With regard to the nominal argument, we're not talking about a small 2nd floor cantilever, but
rather a very large 2-story overhang. So I'm not sure this can be considered nominal,
inconsequential - going from no overhang to a 2-story, 40' x 1 10'overhang.
If they can't re -state their case, it may be that the decision maker will have to determine that
this alleviates an existing problem of city-wide concern as the justifcation for granting the
modification.
Subsequent to these comments the City staff determined that this was not a
requirement of this project and did not require a Modification.
[12/22/09]
[11/20/09] The second floor can't overhang the lower front or side exterior walls (Sec.
4.9(E)(1)(d). A modification will be required to allow what is proposed.
Subsequent to these comments the City staff determined that this was not a
requirement of this Droiect and did not reouire a Modification.
Please address Peter Barnes two comments and email PDFs to him and me with the
corrected plan and Modification Request.
If you have any questions regarding these issues or any other issues related to this project,
please feel free to call me at (970) 221-6750.
Sincerely,
Emma McArdle
City Planner
Page 4
as 40
Department: Stormwater-Water-Wastewater Issue Contact: Roger Buffington
Topic: Landscape Plan
Number: 56 Created: 12/22/2009
[12/22/09] Show water/sewer services on landscape plan and maintain landscape
separation distances.
Done
Department: Stormwater-Water-Wastewater Issue Contact: Wes Lamarque
Topic: Stormwater
Number: 28 Created: 11 /24/2009
[12/18/09] Additional comments may follow during final compliance review.
[11/24/09] Stormwater is ready for a hearing.
Acknowledged.
Department: Stormwater-Water-Wastewater Issue Contact: Roger Buffington
Topic: Water/Wastewater
Number: 53 Created: 12/22/2009
[12/22109] The existing water main in Meldrum is NOT PVC.
The material of PVC has been removed from the Existing Conditions Sheet and the
Utility Sheet.
Number: 54 Created: 12/22/2009
[12/22/09] Revise note on Sht CS2 pertaining to water line materials.
The note has been revised.
Number: 55 Created: 12/22/2009
[12/22/09] Add applicable Standard Details at Final Compliance.
Details have been added to the final Utility Plans.
Department: Zoning Issue Contact: Peter Barnes
Topic: Zoning
Number: 20 Created: 11 /20/2009
[12/22/09]
[11/20/09] Show the drive aisle dimensions on the site plan.
The dimensions were added to the Site Plan at that time.
Number: 22 Created: 11 /20/2009
[12/28/09] With regard to Modification Request 01:
I'm not convinced that they really addressed the 'equal to or better than' criteria, or
successfully explained how this is a nominal divergence. For instance, the code prohibits
the overhang, so I think they need to explain why the overhang is equal to or better than a
plan that doesn't have it. They explain that it maintains the existing traffic flow and retains
on -site parking, but I don't believe the purpose of the standard is to preserve the traffic flow
and number of parking spaces. And anyway, those are arguments that apply equally to a
building that doesn't have the overhang addition. I assume they mean that if they were to
construct a 1 st floor addition under this portion of the 2nd and 3rd floors, then there wouldn't
be an overhang and it would comply, but then the traffic flow and amount of parking would
be negatively affected, and therefore it's better to have no 1 st floor. The problem with that
argument would be that they couldn't build a 1 st floor addition under the overhang since
they've already maxed out the allowable floor area.
Paoe 3
ft 40
on the grading plan, however adding a very small highpoint just to the east of where the
curb cut into the swale is should be added to ensure that low flows enter the swale and does
not continue down the flow line and into the sidewalk ramp.
The grading and plans have been updated to represent detail D10-B.
Number: 61 Created: 12/23/2009
[12/23/09] On the curved portion of the porch that is very near the ROW line on the East
side of the property, please make sure that no footings or structures are within the ROW.
Number: 62 Created: 12/23/2009
[12/23/09] Is any special colored or textured concrete proposed for the section of concrete
that is on the east side of the building that ties into the sidewalk? If so, some language may
need to be included in the Development Agreement that identifies that neither the city nor
utilities are responsible for replacing the "upgraded" concrete should it need to be removed
and replaced.
Department: PFA Issue Contact: Carie Dann
Topic: Fire
Number: 31 Created: 11 /24/2009
[12/17/09] Still need do get together to resolve.
Let's continue to work together to resolve the few oustanding issues (FDC location, Knox
Box location(s), etc.
The FDC has been located on the Site Plan, off the southeast corner of the
building, approximately halfway between the building and the property line and
approximately 4 ft. behind the curbcut curb with a note that requires the
contractor to coordinate the final location with Poudre Fire Authority prior to
installation.
Two Knox Boxes have been indicated on the Site Plan: 15` next to the fire riser
room access door (refer to door on south wall of building) and 2nd on the
exterior building column just north of the main building entry on the east side of
the building.
Number: 51 Created: 12/17/2009
After reviewing plans again and considering the technicality of the Fire Code when it
concerns emergency vehicle access, we reallly need do extend the Emergency Access
Easement along the drive aisle, west to the edge of the property. While this means
exceeding our 150-foot max length for a fire lane (meaning we should have a 100-foot
diameter turnaround), I think it's more important to ensure that buidling is technically within
access. This is an existing structure and you don't have room for the turnaround.
The Emergency Access Easement has been revised to show it extending to the
alley on the west side of the property. Refer to the Site Plan and the Utility Plans.
An exhibit and legal description has been included with this submittal.
Department: Technical Services Issue Contact: Jeff County
Topic: General
Number: 58 Created: 12/23/2009
[12/23/09] All site, landscape & utility plans look good. No problems.
Page 2
40 40
i STAFF PROJECT REVIEW
Citv of Fort Collins
Otter Properties LLLP Date: 12/28/2009
Curt Richardson
#1 Old Town Square Suite 300
Fort Collins CO 80524
Staff has reviewed your submittal for Otter Box Corporate Headquarters PDP Type II, and
we offer the following comments:
Applicant responses shown thus after each comment Jan. 27, 2010
With Final Plan review submittal.
ISSUES:
Department: Current Planning Issue Contact: Dana Leavitt
Topic: Fire
Number: 52 Created: 12/18/2009
[12/18/09] No comments.
No comment required.
Department: Engineering Issue Contact: Andrew Carney
Topic: Genera!
Number: 50 Created: 11 /30/2009
[12/18/09] Addressed, but carried forward.
[11/30/09] Engineering has determined that this project will not be responsible for alley
improvements to the existing alley in the rear of the popertyt. However the project is
responsible for the undergrounding of the overhead line(s). If this can not be done at this
time the project will be responsible for providing conduit for the future undergrounding. If the
line will be in the grass buffer along the alley (outsiede of the ROW) a easement will be
required.
Due to service lines, it is currently not feasible to place the overhead electric
lines below ground. I have added conduit and a note on the Utility Sheet for
installation and future undergrounding. The conduit is proposed to the west of
the existino electric Doles and will remain within the existino right-of-way.
Number: 57 Created: 12/23/2009
[12/23/09] Not needed prior to hearing, but the emergency access easement will need to be
reviewed prior to final plan approval.
An exhibit and leaal description has been provided with this submittal.
Number: 59 Created: 12/23/2009
[12/23/09] In final compliance please add all applicable details (701, 707, 1601, 1602, 1606,
1607, 2201, D10B)
The soecified details have been added to the Utilitv Plan set.
Number: 60 Created: 12/23/2009
[12/23/09] The sidewalk chase that drains the North drive entrance will need to be built
according to standard detail D10B and should include a concrete pan running from the walk
out to the curb as well as the 1 foot flares in the sidewalk to protect pedestrians from walking
into the swale. Please refer to Detail D10B for the design specifics. Also, it is difficult to tell