estimate is $25 million. We
are told that CDOT does not have funding in place at this time.
21. Is there an interim improvement option versus total re -build?
A. Yes, the interim improvement would be lane widening.
4
6. When would a school be constructed on the eastern portion of the site
and how would it be funded?
A. We think a school would be needed in the neighborhood of 2015,
depending on the rate of growth in this area of the District. Funding
.would also be dependent on a successful bond issue.
7. What would you build with Phase One Warehouse?
A. We would build a left turn lane for eastbound Prospect, a stormwater
detention pond, and landscaping around the building. We would not
build the berm along our north property line with Phase One as we
prefer to keep as much land under irrigated agriculture as possible.
8. How much would Phase One cost?
A. Approximately $3.25 million. These funds are available from the
current bond revenues and from savings on other projects and interest
earnings.
9. 1 live in Kitchell Estates and am concerned about the views to south.
A. Yes, we understand that the open field provides nice views and
that any development could impact views to the south.
10. Would the District be selling land to Larimer County?
A. Yes.
11. Would the County then close their operation on East Vine Drive?
A. Yes.
12. Does the Transportation Impact Study include the County facilities?
A. Yes.
13. Would the District construct a new bridge over the Lake Canal?
A. No.
14. Would the District re -locate the ditch with Phase One?
A. We do not know yet.
3
ADDITION OF TWO PERMITTED USES
The District is proposing to apply to the Planning and Zoning for the ability to
place two uses on the site that are currently not permitted in the Urban Estate
zone district. These two uses are Office and Warehouse.
Unless otherwise noted, all responses are from the applicant or the consultants.
Questions, Concerns, Comments
1. If approved by the Planning and Zoning Board, could we take our
concerns to the Poudre School District Board of Education?
A. Yes.
2. How long as PSD owned the land?
A. Since 1999.
3. Does the Board of County Commissioners know of this joint
development possibility with the Larimer County Road and Bridge
Department?
A. Yes, they are aware.
4. Why is this project needed? What's wrong with the current facilities?
A. Our current facility is located in the northwest portion of the District.
With the recent growth patterns, most of the schools are in the eastern
and southern portions of the District. An eastern bus hub would
reduce the miles the buses have to travel to and from their bus routes.
We would retain the present facility to serve the western and mountain
schools. Regarding the warehouse, we are presently over -crowded
and lease space in other buildings. A new warehouse would
consolidate the leased spaces and we gain efficiencies by being close
to 1-25 for both receiving materials and distribution to the new schools.
5. What about funding?
A. For PSD, we have funding in place for the Phase One Warehouse
only. Future phases would depend on the successful passage by the
voters of a bond issue. For Larimer County, all phases would depend
on a bond issue.
2
SECOND NEIGHBORHOOD MEETING SUMMARY
PROJECT:
DATE:
APPLICANT:
CONSULTANTS
CITY PLANNER:
Poudre School District — East Prospect Road Service
Facility and Junior High School
December 15, 2008
Poudre School District c/o Mr. Ed Holder
Mr. Bruce Hendee, BHA Design
Mr. Eric Bracke, ELB Engineering
Ted Shepard
CITY TRAFFIC OPERATIONS ENGINEER: Joe Olson
This is the second neighborhood information meeting for this project. By way of
review, this project represents a joint development between the Poudre School
District and Larimer County to develop the 98 acres located at the northwest
comer of East Prospect Road and County Road 5. The westerly portion of the
property would be devoted to various service functions of both organizations.
The easterly portion would be reserved for a future school.
For the Poudre School District, these functions include a materials warehouse,
an office building, a fleet maintenance building, covered parking for school buses
and a fleet fueling station. For Larimer County, these functions include fleet
maintenance and storage for the fleet and materials for the Road and Bridge
Department as well as a future warehouse and a general parking area.
These functions would not all be constructed at once. The Poudre School
District's proposed central distribution warehouse would be Phase One. The
other various buildings and site improvements would be phased in over time on
an as -needed basis. An internal street network is proposed to provide access to
the various parcels and to provide the required access for the Poudre Fire
Authority.
OVERALL DEVELOPMENT PLAN
The District is proposing to apply to the Planning and Zoning Board for an Overall
Development Plan. The purpose of an O.D.P. is to establish general planning
and development control parameters for projects that will be developed in phases
with multiple submittals while allowing sufficient flexibility to permit detailed
planning in subsequent submittals.