HomeMy WebLinkAboutVERIZON WIRELESS FTC DRAKE CROSSING - PDP/FDP - FDP130032 - SUBMITTAL DOCUMENTS - ROUND 2 -Comment Number: 1
Comment Originated: 08/21/2013
08/21/2013: EMERGENCY GENERATOR
The storage and use of diesel fuel, in conjunction with the diesel generator, shall comply with
any applicable sections of Chapter 34 of the International Fire Code on Flammable and
Combustible Liquids. The equipment shelter housing the generator shall be properly signed
and labeled.
Department: Stormwater Engineering
Contact: Jesse Schlam, 970-218-2932, Ischlam@fcgov.com
Topic: Erosion Control
Comment Number: 1
Comment Originated: 08/01/2013
08/01/2013: No Comment from Erosion Control. This site; disturbs less than 10,000 sq-ft, is not
in a sensitive area, and is not in a larger development under construction. Therefore, no
submittal of erosion control material is needed. However, the site still must still be swept and
maintained to prevent dirt and other pollutants from entering the storm sewer or else BMPs will
be required of the site. If you need clarification concerning this, or if there are any questions
please contact Jesse Schlam 970-218-2932 or email @ jschlam@fcgov.com
Contact: Wes Lamarque, 970-416-2418, wlamargue@fcgov.com
Topic: General
Comment Number: 2 Comment Originated: 08/19/2013
08/19/2013: No comments.
Department: Technical Services
Contact: Jeff County, 970-221-6588, (county@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 08/07/2013
08/07/2013: Please rotate the text marked on sheet A1.0, 180 degrees so it is read from the
right side of the sheet. See redlines.
APPLICANT RESPONSE: This has been corrected.
Comment Number: 2 Comment Originated: 08/07/2013
08/07/2013: There is one line over text issue on sheet A3.0. See redlines.
APPLICANT RESPONSE: This has been corrected.
Department: Water -Wastewater Engineering
Contact: Roger Buffington, 970-221-6854, rbuffington@fcgov.com
Topic: Site Plan
Comment Number: 1 Comment Originated: 08/22/2013
08/22/2013: Show existing water service, meter pit and fire line on the site plan.
APPLICANT RESPONSE: This has been added.
Contact: Andrew Gingerich, 970-221-6603, agingerich@fcgov.com
Topic: General
Comment Number: 1 Comment Originated: 08/20/2013
08/20/2013: From the plat of the Drake Crossing Center 2nd Filing it appears that there is a
building envelope surrounded by a blanket access and utility easement. Measuring from the
plat and aerials it appears that the new structure may just barely fit within the existing building
envelope and potentially encroach into the easement by 1 - 2 feet. Please provide information
confirming that the structure will fit within the building envelope, otherwise we may need to
proceed with vacating a small portion of the blanket easement.
APPLICANT RESPONSE: Please see attached Building Envelope Detail showing that the
equipment structure ("Proposed Lease Area") does in fact fit inside the building envelope.
Comment Number: 2 Comment Originated: 08/20/2013
08/20/2013: An excavation permit will be required for any work within the right of way for tying in
communication lines.
Comment Number: 3
Comment Originated: 08/20/2013
08/20/2013: Any damaged curb, gutter and sidewalk existing prior to construction, as well as
streets, sidewalks, curbs and gutters, destroyed, damaged or removed due to construction of
this project, shall be replaced or restored to City of Fort Collins standards at the Developer's
expense prior to the acceptance of completed improvements and/or prior to the issuance of
the first Certificate of Occupancy.
Department: Environmental Planning
Contact: Lindsay Ex, 970-224-6143, lex@fcgov.com
Topic: General
Comment Number: 1
08/13/2013: No comments.
Department: Light And Power
Contact: Rob Irish, 970-224-6167, rirish@fcgov.com
Topic: General
Comment Originated: 08/13/2013
Comment Number: 1 Comment Originated: 08/14/2013
08/14/2013: Existing transformer is a 500KVA 120/208v 3-phase. Any relocation or modification
to the existing electric facilities will incur system modification charges.
Comment Number: 2 Comment Originated: 08/14/2013
08/14/2013: A C-1 form and One -line diagram will need to be submitted to Light & Power
Engineering showing power requirements.
Comment Number: 3
Comment Originated: 08/14/2013
08/14/2013: Owner will be responsible for Electric Capacity Fee and Building Site charges.
Contact Light & Power Engineering @ 970-221-6700.
Department: PFA
Contact: Jim Lynxwiler, 970-416-2869, Ilynxwiler@poudre-fire.org
Topic: General
September 16, 2013
Verizon Wireless FTC Drake Crossing, FDP130032, Round Number 1
APPLICANT RESPONSE TO FIRST ROUND COMMENTS
Please see the Applicant's remarks following each comment which requires a response.
Comment Summary:
Department: Current Planning
Contact: Noah Beals, 970-416-2313, nbeals@fcgov.com
Topic: General
Comment Number: 1
Comment Originated: 08/19/2013
08/22/2013: Applicant pointed out where this information has already been provided. No
further action is needed for this comment.
08/19/2013: Land Use Code (LUC) 3.8.13(C)(3) Roof monted equipment shall be located as far
away as possible for the roof's edge as possible. Please explain the proposed location and
why it is as far away from the roof edge as possible.
Comment Number: 2 Comment Originated: 08/19/2013
08/19/2013: LUC 3.18.13(C)(4) Along with the relocation of the two shurbs and one tree.
Additional landscaping should be added North of the equipment shelter.
APPLICANT RESPONSE: Please see Sheet L1 which shows three (3) additional shrubs in
front of the equipment shelter. These shrubs are also shown on the photosimulation of the
equipment shelter.
Comment Number: 3 Comment Originated: 08/19/2013
08/19/2013: LUC 3.18.13(C)(3) What is the cable tray made of? It should resemble a brick
column to blend better with the buildng.
APPLICANT RESPONSE: Please see the photosimulation of the equipment shelter. The cable
tray is metal but will be painted to match the color and texture of the brick on the building.
Comment Number: 4 Comment Originated: 08/19/2013
08/19/2013: LUC 3.18.13(B) The applicant has explained why co -locations was not possible in
current near by locations. But please provide information how the current proposal will allow for
co -location.
APPLICANT RESPONSE: Verizon Wireless antennas will occupy only a small portion of the
building rooftop. The existing rooftop is approximately 55,333 sq. ft.; the proposed antenna
screens will each occupy approximately 225 sq. ft. for a total of 450 sq. ft. The remaining area
of the rooftop will be available for co -location of other carriers.
Comment Number: 5 Comment Originated: 08/19/2013
08/19/2013: Remove the word future from plans.
APPLICANT RESPONSE: This has bee done.
Department: Engineering Development Review