Loading...
HomeMy WebLinkAboutRIGDEN FARM, 15TH FILING - PDP - 11-09 - SUBMITTAL DOCUMENTS - ROUND 1 - CORRESPONDENCE-CONCEPTUAL REVIEWDevelopment Standards, and Article 4. Districts (specifically Division 4.23 - Neighborhood Commercial Zoning District). The most pertinent sections of Article 3 (relative to this new mixed -use development) are Sections 3.2.1 - Landscaping, 3.2.2 - Parking, 3.5.1 - Architectural Compatibility, and 3.5.3 - Mixed -Use, Institutional and Commercial Buildings. Also, there are Land Use and Development Standards specific to the NC District that development on this property will be subject to. Copies of Article 3 and Division 4.23 are available in the Current Planning Department or on the City of Fort Collins website @ www.fceov.com. Go to Departments, then the Current Planning Department. Response: Site Specific PDP's will be addressed these codes. 9. The City's Current Planning Department will coordinate the development review process. The required submittal package will be submitted to the Neighborhood & Building Services Department and distributed accordingly to other City departments and outside reviewing agencies involved in development review. The submittal requirements for Project Development Plans and Final Compliance Plans are available on the City's website. Response: Noted. No response required. 10. The proposed commercial/retail uses in the multiple buildings are permitted in the NC District as a Type 1 or Type 2 review and public hearing. See Sections 4.23(B)(2)(c) and 4.23(B)(3)(c) of the LUC. The applicant for this development request may or may not be required to hold a neighborhood information meeting prior to formal submittal of the project. Type 2 development proposals are subject to the neighborhood meeting requirement. Regardless, City staff is suggesting that it would be beneficial to hold a neighborhood meeting. Please contact Steve Olt, at 221-6341, to assist you in possibly setting a date, time, and location for a meeting. Steve, and possibly other City staff, would be present to facilitate the meeting. Response: When this application was discussed in the pre -application meeting, we thought that a neighborhood meeting was not required or needed at this time since we are proposing any site specific plans. Future PDP submittals may warrant a neighborhood meeting. !f a meeting is requested for this application, we are willing to have one. We thank the City for their time in reviewing this application. If you have any questions, please feel free to contact me at 303-357-4600 or email at smaiergagoc.com. Respectfully, Scott Maier P.E. (CO) Project Manager Armstrong Development Properties, Inc. Response: We will continue to work with the Power Department as the project progresses. d. There are existing streetlights along the south side of Custer Drive. Response: One of the existing street lights will need to be relocated We will continue to work with the Power Department to address this situation. e. A C-I Commercial Form must be filled out to help determine the electric needs for this development. Response: We will continue to work with the Power Department as the project progresses. We may need to make assumptions for future tenants. Please contact Doug, at 224-6152, if you have questions about these comments. 6. Carle Dann of the Poudre Fire Authority offered the following comments: a. All of the buildings must be fire sprinklered and equipped with Knox Boxes. Response: Building Codes will be addressed by each tenant by a separate application. b. A fire lane, with an emergency access easement, is required if the buildings are not fire sprinklered. The fire lane must provide turning radii of 25' inside and 50' outside. Response: The site plan is provided with radii labeled for review. C. All of the buildings must be within 300' of a fire hydrant, with fire flows of at least 1,500 gallons per minute. Response: Noted. We would like to do a fire flow test as soon as possible. d. Addressing on the buildings must be visible from the street they are addressed from, with numerals at least 6" high on a contrasting background. Response: Building Codes will be addressed by each tenant by a separate application. e. A fire flow test can be done for this site. Response: We would like to do a fire flow test as soon as possible. Please contact Carie, at 416-2869, if you have questions about these comments. This development request will be subject to the Development Review Fee Schedule that is available in the Current Planning Department office. The fees are due at the time of submittal of the required documents for the appropriate development review process by City staff and affected outside reviewing agencies. Also, the required Transportation Development Review Fee must be paid at time of submittal and this fee is paid directly to the Engineering Department. Response: All of the submittal fees have been include with this submittal. 8. This development proposal is subject to all the requirements set forth in the City's LUC, specifically Article 2. Administration (Development Review Procedures), Article 3. General Response: We are proposing to use the existing sanitary sewer main stub. We are also proposing some additional water stubs for the future tenants. b. Any water/sewer lines extending into the site must be used (if properly sized) or abandoned at the main. Response: Noted. c. Development fees and water rights will be due at building permit. Response: Noted. It is our understanding that theses fees are associated with building permits and will be paid then. Please contact Roger, at 221-6854, if you have questions about these comments. 4. Glen Schlueter of the Stormwater Utility offered the following comments: a. This site is part of the Rigden Farm overall drainage plan. On -site detention and water quality treatment are included in that plan. The design engineer will need to verify compliance with the overall drainage plan especially the impervious percentage and drainage patterns. If there are differences, the design engineer will need to identify the impacts and possibly mitigate them. Response: A drainage report has been included in this submittal and this development complies with the Master drainage study. The impervious area was assumed and future tenants will need to meet the assumptions. b. The design of this site must conform to the requirements of the Foothills Drainage Master Drainage Plan as well the City's Design Criteria and Construction standards. Response: A drainage report has been included in this submittal and this development complies with the Master drainage studv. c. The city wide development fee is $4,420/acre ($0.1015/sq.ft.) for new impervious area over 350 sq.-ft. No fee is charged for existing impervious area. This fee is to be paid at the time each building permit is issued. Response: Noted. It is our understanding that theses fees are associated with building permits and will be paid then. Please contact Glen, at 224-6065, if you have questions about these comments. 5. Doug Martine of the Light & Power Department offered the following comments: a. The City has existing 3-phase power to the site. However, there is no existing vault. The development must accommodate this situation. Response: We will continue to work with the Power Department as the project progresses. b. The transformer locations must be coordinated with Light & Power. Transformers can be located no more than 10' from a paved area that can be accessed by City trucks and equipment. If the applicant submits a PDP only for the driveway improvements on -site there will be some risk for the future PDP's. Response: Noted. Each future tenant will need to address this comment. C. The standard electric development charges will apply to this development request. This property has 3 street frontages; therefore, the charges could be relatively high. 0 h. Triple street cut fees would apply where streets that have been paved for 5 years or less may have to be cut to install utilities, etc. Response: Based on our discussion in the pre -application meeting, it is our understanding that the surrounding streets are older than 5 years and therefore this comment is not applicable. This development may be responsible for repays for street improvements to Custer Drive and Illinois Drive. Response: We are researching to see if there are any street repays. Please contact the Poudre Fire Authority (PFA) for their emergency access needs. Response: Comments from the fire authority is addressed below. k. A subdivision plat is not required as part of this submittal to the City for development review because it was previously platted as Tract A of Rigden Farm Filing One. Any changes in easements, new easements determined to be necessary, or street right-of-way determined to be necessary on the property may be done through separate documents or by replat of the property. Additional utility easement width, from 9' to 15', along Custer Drive may be necessary due to existing lighting and fencing in this area. Response: We are proposing a replat of the subdivision. A Development Agreement and a Development Construction Permit will be required for development on this property. Response: Noted. We will prepare the agreement and permit as we achieve approvals for the PDP and final plans. In. Development on this property will be responsible for the repair and/or replacement of any damaged existing curb, gutter, and sidewalk around the site. Response: Noted n. The required Transportation Development Review Fee must be paid at time of submittal of the PDP. This fee is paid directly to the Engineering Department. Please contact Marc to determine the actual amount of fee to be paid. Response: The transportation fee is included in this submittal o. Dedication of all necessary on -site easements must be done by re -plat or by separate document(s). Response: We are proposing a replat of the subdivision. Please contact Marc, 221-6605, if you have questions about these comments. Roger Buffington of the Water/Wastewater Department offered the following comments: a. Existing mains: 12-inch water main in Custer, 8-inch water main in Illinois, 8-inch sanitary sewer in Custer (East half of site only), 8-inch water and 8-inch sewer mains are stubbed onto site at approximately the midpoint of the north side. 1. All trash enclosures in this development must be designed and constructed to accommodate recycling and match the materials on the buildings. Response: Noted. Not applicable at this time, however, future PDP's will address this comment. Please contact Jenny, at 416-2313, if you have questions about these comments. 2. Marc Virata of the Engineering Department offered the following comments: a. The standard utility plan submittal requirements will apply to this development request. Response: A utilityplan has been included in this submittal. b. Street oversizing fees will apply to this development request. The fees are based on vehicle trip generation for the proposed land use(s) in the development plan. Please contact Matt Baker of Engineering, at 224-6108, for detailed information on the fees. The fees will be collected at the time of issuance of building permits. Response: Noted. Not applicable at this time, however, future building permit requests will comply. C. The Larimer County Road Impact Fees will apply to development on this property. Response: Noted It is our understanding that theses fees are associated with building permits. d. A Transportation Impact Study (TIS), addressing all modes of transportation, will be required with your Project Development Plan (PDP) submittal. Please contact Joe Olson of the Traffic Operations Department, at 224-6062, and Matt Wempe of the Transportation Planning Department, at 416-2040, to determine what information will be needed in the TIS pertaining to Level of Service (LOS) for vehicle, pedestrian, bicycle, and transit modes of transportation. Response: A Traffic Impact Study has been included in the submittal. e. This development will be subject to the requirements set forth in the Larimer County Urban Area Street Standards (LCUASS), especially how they relate to the separation between the proposed access from Custer Drive. Figure 9-1 of LCUASS specifies a 200' centerline to centerline distance between the proposed driveway and Timberline Road. Response: The proposed access point is separated more than 200' from Timberline Road centerline. The proposed driveway on Illinois Drive must line up with the existing driveway into The Seven Oaks Academy to the east. Response: The proposed access drive's do line up with the adjacent property access point. g. The driveway types and widths must be to street standards. Response: The driveway types and widths are indicated on the site plan. 0 c. measurement shall apply to the highest portion. This is set forth in Section 4.23(E)(2)(d) of the LUC. Response: Noted Not applicable at this time, however, future PDP's will address this comment. d. All buildings in the NC District shall be limited to 5 stories in height, per Section 4.23(E)(2)(d) of the LUC. Response: Noted. Not applicable at this time, however, future PDP's will address this comment. e. The maximum parking allowances for non-residential uses are set forth in Section 3.2.2(K)(2) of the LUC, specifically the table in Section 3.2.2(K)(2)(a). The proposed bank on Lot 1 of the conceptual plan would be permitted to have a maximum of 15 parking spaces (4,195 square feet x 3.5 spaces/1,000 square feet). Response: Noted Not applicable at this time, however, future PDP's will address this comment. f. At least 1 van accessible parking space and a certain number of handicapped parking spaces are required in this development. The number of spaces and definition of van accessible are found in Section 3.2.2(K)(5)(d) of the LUC. Response: Noted. Not applicable at this time, however, future PDP's will address this comment. g. Bicycle parking must be provided in the development and it must satisfy the requirements set forth in Section 3.2.2(C)(4) of the LUC. Response: Noted. Not applicable at this time, however, future PDP's will address this comment. h. The buildings in this development will be subject to the requirements set forth in Section 3.5.3 - Mixed -Use, Institutional and Commercial Buildings of the LUC relating to the "build -to" line standards. Response: Noted. Not applicable at this time, however, future PDP's will address this comment. The Bank pad is not able to comply due to the existing corner monuments. This was discussed at the pre -application meeting and it was understood. The required amount of parking lot interior landscaping is set forth in Sections 3.2.1(E)(5) and 3.2.2(M) of the LUC. The required (minimum) amount is either 6% or 10%, depending on the number of parking spaces in a lot. In excess of 100 spaces requires 10% interior landscaping. Response: Noted Not applicable at this time, however, future PDP's will address this comment. j. Street trees around the site must be provided in accordance with Section 3.2.1(D)(2) of the LUC. Response: Noted. Not applicable at this time, however, future PDP's will address this comment. There are existing street trees along Custer Drive. k. This development will be in the City's Residential Neighborhood Sign District; therefore, locations only for exterior building wall signage must be shown on the building elevations that are submitted for development review. The actual size and content of signs should not be shown. The signage will be reviewed by the Zoning Department at the time of a building permit application. Response: Noted. Not applicable at this time, however, future PDP's will address this comment. • ARMSTRONG Su t27Street 0122 Suite 2700 DEVELOPMENT Denver,C080230 www.armstrongdev.com PROPERTIES, INC. 303.357.4600 February 4, 2009 303.357.4605 fax City of Fort Collins — Planning 281 North College Avenue Fort Collins, CO, 80524 RE: PDP Submittal — Southeast Comer of Timberline Rd. and Custer Dr. ADPI At Rigden Farms MEETING DATE: January 12, 2009 ITEM: Bank & Commercial/Retail Development on Tract A of Rigden Farm, Filing One APPLICANT: Scott Maier, David Moroney Armstrong Development Properties, Inc. 999 Eighteenth Street, Suite 2700 Denver, CO. 80202 LAND USE DATA: Request to replat Tract A of Rigden Farm, Filing One into 3 separate lots and initially submit an application for a development plan for minor infrastructure improvements on the 2.7 acre site, which is bounded by South Timberline Road to the west, Custer Drive to the north, Illinois Drive to the east, and the Timberline Church to the south. A second application would be submitted and processed separately for a proposed bank on the westerly lot and future applications would be submitted and processed for the 2 easterly lots. The entire property is in the NC, Neighborhood Commercial zoning district. COMMENTS: Jenny Nuckols of the Zoning Department offered the following comments: a. This property is in the NC, Neighborhood Commercial District. There are numerous commercial/retail uses permitted in this District, including financial services. Response: No Response Necessary b. "Offices, financial services and clinics" are permitted in the NC District, subject to an administrative (Type 1) review and public hearing. Response: No Response Necessary b. All buildings in the NC District shall have a minimum height of 20', measured to the dominant roof line of a flat -roofed building, or the mean height between the eave and ridge on a sloped -roof building. In the case of a complex roof with different co -dominant portions, the