HomeMy WebLinkAboutWATER'S EDGE @ RICHARD'S LAKE - PDP - 58-86J - CORRESPONDENCE - (8)[5/8/06] Sheet 13 shows an existing street stub or driveway on the north side of Brightwater
just west of Longboat Way. This will need to be closed. Please provide a ped ramp as
required for a T-Intersection.
Number: 112 Created: 7/4/2006
[12/26/06]
[7/4/06] Key Map needs to be updated to match current layout.
Number: 113 Created: 7/4/2006
[12/26/06]
[7/4/06] Before Hearing - There seems to be some confusion about the cross section
requirement. The spots for FL and CL are only for Locals where CL and FL stationing is
being used in lieu of using only CL stationing (as the code requires). Cross sections are still
required every 50' for all Arterial and Collector streets and they need to contain all
information required on the checklist or LCUASS. Spots for the locals are required in final
compliance, cross sections for collectors and arterials are required before hearing. 'Update
- Sheri has agreed to take a striping sheet showing existing row and the proposed edge of
pavement on the east side of Turnberry versus cross sections at this time.
Department: Light & Power Issue Contact: Doug Martine
Topic: Plat
Number: 147 Created: 1 /4/2007
[1/4/07] Need an 8 ft. utility easement along all tracts unless the tracts are identified as
blanket utility easements. An 8 ft. utility easement is needed along both sides of the private
drives.
Department: PFA Issue Contact: Carle Dann
Topic: Fire
Number: 142 Created: 12/26/2006
[12/26/06] PFA approves the modification request pertaining to Section 3.6.2(L)(1)(b) of the
FCLUC. Please note that PFA's "emergency response addressing requirements", which the
modification addresses, are based on the above section of the FCLUC. The LUC, which
specifies a private drive ... "is connected to only one street", is driving the modification
request, not PFA's addressing requirements.
Be sure and return all of your redlined plans when you re -submit.
If you have any questions regarding these issues or any other issues related to this project,
please feel free to call me at (970) 221-6750.
Yours Truly,
Steve Olt
City Planner
Page 6
0
Number: 32 Created: 5/9/2006
[12/26/06]
[7/4/06] Before Hearing - Just concerned with interim Turnberry improvements and where
the existing row is (do we need offsite row?), the taper to the north (do we have enough row
to accommodate it?) and the left turn at Douglas. John Gooch is submitting that information
with the intention of clearing up these questions and going to hearing August 17th. All other
comments will follow in the Final Compliance submittal.
[5/9/06] Little to no information was provided for existing offsites within 150' of the project.
The next submittal showing this information may trigger new comments and may require
additional changes to the plan sets.
Number: 47 Created: 5/9/2006
[12/26/06]
[7/4/06] Before Hearing - Carrying this comment forward until the plans show how the
proposed is tieing into the existing (see comment 32).
[5/9/06] See 7.4.1.A.6 for transitions for roadway shifts and lane drops.
Number: 137 Created: 7/11 /2006
[12/26/06)
[7/11/06] Final Compliance - The Morningstar median has been approved with the condition
that the median west of the roundabout is carried through to the Hearthfire intersection. The
proposed center turn lane is unnecessary as there are no access points or driveways on
either side of the street. Unused pavement breaks down faster and increases the
maintenance cost to the city so no variance can be granted. The other option the developer
has to remove the median for the entire length of the road to Turnberry. Note - This
comment does NOT need to be addressed prior to hearing.
Topic: Utility Plans
Number: 22 Created: 5/8/2006
[12/26/06]
[7/5/06] Thank you for submitting the checklist with this round. Just as a reminder, only
highlighted items are required and reviewed before going to hearing. All unhighlighted items
on the checklist are required in Final Compliance and are not reviewed prior to that. You will
turn in a "fresh" E4 at the first round of final showing that all required items have been
addressed in the plan sets or it'll trigger other comments.
[5/8/06] See Appendix E4 for all information that must be shown on the plans before going
to hearing. Please complete the checklist and submit with the next round of review. Any
information not shown on the plans required by the checklist will become a new comment
that will need to be addressed before going to hearing.
Number: 26 Created: 5/8/2006
[12/26/06]
[7/4/06] Final Compliance - May want to visit with JR in Tech Services after the first final
compliance submittal to get his input as early as possible. The set still has scanning
problems but this does not need to be worked out prior to hearing (it's more of a FC issue).
[5/8/06] Please see Appendix E6 for scanning requirements. May need to change the scale
and break some sheets into more sheets so that they scan properly.
Number: 29 Created: 5/8/2006
[12/26/06]
[7/4106] Final Compliance, issue still remains open.
Page 5
i 0
Topic: Plan and Profiles
Number: 136 Created: 7/11 /2006
[12/26/06]
[7/11/061 Final Compliance - turn on existing layer.
Topic: Plat
Number: 63, Created: 5/9/2006
[12/26/06]
[7/4/06] Repeat.
[5/9/06] From Technical Services: Boundary and legal close but do not match. Several
numbers do not match.
Number: 64
[12/26/06]
[7/4/06]
Created: 5/9/2006
[5/9/06] From Technical Services: Please show ties to oil radii. Locate easement.
Number: 118 Created: 7/4/2006
[12/26/06]
[7/4/06] Provide a tract table (who owns and maintains each tract plus what each tract is
for).
Number: 119 Created: 7/4/2006
[12/26/06]
[7/4/06] Scanning requirements in Appendix E6 aren't being met.
Number: 133 Created: 7/11/2006
[12/26/061
[7/11/06) From Technical Services: Text over text and line over text. Please correct and
see Appendix E6 for scanning requirements.
Number: 134
[12/26/06]
[7/11/06] From Technical Services:
Created: 7/11 /2006
How was Turnberry dedicated?
Number: 135 Created: 7/11 /2006
[12/26/06]
[7/11/06] From Technical Services: This is a preliminary plat - will need to see again in
Final Compliance for more detailed comments.
Topic: Street Design
Number: 12 Created: 5/8/2006
[12/26/06]
[7/4/06] Before Hearing - The proposed section of Morningstar west of Navigator does not
tie into existing and does not meet standard. Why are there 10' sidewalks proposed for two
sections west of the roundabout?
[5/8/06] Only one typical section is provided for Morningstar when there appears to be three
according to the horizontal control sheet in the utility plans. What are the typical sections for
the remaining two? Will need to see these before any approvals are given.
Page 4
Number: 145 Created: 12/28/2006
'[12/28/06] An 8' utility easement is required on both sides of the "alleys" or private drives.
Number: 146 Created: 12/28/2006
[12/28/06] A Utility Coordination is required to make sure the lots can be served with the
proposed layout and before the layout can be approved.
Topic: Grading
Number: 27 Created: 5/8/2006
[12/26/06]
[7/4/06] Final Compliance.
[5/8/06] Slopes can not exceed 4:1 and grades at the back of walk must be flat to nearly flat
for a minimum of 2'. Some areas have extremely steep slopes shown (not labeled) and may
require a retaining wall. Utilities are another concern (no structures are allowed in utility
easements). All lots less than 50' will need to show the driveway and utility locations on the
plan sets to make sure everything fits, including the street tree. A utility coordination has
been set for 2pm next Wednesday, the 17th of May to work out all the issues. All items
must be resolved and approved by the utilities prior to going to hearing.
Number: 41 Created: 5/9/2006
(12/26/06]
[7/4/06] Final Compliance - Please show slope info.
[5/9/06] Sidewalk grades are an issue. It appears that you are exceeding maximum slopes
per ADA requirements. Please label all sidewalk slopes where appropriate.
Number: 108 Created: 7/4/2006
[12/26/06]
[7/4/06] Before Hearing - Show existing grading for a minimum of 50' and tie proposed into
existing. Hard to tell if offsite grading is occuring due to the large property boundary line
weight. Will need to see this to determine if offsite easements are required. Please reduce
the line weight widths on the extra thick ones for legibility - all sheets. I can push this to
Final Compliance IF it is agreed that if offsite grading easements are needed and can't be
obtained, then the grading will need to change to pull everything back on site.
Topic: Landscape Plans
Number: 55 Created: 5/9/2006
[12/26/06]
[7/4/06] Final Compliance - Just keeping this comment alive until these conditions are
included in the DA.
[5/9/06] Landscaping in the median will not be maintained by the city nor will any damage to
the road caused by the irrigation system. All landscaping/road damage must be maintained
by the development and the future HOA and language as such will be included in the
Development Agreement. Landscape medians must include drainage facilities to handle
sprinkler runoff and nuisance flows. Refer to Appendix C for all other requirements.
Topic: Overall Utility Plan
Number: 114 Created: 7/4/2006
[12/26/06]
[7/4/06] Final Compliance - Hard to read, probably won't scan. Suggest breaking this out
into more sheets for legibility.
Page 3
[12/26/061
[7/4/06] Before Hearing - Comment 100 by Ward Stanford in Traffic will require that this
required left turn lane will have to be either designed and constructed with this development
or just designed with an equivalent cash amount to construct it in the future in the form of a
contribution in aid. I will bring the matter to Trans Coordination today if possible or next
week at the latest. Will need a preliminary design/layout prior to going to hearing.
Number: 105 Created: 7/4/2006
[12/26/06]
[7/4/06] Final Compliance - The ramps at Jettyand Skiff are not correct. Please treat as a
T-Intersection.
Number: 106 Created: 7/4/2006
[12/26/06]
[7/4/06] Before Hearing - Please provide a section through the proposed retaining wall on
the north side of lots 112 and 113 so that we can determine if offsite easements are
required. Please indicate the property line on the section and consider the excavation
requirements to install the wall. How tall will it be? Will need bottem and top of wall spots
on the utility plans.
Number: 107 Created: 7/4/2006
[12/26/06]
[7/4/06] Final Compliance - Missing ramps at Fleet and Morningstar as well as a ped refuge
area in the median. Also, there is an extra ped refuge shown on Morningstar that has no
purpose (located east side of Longboat), please remove.
Number: 110 Created: 7/4/2006
[12/26/06]
[7/4/06] Final Compliance - Shouldn't the ramp and the sidewalk line up at the south side of
the MF/Parkside and Cruiser?
Number: 111 Created: 7/4/2006
[12/26/06]
[7/4/06] Final Compliance - Please note on the Site and Utility Plans that driveway access
will not be allowed for the "A" lots on Daysailor and Outrigger and that all garage/driveway
access must occur off the alley or private drive. This note will also be made in the
Development Agreement.
Number: 117 Created: 7/4/2006
[12/26/06]
[7/4/06] Driveways must be perpendicular to the road (plus or minus 10 degrees) for a
minimum of 25'.
Number: 143 Created: 12/26/2006
[12/26/06] All comments from the last round were carried forward because only a
modification request was received with this round.
Number: 144 Created: 12/28/2006
[12/28/06] The proposed median in the local street will not be landscaped or maintained by
the city. In addition, it must remain in row (not in a tract) and no structures of any kind are
allowed within it.
Page 2
STAFF PROJECT REVIEW
City of Fort Collins
VIGNETTE STUDIOS
144 N MASON ST #2
FORT COLLINS, CO 80524
Date: 01 /19/2007
Staff has reviewed your submittal for WATERS EDGE AT RICHARD'S LAKE PDP - TYPE II,
and we offer the following comments:
ISSUES:
Department: Engineering Issue Contact: Susan Joy
Topic: Before Hearing
Number: 138 Created: 7/11 /2006
[12/26/06]
[7/11/06] In order to go to hearing, please address all "Before Hearing" comments but
basically what I need is the Morn ingstar/Turn berry intersection design showing the reworked
median with the striping called out and dimensioned, an interim striping sheet for Turnberry
showing the existing row, proposed edge of pavement, burrow ditch(?) on the Lind side and
the taper lengths called out to the north so we can see if offsite row is needed, and the left
turn at Douglas design with the taper lengths called out and the row shown (offsite row
needed?). We can leave the retaining wall cross section to Final Compliance if all agree
that it may need to be moved back into the site to avoid offsite grading or that offsite
easements may be required. I'm not going to return any redlines since we're going to work
out the important issues informally. All other comments are Final Compliance comments
and do not apply at this time.
Topic: General
Number: 21 Created: 5/8/2006
[12/26/06]
[7/4/06] Repeat. Final Compliance item with the understanding that we'll have to work
through any new issues at that time.
[5/8/06] All sheets, all plan sets, need to show all existing features within 150' of the project
boundaries so we can see how you're tying in and that all separation distances, street
alignments, etc, are being provided.
Number: 42 Created: 5/9/2006
[12/26/06]
[7/4/06] Repeat. Final Compliance. The developer has two choices for the street stub's
existing row. First choice is to research who would receive the row (neighbor to north? Or
the other site's HOA?) and then work out an access easement to connect your sidewalk
through there OR leave the row as is and then agree to maintain the area with this
development's HOA. If this is the option you would prefer, then the sidewalk could be
repositioned away from the lot to the south and the area could be landscaped as more of an
entry feature to your development.
[5/9/06] Need to show the existing rights of way and what you are planning to have vacated.
Will need legals and exhibits for each proposed vacation along with an $800 filing fee for
each vacation. Larimer County Filing Fees also apply but those will be determined at a later
time.
Number: 104
Created: 7/4/2006
Page 1