Number: 30 Created: 8/29/2006
[ 10/4/06]
[8/29/06] If the clean -outs on the sewer services are in the driveways,
traffic rated clean -outs are required. Include the standard detail.
Department: Zoning Issue Contact: Peter Barnes
Topic: Zoning
Number: 51 Created: 9/21 /2006
[9/21/061 Section 4.7(E)(4) of the LUC requires the side yard setback to be
at least 5' for the first 18' of wall height. Portions of a wall along the side lot
line that exceed 18' in height require an additional setback of 1' for each 2'
or fraction thereof of wall height that exceeds 18' in height. I can't tell for
sure from the elevations whether or not this is met (i.e. If a part of the wall
is set in or if the entire wall is in the same vertical plane). There may be a
problem with the south wall of Unit A if it's 20' tall as it appears to scale to.
In such case it would have to be 6' from the north lot line and it is only
about 5'. There may also be a problem with additional portions of the south
side of Unit A, but I can't tell if or where there's a break in the vertical
plane.
Be sure and return all red -lined plans when you re -submit, per the
Revisions Routing Sheet, attached.
If you have any questions regarding these issues or any other issues related
to this project, please feel free to call me at 221-6341.
Yours Truly,
Steve Olt
City Planner
cc: Randy Maizland
Alpine Consulting Engineers
Current Planning file #22-06
Page 4
1
Number: 39 Created: 9/ 1 /2006
[10/5/06] Please fix any more errors in the text of the report and include
site specific explanation of the 5,000 sf rule.
[9/ 1 /06] Please update the drainage report text to the current site and edit
all inconsistencies.
Number: 41 Created: 9/ 1 /2006
[10/5/06] Repeat Comment. Please document this with detailed grading on
the grading plan.
[9/1/06] The flows from the site need to be directed to Wood street and the
alley. Please document on the drainage plan that onsite flows will not enter
neighboring properties and flow to the street and alley. This needs to be
done with flow arrows and spot elevations that support the design.
Number: 52 Created: 10/3/2006
[ 10/3/06] The detention quantity calculation for this site is incorrect. Six
times the amount of detention being proposed is required, 2425 cf is
required with a .3 cfs release rate. After meeting with the City, applicant
will include water quality detention and submit a variance for the quantity
detention.
Number: 53 Created: 10/3/2006
[ 10/3/061 Water quality detention is also requited for this site. Please
include in the drainage report calculations that document the amount of
water quality volume, orifice sizing, etc.
Number: 55 Created: 10/5/2006
[ 10/5/061 Please include the City's standard water quality outlet structure
detail on the plans.
Number: 56 Created: 10/5/2006
[ 10/5/06] Please remove the incorrect orifice sizing calculation of 3 cfs in
the report. .3 cfs is the 2-year historic release rate.
Number: 57 Created: 10/5/2006
[10/5/06] The detention documentation is the only thing required before a
hearing.
Department: Stormwater-Water-Wastewater Issue
Contact: Roger Buffington
Topic: Water/Wastewater
Number: 28 Created: 8/29/2006
[10/4/06]
[8/29/06] The curb stops must be in the utility easement adjacent to Wood
Street, and the meter pits must be within 2 feet of the curb stops.
Page 3
s
[8/ 15/06] Provide all 48 standard PDP general notes from Appendix E-1.
Any notes that do not apply to the project may be lined out but should not
be deleted.
Number: 14 Created: 8/ 15/2006
[ 10/3/061 The lot lines are now being shown but the line types are very
inconsistent or do not correspond to the legend. Please revise line types
accordingly, see redlines for clarification.
[8/ 15/06] Please show the existing lot line between lots 4 and 5 on all
sheets in the Utility Plan set. Clearly label property lines and existing right-
of-way limits.
Number: 20 Created: 8/ 15/2006
[10/3/06] ROW dimensions are not properly labeled on the Site and Utility
Plans. The alley ROW is 20 feet wide and Wood Street ROW is 100 feet wide
as dedicated on the Capitol Hill Subdivision Plat. Please revise the labeling
and dimensions on the plans accordingly.
[8/ 15/06] Show and label all property lines and right-of-way limits on the
Utility Plan sheet.
Department: Transportation Planning Issue Contact: David Averill
Topic: Utility Plans
Number: 31 Created: 8/29/2006
[10/3/06] Please label and dimension all walkways on the utility plans.
Thanks.
[8/29/06] Sidewalk on Wood isn't represented consistently between the site
and utility plan sets. What is the proposed improvement exactly?
Department: Stormwater-Water-Wastewater Issue
Contact: Roger Buffington
Topic: Landscape Plans
Number: 54 Created: 10/4/2006
[ 10/4/06] Show water and sewer services on landscape plan and provide
required separation distances.
Department: Stormwater-Water-Wastewater Issue
Contact: Wes Lamarque
Topic: Stormwater
Number: 38 Created: 9/ 1 /2006
[10/5/06] Please include the net increase in a paragraph in the text of the
drainage report.
[9/ 1 /06] Please clearly document the impervious area's net increase for.
this site. The calculations indicate the net increase to be over 7,000 sf,
which would require this site to provide onsite quantity and quality
detention.
Page 2
!00;
�3STAFF PROJECT REVIEW
City af'FoR Collins
CRAIG MCKEE
Date: 10/09/2006
Staff has reviewed your submittal for 617 WOOD STREET, PDP - TYPE 2,
and we offer the following comments:
ISSUES:
Department: Current Planning Issue Contact: Steve Olt
Topic: Stormwater
Number: 58 Created: 10/9/2006
[10/9/06] There are issues associated with the storm drainage for this
development. If they can be resolved in a timely fashion and to Stormwater's
satisfaction, no later than October 18th, then this item could possibly go
to the Planning & Zoning Board on November 16th.
Department: Engineering Issue Contact: Randy Maizland
Topic: Engineering
Number: 37 Created: 8/31 /2006
[10/3/06] Same comment relating to street cuts on Wood Street for water
service connections.
[8/31 /06] Pavement management comment - Wood Street was paved in
2003. Penalties will apply to any street cuts made on Wood Street - triple
street cut fees.
Topic: Site Plan
Number: 8 Created: 8/ 15/2006
[10/3/06] The applicant has indicated that the standard 8 foot utility
easement behind the alley ROW may not be needed by the public utility
companies however, an 8 foot utility easement is being shown on the plans
and no variance request has been submitted by the engineer. Until a formal
variance request has been submitted and approved by the utility providers,
the City will require that an 8 foot wide utility easement dedication be
submitted with a $250 transportation development review fee. If a variance
request is submitted and approved, the utility easement should be removed
from the plans.
[8/ 15/06] Alley standards require that an 8 foot wide utility easement be
dedicated behind the alley right-of-way. This proposed easement shall be
shown and labeled on the Site Plan.
Topic: Utility Plans
Number: 13 1 Created: 8/ 15/2006
[ 10/3/06] Several general notes that apply to this development were lined
out on the Utility Plans. Please see the redlines for clarification on which
notes can be lined out.